Columbia Gas Transmission, LLC v. RDFS, LLC

Court of Appeals for the Fourth Circuit·Decided July 29, 2025·No. 24-1387·Published

Opinion

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 24-1387

COLUMBIA GAS TRANSMISSION, LLC, Plaintiff – Appellee,

and

UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION, Third Party Defendant – Appellee, v.

RDFS, LLC, a temporary easement to operate and maintain a natural gas transmission line across 1.46 acres of property in Wetzel County, West Virginia, (Parcel ID No. 2-8-58),

Defendant – Appellant,

and

UNKNOWN PERSONS AND INTERESTED PARTIES, Defendant.

Appeal from the United States District Court for the Northern District of West Virginia at Wheeling. John Preston Bailey, District Judge. (5:23-cv-00364-JPB)

Argued: May 8, 2025 Decided: July 29, 2025

Before WILKINSON, NIEMEYER and BERNER, Circuit Judges.

Affirmed by published opinion. Judge Berner wrote the opinion, in which Judge Wilkinson and Judge Niemeyer joined.

ARGUED: Joy Melina Diaz Llaguno, HOOK & HOOK PLLC, Waynesburg, Pennsylvania, for Appellant. Nicolle Renee Snyder Bagnell, REED SMITH, LLP, Pittsburgh, Pennsylvania. for Appellee. ON BRIEF: Matthew R. Miller, HOOK & HOOK PLLC, Waynesburg, Pennsylvania, for Appellant. Colin E. Wrabley, Emily A. Davis, REED SMITH LLP, Pittsburgh, Pennsylvania, for Appellee.

BERNER, Circuit Judge:

Columbia Gas Transmission operates a natural gas pipeline that runs across a parcel of land owned by RDFS, LLC. Columbia possesses an easement to operate and maintain the pipeline on RDFS’s parcel. After learning that a coal company was planning to mine beneath the parcel, Columbia sought access to the parcel in order to mitigate potential harm to its pipeline. RDFS denied Columbia access to the parcel.

Columbia brought suit and the district court granted a preliminary injunction allowing Columbia to go forward with its mitigation efforts. We agree that Columbia’s easement likely granted it access to the parcel. Accordingly, we affirm the ruling of the district court.

I. Background

Columbia Gas Transmission (Columbia) owns and operates an underground natural gas pipeline that crosses through Wetzel County, West Virginia. The Federal Energy Regulatory Commission granted Columbia a “Blanket Certificate of Public Convenience and Necessity” allowing it to develop and operate the pipeline. RDFS, LLC’s predecessor sold to Columbia’s predecessor an easement for the pipeline to cross RDFS’s parcel in 1969. The easement provides that Columbia has the right to “operate, maintain, replace, and finally remove” the pipeline “through all that certain tract of land” which makes up the parcel. J.A. 20.

In June 2023, a coal mining company informed Columbia of its plans to conduct underground mining beneath RDFS’s parcel. The mining was likely to cause the ground

above the area mined, including the area underneath Columbia’s natural gas pipeline, to subside as much as four feet. Columbia concluded that it needed to unearth the pipeline and perform significant mitigation work to prevent the pipeline from being damaged by the subsidence. In order to complete the mitigation work before the coal mining company began its operations, Columbia would need to start the mitigation project by March 1, 2024. This start date was also necessary to meet the seasonal deadline for tree-clearing to protect the Indiana bat, an endangered species found in West Virgina.

Columbia approached RDFS to discuss the proposed mitigation work. RDFS contended then, as it does now, that the work exceeded the scope of Columbia’s easement. RDFS insisted that Columbia needed to acquire additional access rights to the parcel. Efforts to resolve the dispute reached an impasse.

II. Procedural History

Facing an impending deadline, Columba sued RDFS to gain access to the parcel.

Columbia sought two alternate forms of relief. First, Columbia requested a declaration that the Columbia’s easement permits access to the parcel to carry out work necessary to mitigate damage to the pipeline, and an injunction granting such access. In the alternative, Columbia sought an order condemning a temporary easement on the parcel under the Natural Gas Act of 1938, Pub. L. 75-688, 52 Stat. 821. Columbia promptly moved for a preliminary injunction on the basis that the easement allowed it the necessary access, or, in the alternative, for partial summary judgment to condemn a temporary easement.

