Columbia Gas v. R.S v. Inc., Unpublished Decision (12-29-2006)

2006 Ohio 7064
CourtOhio Court of Appeals
DecidedDecember 29, 2006
DocketNo. 05-JE-29.
StatusUnpublished
Cited by2 cases

This text of 2006 Ohio 7064 (Columbia Gas v. R.S v. Inc., Unpublished Decision (12-29-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas v. R.S v. Inc., Unpublished Decision (12-29-2006), 2006 Ohio 7064 (Ohio Ct. App. 2006).

Opinions

OPINION
{¶ 1} Plaintiff-appellant, Columbia Gas of Ohio, Inc., appeals from a jury verdict in the Jefferson County Common Pleas Court in favor of defendants-appellees, RSV, Inc., RSV Trucking, Inc., and Robert S. Vukelic, on appellant's claims of trespass and negligence.

{¶ 2} On April 2, 1993, Paul and Virginia Hatcher granted appellant a general easement over approximately 25 acres of land. The Hatchers had used part of their land as a landfill. The easement granted appellant the right to operate, maintain, and repair a natural gas pipeline running through the land without restriction or limitation. The gas pipeline was a high-pressure line which served as a major feed to customers in the Steubenville area.

{¶ 3} In 1994, the Hatchers sold their land to Pine Hollow C DD Inc. (Pine Hollow), a corporation controlled by Vukelic. Pine Hollow used the land to operate a landfill business for some time. The landfill business subsequently operated for several years under another corporation controlled by Vukelic, known as RSV Trucking, Inc.

{¶ 4} In 2001, the Environmental Protection Agency (EPA) required appellees to construct a water diversion channel to direct storm water away from the landfill site. Appellees retained Jeffrey Oinonen, an engineer, to construct a 60-inch storm water pipeline to divert water from the site. During the construction process, Oinonen encountered 30 feet of solid rock in the bed where the pipeline was to be installed. Therefore, blasting was required to remove the rock in order to properly install the pipeline. However, Oinonen was concerned because the excavating was to occur underneath the gas pipeline. Oinonen notified appellant of the situation.

{¶ 5} Appellant had concerns regarding the blasting around the gas pipeline. At a meeting held September 11, 2001, appellant, the EPA, and the Public Utilities Commission concluded that the pipeline had to be relocated. The EPA instructed that no blasting was to occur until the pipeline was relocated. The EPA further instructed appellant that the pipeline needed to be relocated by the end of 2001, so that appellees could install the water diversion channel in a timely manner.

{¶ 6} After considering several options for the location of the new pipeline, appellant decided to relocate the pipeline south along State Route 213, around the southern portion of the landfill, and north up Backbone Ridge Road. The relocation project commenced on October 22, 2001, and was completed on December 19, 2001. According to appellant, the total cost of the relocation was $347,763.92.

{¶ 7} In early December 2001, a landslide occurred along Backbone Ridge Road. Appellant was concerned about the safety of the gas pipeline, and continually monitored it to ensure that it was not affected by the slippage along Backbone Ridge Road. The road eventually began to slip in close proximity to the gas pipeline. Therefore, appellant determined that due to the worsening conditions, the portion of the gas pipeline along Backbone Ridge Road had to be relocated. Appellant relocated this portion of the gas pipeline along State Route 7. This second relocation project along State Route 7 commenced in November 2003 and was completed in January 2004. The total cost of the second relocation was $800,228.

{¶ 8} In the meantime, on December 16, 2002, appellant filed a complaint against appellees asserting trespass and negligence. Appellant asserted that appellees intruded upon its right-of-way causing it to expend money to relocate its gas line.

{¶ 9} The case was heard before a jury in March 2005. In a majority decision, six out of eight jurors returned a verdict in favor of appellees. Appellant moved for a judgment notwithstanding the verdict or, in the alternative, for a new trial. After a hearing, the court denied both of appellant's motions. Appellant filed this timely appeal on July 15, 2005.

{¶ 10} Appellant asserts six assignments of error, the first of which states:

{¶ 11} "THE JUDGMENT IS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE."

{¶ 12} A judgment supported by some competent, credible evidence going to all the material elements of the case must not be reversed as being against the manifest weight of the evidence. Willett v. Felger (Mar. 29, 1999), 7th Dist. No. 96CP-40; Gerijo, Inc. v. Fairfield (1994),70 Ohio St.3d 223, 226, 638 N.E.2d 533. Furthermore, in considering whether a judgment is against the manifest weight of the evidence, it is important that this court be guided by the presumption that the findings of the trier of fact are correct. Seasons Coal Co., Inc. v. Cleveland (1984),10 Ohio St.3d 77, 80, 461 N.E.2d 1273. If the evidence is susceptible to more than one interpretation, we must construe the evidence consistently with the trial court's judgment. Gerijo, 70 Ohio St.3d at 226.

{¶ 13} Appellant asserted two claims, trespass and negligence. To prevail on a claim of trespass, the plaintiff must prove: "(1) an unauthorized intentional act, and (2) entry upon land in the possession of another." Brown v. Scioto Cty. Bd. of Commrs. (1993),87 Ohio App.3d 704, 716, 622 N.E.2d 1153. A negligence claim requires the plaintiff to prove: (1) duty; (2) breach of duty; (3) causation; and (4) damages.Anderson v. St. Francis-St. George Hosp., Inc. (1996), 77 Ohio St.3d 82,84, 671 N.E.2d 225.

{¶ 14} Appellant claims that the jury verdict is against the manifest weight of the evidence. First, appellant claims that the evidence demonstrated that appellees were liable for the relocation of the gas pipeline.

{¶ 15} Appellant's easement states, in part:

{¶ 16} "The Grantors warrant that, to the best of their knowledge, the lands encompassed by this easement have not been used as a dump site and contain no substances or materials which if disturbed would cause or threaten to cause impairment to human health or the environment." (Pl. Ex. 9).

{¶ 17} Appellees argued at trial that the land encompassing the easement was being used as a landfill site when the easement was granted, and that the Grantors and appellant knew of this activity. They offered several exhibits to support their position. (See Def. Ex. I, J, and K). Additionally, Christine Maynard, a senior engineer with appellant, and David Webb, a field operations leader for appellant, acknowledged that appellant knew of the landfill in 1993. (Tr. 94, 310). And Vukelic testified that the Hatchers had used their land for dumping before he acquired it. (Tr. 361). Therefore, appellees argued that the easement was breached the day it was signed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Fisher
2020 Ohio 6868 (Ohio Court of Appeals, 2020)
State v. Lamb
2018 Ohio 1405 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 7064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-v-rs-v-inc-unpublished-decision-12-29-2006-ohioctapp-2006.