Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission

848 F.2d 250, 270 U.S. App. D.C. 193
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 3, 1988
DocketNo. 87-1260
StatusPublished
Cited by1 cases

This text of 848 F.2d 250 (Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission, 848 F.2d 250, 270 U.S. App. D.C. 193 (D.C. Cir. 1988).

Opinion

Opinion for the Court filed by Circuit Judge SILBERMAN.

SILBERMAN, Circuit Judge:

In this petition for review, Columbia Gas challenges the Federal Energy Regulatory Commission’s (“FERC’s”) denial of its application for an individual section 7(c) certificate to transport natural gas at a selective discount. See 15 U.S.C. § 717f(c) (1982). Although Columbia currently holds a blanket certificate under FERC’s Order No. 436, which explicitly permits selective discounting in return for subjecting a transporter of gas like Columbia to certain competitive safeguards, Columbia nevertheless argues that it is entitled to an exception to the generally recognized rule that selective discounting is not permitted under § 7(c) certificates. We believe FERC’s denial of Columbia’s request was not arbitrary and capricious, accordingly we deny the petition for review of the Commission’s decision.

I.

Columbia’s proposal to carry natural gas into the Baltimore/Washington area at a selective discount arose out of a plan by Consolidated Gas to deliver up to 60,000 decatherms (“Dth”)1 of natural gas per day to two local distribution companies, Washington Gas Light Co. (“WGL”) and Baltimore Gas & Electric Co. (“BG & E”). Consolidated, since its pipelines stopped short of the Baltimore/Washington area, sought FERC’s authority to transport its gas through another pipeline part of the way and then, for the balance of the trip, through new interconnection facilities, which would cost WGL and BG & E $25 million to build. See Consolidated Gas Transmission Corp., 36 F.E.R.C. ¶ 61,273, at 61,660-62, 61,670 (1986). Columbia, asserting it could transport the gas from Consolidated’s pipelines to WGL and BG & E at a cheaper price without construction of an allegedly duplicative facility, intervened in opposition to Consolidated’s application for a certificate of public convenience. The Commission never had to resolve the dispute because all four parties— Consolidated, Columbia, WGL, and BG & E — reached a negotiated settlement: Columbia agreed to carry Consolidated’s gas into Baltimore/Washington at a rate of 8.5 cents/Dth for at least 10 years, a rate so attractive that Consolidated, WGL and BG & E agreed to scuttle the proposed $25 million project.

Columbia, in order to proceed with its proposal, needed legal authority to carry Consolidated’s gas. Columbia ostensibly was faced with two choices. It could either petition FERC for individual certification under section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c) (1982), or operate under [195]*195its blanket section 7(c) certificate previously granted pursuant to FERC’s Order No. 436, 50 Fed.Reg. 42,408 (1985) (codified at scattered sections of 18 C.F.R.) partially reversed and remanded, Associated Gas Distributors v. FERC, 824 F.2d 981 (D.C. Cir.1987) (“AGD"), cert. denied sub nom., Southern Cal. Gas Co. v. FERC, — U.S. -, 108 S.Ct. 1469, 99 L.Ed.2d 698 (1988). When the relative advantages of each course of action are explained, it becomes quite understandable why Columbia chose to seek an individual certificate and also why FERC ultimately refused.

Traditionally, FERC has authorized pipelines to transport gas by issuing a § 7(c) certificate of public convenience and necessity for each individual transaction. In this fashion, FERC has monitored significant actions by interstate pipelines, generally requiring that the rate charged reflect the full costs attributable to the transaction. FERC’s typical concern is that a pipeline will charge a lower rate, or discount to one customer in its system and make up the difference vis-a-vis another. Because rates are established at the outset of the project and can be adjusted midstream if the pipeline finds it is not recovering its costs, FERC has been, over the years, especially attentive to the possibility that discounting would lead to discriminatory pricing. See, e.g., Transcontinental Gas Pipe Line Corp., 28 F.P.C. 979, 983 (1962). Under individual section 7(c) authority, pipelines historically functioned as merchants, who purchased natural gas from third parties and then transported it for resale. But the Commission found that the interstate pipeline network was not running efficiently because interstate pipelines retained market power in the transportation of gas and generally declined to transport gas in competition with their own sales, thus discriminating in the transportation of gas to the detriment of consumers. See AGD, 824 F.2d at 993-96.

FERC responded with Order No. 436, designed to meet both these concerns and the growing need for increased flexibility so pipelines could take advantage of rapidly developing business opportunities without the regulatory delay and constraints arising out of individual § 7(c) certificates. Id. at 996. FERC’s Order 436 was essentially an effort to facilitate the “unbundling” of pipeline services and product by encouraging pipelines who previously acted only as gas merchants to act also as pure transporters of third-party gas, even though they would thereby compete with their own products. AGD, 824 F.2d at 994. In return for the heightened flexibility offered to a holder of a blanket certificate, which authorizes transportation services generically and the right to discount selectively, id. at 996, FERC imposed several obligations on the transporter. The most important is the requirement that the pipeline operate under a rate system that is designed to maximize the nondiscriminatory transportation of gas as well as hold the pipeline’s shareholders accountable for business decisions, like selective discounts, in order to ensure reasoned behavior from the pipeline. See generally Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, [1982-1985 Transfer Binder, Regulations Preambles] Fed. Energy Reg. Comm’n Rep. (CCH) 1130,665, at 31,-533-49 (Oct. 9, 1985) (“Preamble”).

FERC thus allocated to the pipelines the risk of the success or failure of their market participation — not always the case before Order 436. FERC’s key innovation in Order 436 was to shift the focus from setting transportation rates based on what the pipeline had carried in the past to projections of what the pipeline would carry in the future. FERC thus sets a one-part volumetric rate based on a projection of the volume of gas that can reasonably be expected to be transported through the pipeline’s system. See 18 C.F.R. § 284.7(d)(2). Then, the pipeline must estimate its fully allocated cost of service for transporting this volume. Id. § 284.7(d)(2)-(4); Preamble at 31,535. With these two numbers, FERC establishes what the pipeline’s fully based cost per unit of volume will be. For example, if a pipeline intends to carry 1,000 Dth through its pipeline, and total costs will be $500, then the rate will be simply $0.50 per Dth. This rate, also known as the “maximum,” will achieve full recovery [196]*196of costs for a transporter if it meets its projected volume. Pipelines, like Columbia, are also permitted to charge less than the “maximum” under Order 436 as long as the rate falls within a previously approved rate band.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
848 F.2d 250, 270 U.S. App. D.C. 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-transmission-corp-v-federal-energy-regulatory-commission-cadc-1988.