Columbia Gas of PA, Inc. v. Menallen Twp. & PA PUC

CourtCommonwealth Court of Pennsylvania
DecidedJanuary 2, 2026
Docket530 M.D. 2022
StatusPublished

This text of Columbia Gas of PA, Inc. v. Menallen Twp. & PA PUC (Columbia Gas of PA, Inc. v. Menallen Twp. & PA PUC) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas of PA, Inc. v. Menallen Twp. & PA PUC, (Pa. Ct. App. 2026).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Columbia Gas of : Pennsylvania, Inc., : Petitioner : : v. : No. 530 M.D. 2022 : Menallen Township and : Pennsylvania Public : Utility Commission, : Respondents : Argued: December 8, 2025

BEFORE: HONORABLE PATRICIA A. McCULLOUGH, Judge HONORABLE STACY WALLACE, Judge HONORABLE MATTHEW S. WOLF, Judge

OPINION BY JUDGE WOLF FILED: January 2, 2026

In this original jurisdiction action, Columbia Gas of Pennsylvania, Inc. (Columbia) challenges as preempted and ultra vires an ordinance of Menallen Township (Township) regulating utility development. Now before the Court are Columbia’s and the Township’s cross-applications for summary relief. We conclude that a portion of the relief Columbia seeks is not ripe for review, and we dismiss Counts III and IV of Columbia’s Amended Petition for Review (Petition) on that basis. However, we also conclude that a portion of the Township’s ordinance is preempted by state law, and we thus grant summary relief for Columbia on Counts I and II of the Petition. I. BACKGROUND The underlying facts are generally undisputed. Columbia is a public utility that sells and distributes natural gas to about 444,000 retail customers in Pennsylvania. It is regulated by the Pennsylvania Public Utility Commission (PUC), including under the Public Utility Code.1 The PUC has approved a certificate of public convenience and a tariff for Columbia. As part of its utility service, Columbia builds, maintains, and updates a high-pressure gas pipeline network on either private or public rights-of-way. Some of that network is located in the Township. From 2016 to 2022, Columbia performed three infrastructure- expansion projects in the Township, for which it installed about 1,700 linear feet of pipe in public rights-of-way. For those projects, Columbia paid $14,259 in fees under the Township’s Ordinance 178, which is the Ordinance Columbia challenges in this action. At the time it filed the Petition, Columbia had four additional projects planned in the Township that require adding or replacing approximately 7,000 feet of pipe in the Township, as follows:

(a) 148 Stoney Point, a new facilities project requiring the installation of 410 feet of pipe;

(b) Kaider Road, a pipeline replacement project requiring the installation of 5,200 feet of pipe;

(c) Anthram Street, a pipeline replacement project requiring the installation of 760 feet of pipe; and

(d) Duck Hollow Road, a pipeline replacement project requiring the installation of 300 feet of pipe.

Pet. ¶ 29. Columbia believes the last three projects, for replacement of existing pipeline, are required by the Public Utility Code and the PUC’s regulations. On

1 66 Pa.C.S. §§ 101-3316.

2 March 10, 2023, Columbia paid, under protest, $42,542.08 in Ordinance 178 fees so that it could begin the three replacement projects. A. Ordinance The Township enacted Ordinance 178 in 1997. The Ordinance generally regulates excavation or “opening” of public streets and requires a permit for any such work. Here, Columbia challenges several sections of Ordinance 178.2

2 The following sections of Ordinance 178 are at issue in this case:

Section 13. Restrictions Regarding Trees and Shrubbery. The permission herein granted does not confer upon the permittee or its contractors the right to cut, remove or destroy trees or shrubbery within the legal right of way except under specifications, regulations and conditions as the Township of Menallen may from time to time prescribe.

