Colt Industries, Inc. v. United States

11 Cl. Ct. 140, 25 ERC 1283, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20962, 25 ERC (BNA) 1283, 58 A.F.T.R.2d (RIA) 6057, 1986 U.S. Claims LEXIS 780
CourtUnited States Court of Claims
DecidedOctober 23, 1986
DocketNo. 614-84T
StatusPublished
Cited by4 cases

This text of 11 Cl. Ct. 140 (Colt Industries, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colt Industries, Inc. v. United States, 11 Cl. Ct. 140, 25 ERC 1283, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20962, 25 ERC (BNA) 1283, 58 A.F.T.R.2d (RIA) 6057, 1986 U.S. Claims LEXIS 780 (cc 1986).

Opinion

MEMORANDUM OF DECISION

HARKINS, Judge:

This tax refund case is before the court on cross-motions for partial summary judgment. Oral argument was heard on July 16, 1986. There is no dispute as to any material fact and disposition by summary judgment of Count I of the complaint is appropriate.

The Internal Revenue Service (IRS) disallowed, under section 162(f) of the Internal Revenue Code of 1954, as amended, deductions taken by plaintiff for payments that total $1.6 million to the Clean Air Fund and to the Clean Water Fund of the Commonwealth of Pennsylvania. The payments were made pursuant to a consent decree that directed payment of civil penalties assessed pursuant to section 309(d) of the Federal Water Pollution Prevention and Control Act (Clean Water Act), 33 U.S.C. § 1319(d) (1982) and section 113(b) of the Clean Air Act, 42 U.S.C. § 7413(b) (1982). The sole issue is whether the payments constitute “a fine or similar penalty paid to [141]*141a government for the violation of any law” for which a deduction as an ordinary or a trade or business expense is barred by I.R.C. § 162(f). For the reasons that follow, defendant’s motion for partial summary judgment must be allowed.

Plaintiff, Colt Industries, Inc., in 1979, through its affiliated subsidiary, Crucible, Inc. (Crucible) manufactured basic steel and fabricated steel products at mills and plants in Midland, Pennsylvania. Crucible’s operations were subject to regulation under several environmental protection laws and regulations, including the Federal Clean Air Act and the Federal Clean Water Act, the Pennsylvania State Implementation Plan (SIP) and the rules and regulations of the Pennsylvania Department of Environmental Resources (DER regulations), Title 25, Part I, Subpart C, Article III, Air Resources.

On May 31, 1972, the Administrator of the United States Environmental Protection Agency (EPA), pursuant to section 110 of the Clean Air Act, 42 U.S.C. § 7410, promulgated and approved major portions of the SIP for the attainment and maintenance of the national primary ambient air quality standards in Midland, Pennsylvania and other areas. The SIP included provisions of the DER that contained air pollutant emission limitations applicable to Crucible’s Midland works.

On December 17, 1974, EPA Region III issued National Pollutant Discharge Elimination Permit No. PA0005754 to Crucible pursuant to section 402 of the Clean Water Act, 33 U.S.C. § 1342. The permit authorized discharges of stated quantities of certain pollutants into the Ohio River.

In 1974, the EPA conducted inspections at Crucible’s Midland works. In July and September 1976, EPA issued Notices of Violation to Crucible pursuant to section 113(a)(1) of the Clean Air Act, 42 U.S.C. § 7413(a)(1). In March 1977, more than 30 days after Crucible received the violation notices, EPA conducted another inspection and found that Crucible continued in violation of the requirements of the notices.

On August 7, 1977, certain Clean Air Act amendments became effective. Pub.L. No. 95-95, 91 Stat. 685 (1977). These amendments provide that violations of the SIP and DER regulations would render the violator liable to assessment of civil penalties of not more than $25,000 per day of violation. 42 U.S.C. § 7413(b). At this time, Crucible had not corrected the conditions in the violation notices.

On April 3, 1978, EPA advised Crucible that a compliance plan it had proposed regarding the 1976 violations was rejected because it did not provide for compliance with all applicable regulations by the statutory date. EPA indicated that it was willing to explore the possibility of arriving at an expeditious and mutually agreeable plan, and stated it was EPA policy to assess a civil penalty in any consent decree which at a minimum would be equal to the economic benefit which had accrued to the company since August 7, 1977.

On May 19, 1978, in connection with discussions with DER regarding compliance with Pennsylvania environmental controls, Crucible filed an application with the DER for a permit to construct an electric arc furnace shop. This application was approved by the DER on July 19, 1978.

On June 16, 1978, EPA requested the Justice Department to institute a civil action against Crucible seeking an injunction requiring Crucible to comply with emission regulations. EPA also recommended that civil penalties be sought in the amount of $25,000 per day of violation of the Clean Air Act. EPA further recommended that civil penalties be assessed for violations of permissible discharge levels allowed in the 1974 permit. Violations of the permit, under Clean Water Act § 301(a), made Crucible liable for civil penalties of up to $10,000 per day.

Negotiations with the DER resulted in a consent decree (DER decree), dated October 20, 1978, pursuant to which Crucible was to close the blast furnace and coke plant at Midland and purchase and install an electric arc furnace shop. The DER decree scheduled the construction of the [142]*142electric arc furnace facility and the shut down of the blast furnace to be done by December 31, 1982. The EPA did not participate in the negotiations with DER which produced the DER decree.

On December 7, 1978, EPA and Crucible met to discuss a proposed compliance plan and the settlement of the potential lawsuit EPA had recommended be brought against Crucible. Crucible, in January 1979, provided EPA with information to assist in the analysis of potential civil penalties under EPA’s Civil Penalty Policy, dated April 11, 1978. Subsequently, EPA proposed several civil penalty amounts.

In February 1979, Crucible had offered $1.6 million cash, plus $400,000 of the amount representing economic benefits to be paid in escrow, with an appropriate percentage to be refunded in the event of compliance before March 1981. Crucible’s offer was subject to final determination by EPA’s penalty panel. On February 27, 1979, EPA completed a recalculation of its analysis of an appropriate civil penalty. The elements of the civil penalty figure, as recalculated, were summarized by EPA as follows (dollar amounts in millions):

Was Is
Economic Benefit $5.0 $4.86
Environmental Harm $ .577 $ .577
Recalcitrance $ .250 $ .150
% Chance of Winning 65% 45%
Gross Penalty $3.80 $2.50
Credits $ .561 $ .801
Settlement Figure $3.20 $1.7

The penalty panel concluded that EPA could accept a $1.6 million civil penalty as consistent with the Penalty Policy Manual if there were compliance by July 1979 with certain water milestones.

Overall, negotiations for the EPA consent decree were conducted from December 1978 to April 1979.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 Cl. Ct. 140, 25 ERC 1283, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20962, 25 ERC (BNA) 1283, 58 A.F.T.R.2d (RIA) 6057, 1986 U.S. Claims LEXIS 780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colt-industries-inc-v-united-states-cc-1986.