The district court first considered Columbia’s motion for a preliminary injunction.

In ruling on a motion for a preliminary injunction, a court must consider four factors that the Supreme Court established in Winter v. Natural Resources Defense Council, Inc., 555 U.S. 7 (2008). The Winter factors are whether: 1) the party seeking the injunction is likely to succeed on the merits; 2) that party will likely suffer irreparable harm in the absence of preliminary relief; 3) the balance of equities weighs in favor of the party seeking the injunction; and 4) granting a preliminary injunction is in the public’s interest. Id. at 20.

Applying the first Winter factor, the district court concluded that Columbia was likely to succeed on the merits because the mitigation work was consistent with maintaining the pipeline, and the easement granted Columbia the right to “operate, maintain, replace, and finally remove” the pipeline on the entire parcel. Regarding the second Winter factor, the district court concluded that Columbia would be irreparably harmed if it was denied access to the parcel because delaying the mitigation efforts could damage the pipeline and lead to serious injury or loss of life. Finally, on the third and fourth Winter factors, the district court found that the balance of the equities and public interest favored Columbia because the mitigation could not only prevent damage to the pipeline, it could also prevent harm to those who rely on the natural gas provided by Columbia.

After the district court granted Columbia’s motion for a preliminary injunction, it next considered Columbia’s motion for partial summary judgment seeking to condemn a temporary easement under the Natural Gas Act. To condemn an easement, Columbia needed to establish: 1) that it holds a certificate of public convenience and necessity; 2) that an easement is necessary to the operation of its pipeline; and 3) that it has been unable

to acquire the necessary property interest from the owner. The district court recognized that the first requirement was met because Columbia possesses a certificate of public convenience granted by the Federal Energy Regulatory Commission. The district court next concluded that the second requirement was met because the mitigation efforts were necessary to operate the pipeline. With regard to the third requirement—that Columbia had “been unable to acquire the necessary property interest from the owner”—the district court noted that the parties had reached impasse in their effort to reach an agreement. The district court thus concluded that Columbia met all three requirements for condemnation under the Natural Gas Act.

III. Analysis

On appeal, RDFS challenges the district court’s grant of the preliminary injunction.

We review a district court’s grant of a preliminary injunction for abuse of discretion. Direx Israel, Ltd. v. Breakthrough Med. Corp., 952 F.2d 802, 814 (4th Cir. 1991). In making this assessment, “we review the district court’s factual findings for clear error and review its legal conclusions de novo.” Centro Tepeyac v. Montgomery Cnty., 722 F.3d 184, 188 (4th Cir. 2013) (en banc) (citation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Columbia Gas Transmission, LLC v. RDFS, LLC, (4th Cir. 2025).

Columbia Gas Transmission, LLC v. RDFS, LLC (Columbia Gas Transmission, LLC v. RDFS, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Messenger v. Anderson
225 U.S. 436 (Supreme Court, 1912)
Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Castro v. United States
540 U.S. 375 (Supreme Court, 2003)
Centro Tepeyac v. Montgomery County
722 F.3d 184 (Fourth Circuit, 2013)
TFWS, Inc. v. Franchot
572 F.3d 186 (Fourth Circuit, 2009)
Kell v. Appalachian Power Co.
289 S.E.2d 450 (West Virginia Supreme Court, 1982)
Lowe v. Guyan Eagle Coals, Inc.
273 S.E.2d 91 (West Virginia Supreme Court, 1980)
United States v. Marlon Flores-Granados
783 F.3d 487 (Fourth Circuit, 2015)
Mary Helen Coal Co. v. Hatfield
83 S.E. 292 (West Virginia Supreme Court, 1914)
American Canoe Ass'n v. Murphy Farms, Inc.
326 F.3d 505 (Fourth Circuit, 2003)
Sejman v. Warner-Lambert Co.
845 F.2d 66 (Fourth Circuit, 1988)