Section 14. Work Necessitating Opening or Excavation to be Done Prior to Street Improvement and Not Until Five Years Thereafter; Exception. The Board of Supervisors of the Township of Menallen shall give timely notice in person or by publication to all persons owning property abutting on any street within the Township of Menallen about to be paved or improved, and to all public utility companies operating in the Township of Menallen, and all such persons and utility companies shall make all water, gas, electric, or sewer connections, as well as any repairs thereto which would necessitate excavation of the said street within thirty (30) days from the giving of such notice, unless such time is extended in writing for cause shown by the Board of Supervisors of the Township of Menallen. New paving shall not be opened or excavated for a period of five years after the completion thereof, except in case of emergency, the existence of which emergency and necessity for the opening or excavating of such paving to be determined by the Board of Supervisors of the Township of Menallen. If it is sought to excavate upon or open a roadway within five (5) years after the completion of the paving, applicant shall make written application to the Township of Menallen, and a permit for such opening shall be issued only after express approval of the Board of Supervisors of the Township of Menallen.

Section 15. Permittee Responsibility for Future Relocation of work. If at any time in the future the roadway is widened, reconstructed or the alignment or grades are changed, the permittee further agrees to change or relocate all or any part of the structures covered by this permit which interfere with the improvement of the (Footnote continued on next page…)

3 Sections 13 through 16 limit the locations where excavation can occur, such as by limiting removal of trees or shrubs, prohibiting excavation of recent pavement, and regulating the depths of the facilities (Location/Relocation Provisions). Section 20 sets the following fees: a permit fee of $150 (Application Fee); inspection and supervision fees of $18-25 per hour for the Township’s engineer to supervise the

roadway at its own cost and expense.

Section 16. Conditions of Laying and Extending Utility Lines. No new water, sewer, steam or gas main, electric, telephone or other utility line shall hereafter be laid or constructed, and no such existing main or line shall be extended, in any of the streets of the Township of Menallen until the plan therefor shall have been first filed with the Board of Supervisors of the Township of Menallen and such plan and the exact location of such main or line, approved by them. The Board of Supervisors of the Township of Menallen shall not approve the locating of any such main or line at a depth less than thirty ( 30 ) inches from the surface of the street unless they shall be convinced that locating the same at a depth of more than thirty ( 30) inches from the surface is impossible or impractical.

....

Section 20. Schedule of Permit and Other Fees. (1) Permit fees to accompany application: $ 150.00; (2) Inspection and supervision fee for Menallen Township Engineer.: $ 18.00 to $ 25.00 per hour, as determined by the Menallen Township Engineer; (3) Fee schedule per square foot for opening or excavation in an approximate size less than 50 square feet: $3.67 per square foot; (4) Fee schedule for opening or excavations per square foot, for each square foot opened or excavated in excess of 50 square feet: $ 3.67 per square foot in excess of 50 square feet; (5) Fee schedule for bond required: $ 25.00 per linear foot.

Section 21. Penalties. Any person, firm or corporation who shall violate any provision of this ordinance, shall, upon being found liable therefor in a civil enforcement proceeding, pay a civil fine set by the Board of Supervisors of the Township of Menallen of not more than $ 600.00 plus costs and reasonable attorneys , fees. Every day that a violation of this ordinance continues shall constitute a separate offense or occurrence. Pet. Ex. 2.

4 work, plus $3.67 per square foot of opening/excavation (Inspection Fees); and a bond amount of $25 per linear foot.3 Section 21 imposes a civil penalty of $600 per day on any entity that violates Ordinance 178.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warth v. Seldin
422 U.S. 490 (Supreme Court, 1975)
Township of Derry v. Pennsylvania Department of Labor & Industry
932 A.2d 56 (Supreme Court of Pennsylvania, 2007)
Town of McCandless v. McCandless Police Officers Ass'n
901 A.2d 991 (Supreme Court of Pennsylvania, 2006)
Ronald H. Clark, Inc. v. Township of Hamilton
562 A.2d 965 (Commonwealth Court of Pennsylvania, 1989)
Hoffman Mining Co. v. Zoning Hearing Board
32 A.3d 587 (Supreme Court of Pennsylvania, 2011)
Governor's Office v. Office of Open Records, Aplt.
98 A.3d 1223 (Supreme Court of Pennsylvania, 2014)
Phantom Fireworks Showrooms, LLC v. Tom Wolf, Governor of the Comwlth of PA
198 A.3d 1205 (Commonwealth Court of Pennsylvania, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Columbia Gas of PA, Inc. v. Menallen Twp. & PA PUC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-of-pa-inc-v-menallen-twp-pa-puc-pacommwct-2026.