Columbia Casualty Co. v. Tibma

63 F.2d 538, 1933 U.S. App. LEXIS 3484
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 28, 1933
DocketNo. 4842
StatusPublished
Cited by3 cases

This text of 63 F.2d 538 (Columbia Casualty Co. v. Tibma) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Casualty Co. v. Tibma, 63 F.2d 538, 1933 U.S. App. LEXIS 3484 (7th Cir. 1933).

Opinion

SPARKS, Circuit Judge.

Appellant’s contention is based on its assumption that there is no substantial evidence in the record to support any one or more of appellee’s affirmative answers, and that by the uneontradieted evidence it was entitled to a verdict and judgment for $12,725.87 and interest on $11,763.07 of that amount from the time it was expended.

The verdict of the jury determined in appellant’s favor the issues raised by the second, third, and sixth paragraphs of the answer, and with those wo are not concerned. It may be conceded that the charge of fraud as contained in the ñfth paragraph of answer is unsupported by any evidence, hence tho sole question for our consideration is whether there is substantial evidence in the record to support the allegations of the fourth paragraph of answer. A determination of this question necessitates a statement of the facts.

On April 21, 1925, the Highway Improvement Company, hereinafter referred to as principal contractor, entered into a contract with the State Highway Commission of Indiana for the construction of a liard-surfaco road in St. Joseph County, Indiana, which was to bo completed by November 15, 1925. On May 16, 1925 tho principal contractor entered into a subcontract with one L. V. Bareus, hereinafter referred to as Bareus, whereby it was agreed that Bareus would do tho grading, ditching, and shouldering of the road at the rate of forty-five cents per cubic yard for the yardage removed. It was further agreed that Bareus should furnish to the principal contractor a surety bond in the sum of $20,000, guaranteeing the completion of the work in accordance with the contract entered into by the principal contractor and the Highway Commission. That bond was given by Bareus and was signed by appellant as surety. It provided that appellant should indemnify the prineix>al contractor against any loss or damage by reason of failure of Bareus to perform his subcontract, and, in tho event that Bareus should fail to comply with tho contract to such an extent that it should be forfeited, axipellant should have the right to assume and perform the contract or sublet it, and to be subrogated to the rights of Bareus against the principal contractor. As a condition to the execution of that bond, however, appellant demanded an indemnitor. Thereupon on June 18, 1925, appellee executed to appellant the indemnity agreement now in suit, which, so' far as material here, obligated appellee to indemnify appellant against all loss and liability by reason of appellant’s execution of the bond to the principal contractor on behalf of the subcontractor.

Bareus entered upon the grading work, and by O’ctober 1,1925 had completed 39,060 yards of the 45,934 yards covered by the principal contract, and of tho 9.541 miles of shoulder work contemplated therein he had completed all hut about four miles. The total allowance for shoulder work under the piine¡x>al contract was $3,022.14, and under tho eighty per cent, clause of the subcontract there had been paid to Bareus on his contract, or to others upon his request, the sum of $13,884.54.

Some time prior to October 1, 1925, the principal contractor notified appellant by letter that Bareus’ maimer of work was not satisfactory. On October 1, 1925, appellant wrote appellee that Bareus was not doing his work satisfactorily and that there might he an obligation on the bond; that they expected him to save them harmless and to get on the job and see that the work was taken care of. Shortly thereafter appellant’s agents inspected the work for tho first time and reported to appellee’s attorney that Bareus was getting along as well as could he expected; that he had men and equipment on the job and could carry on; that they would watch the situation; and that they were sure that the contract would work itself out without liability to any one. Appellee’s attorney at that time informed appellant’s agents that Bareus was not well qualified to handle the job, and that it would be necessary to watch him.

Erom that timo on the negotiations were carried on between the parties by appellant’s agents and appellee’s attorneys and nothing further was done by appellant until the latter part of April, 1926. On April 22, 1926, appellee’s attorney ascertained that the x’rineipal contractor had done a consider alile amount of grading work during the winter and had charged it to Bareus at exorbitant prices, and was threatening to take over the entire subcontract. These facts were immediately communicated by said attorney to appellant at its home office in New York [540]*540by a letter, in which the following statements were made:

“We further found by perusal of the correspondence of the Highways Improvement Company, that your Chicago office from time to time since last fall, has been informed in detail of this situation, and under date of January 6th was- sent a statement showing the exact status of the matter. None of this information was passed to Mr. Tibma, and apparently your company has taken no steps whatever to minimize liability on your bond.

“We are at a loss to understand the apparent lack of interest of your Chicago office. If it is your position that you may rely on Tibma, guarantor, and take ho action whatever on this job, be informed now that Tibma will deny any responsibility.

“Oar investigation discloses that Bareus has little if any equipment left, he has no money to employ workmen and has exhausted his credit.' The writer had quite a talk with the State Highway engineer on the job yesterday and he appears inclined to be very reasonable in the matter of this grade.

“The time has eotaie to put some responsible man on this job and finish it, and it would seem that that responsibility in the first instance rests* on the bonding company. * * * 'We suggest that you have some responsible representative on the ground at once and if you show any spirit of co-operation we feel sure that Mr. Tibma will be glad to work with you.”

Shortly thereafter appellant insisted that appellee take over and complete the contract. This the latter refused to do, and he gave as his reason therefor that he was not a party to the subcontract or the bond, and had no 'rights on the job. He refused to admit or assume any liability, but insisted that appellant do everything possible to prevent further loss, and agreed to co-operate to that end. Thereafter appellant entered into a .contract with a local contractor to take over and complete the work on a cost plus basis. The signing of that contract by appellant was delayed several, days by an effort of appellant to secure ah admission of liability on the part of appellee. The question of appellee’s liability, however, was left open, and both parties joined in the effort to secure completion of the work as cheaply as possible under the then existing conditions. Subsequently appellant paid the local contractor $11,763.07. A very large part of the work done by him consisted in rebuilding berms and shoulders which had washed out during the winter and in cleaning out ditches which had filled in. About seven miles of shoulder work had to be done over.

After the work was completed and accepted, appellant demanded payment from appellee of the full amount of its cost. This was refused on the ground that no settlement had been made with the principal contractor for the work done by Bareus, and without such settlement the amount of liability, if any, could not be determined. Appellant thereupon demanded that appellee institute and prosecute a suit for that purpose, which demand was refused on the ground that his status as indemnitor gave him no standing in court for that purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skousen v. W.C. Olsen Investment Co.
717 P.2d 930 (Court of Appeals of Arizona, 1986)
American Surety Co. of New York v. Franciscus
127 F.2d 810 (Eighth Circuit, 1942)
Dyal v. Wimbish
124 F.2d 464 (Fifth Circuit, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
63 F.2d 538, 1933 U.S. App. LEXIS 3484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-casualty-co-v-tibma-ca7-1933.