Colonial Contractors v. Burd Building Co., No. 509144 (Nov. 2, 1993)

1993 Conn. Super. Ct. 9353
CourtConnecticut Superior Court
DecidedNovember 2, 1993
DocketNo. 509144
StatusUnpublished

This text of 1993 Conn. Super. Ct. 9353 (Colonial Contractors v. Burd Building Co., No. 509144 (Nov. 2, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colonial Contractors v. Burd Building Co., No. 509144 (Nov. 2, 1993), 1993 Conn. Super. Ct. 9353 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This civil action first came to this court by writ, summons and complaint dated November 15, 1988 and returnable January 10, 1989, sounding in two counts and claiming damages, punitive damages, interest and attorney's fees based on a construction contract. On November 15, 1988, the plaintiff applied for a prejudgment remedy which the court, Walsh, J., granted on December 6, 1988, as of record more fully appears. The defendant appeared by counsel which appearance was filed on December 22, 1988.

On May 15, 1989, by agreement of counsel of record, the prejudgment attachment of November 15, 1988 was modified and the modified sum was placed in a joint interest bearing account, approved by Hendel, J.

On May 1, 1989, the defendant filed an answer to the complaint dated April 27, 1989, denying all the allegations CT Page 9354 contained in both counts of the complaint. On May 1, 1989, the defendant filed a counterclaim against the plaintiff dated April 27, 1989 containing two counts seeking damages.

On July 3, 1989, the defendant filed an amended answer to plaintiff's complaint dated June 30, 1989, in which answer the defendant admitted paragraph one of the complaint but denied all other allegations. On November 2, 1990, the plaintiff filed an answer to the counterclaim dated October 31, 1990. On October 18, 1991 and on September 18, 1991, withdrawals were filed as to certain garnishees.

On March 8, 1993, the defendant filed two special defenses to the plaintiff's complaint.

On March 12, 1993, the plaintiff filed a reply to the defendant's special defenses denying the same and the pleadings were closed.

The case came on for hearing before the court commencing on September 15, 1993 and continued thereafter on September 22, 23, 28 and 29, 1993, when the testimony was completed.

On September 29, 1993, upon the conclusion of the testimony, the plaintiff, with leave of the court, filed an amended complaint so as to conform to the proof.

The court, having heard the parties, makes the following findings of fact:

Winfred B. Valentine was the president, chief operating officer, owner and chief stockholder of the plaintiff corporation Colonial Contractors, Inc. Valentine had some engineering background, had been in construction for many years, had been employed by B.N. Baird Construction Co., Farrel Mills in Florida, Metcalfe and Eddy of Boston, Rust Engineering Co., Bechtel Corp. and Stone and Webster on various projects. Valentine had worked at various locations and sites in Florida, Greenwich, Connecticut, Anchorage, Alaska, Puerto Rico, and Brownsville, Nebraska. Valentine had testified in a New York court as a mechanical piping expert.

Valentine and representatives of Burd Building Company entered into negotiations in early January 1988 regarding a site CT Page 9355 located in Jewett City known as Slater Village which envisioned Valentine's corporation doing certain site work, engineering, grading, cutting and filling, clearing and grubbing, installation of storm drains, flares, wing walls, rip rap, a sanitary system, erosion control and maintenance site supervision and mobilization which was finalized in a letter to Valentine dated January 25, 1988 with attachments. See Plaintiff's Exhibit A. Letter from Defendant to plaintiff dated January 25, 1988, Slater Village job. The work itemized in Plaintiff's Exhibit A was to be performed for and in consideration of the sum of $733,225 to be paid by the defendant to the plaintiff in accordance with an agreed billing format for a completed job. Time was of the essence and this project was on a fast track basis. See Plaintiff's Exhibit B and Exhibit N. Prior negotiations between the plaintiff and defendant resulted in Plaintiff's Exhibits A and B (plaintiff's letter of January 28, 1988) which can be considered as the offer of the contract and the acceptance of the same and a meeting of the minds. Certain clarifying data was set forth in Plaintiff's Exhibit C concerning the contract. Valentine was provided with various site development drawings, six sets, see Plaintiff's Exhibit VV. Valentine was engaged in clearing and grubbing the site during March-April 1988.

Certain areas could not be worked on due to wetland designation and possible ancient Indian burial ground until released by proper authority.

Valentine's periodic invoices for March through July 1988 work were paid less retainer. Plaintiff's Exhibit WW notwithstanding.

The defendant's project manager was Russell Morris. The defendant's site superintendent was Chuck Lundberg. The defendant's subsequent site superintendent was Mr. Hawes. The plaintiff's site superintendent was Carl Mattocks.

Daily reports were prepared by both of the site superintendents covering weather conditions, work done, remarks and concerns. See Plaintiff's Exhibit U.

Valentine learned on July 29, 1988 that his company was to be replaced. See Defendant's Exhibit 1, statement by Lundberg as to the problems with plaintiff on the site. Valentine engaged in on site work during the period March through July 1988. CT Page 9356

Defendant received complaints that plaintiff was conducting logging operations in an area designated as wetlands and so marked. See Plaintiff's Exhibit D, letter from Roland J. Harris and Associates to Burd Building complaining of plaintiff's activities on the site concerning unauthorized gravel excavation and unauthorized logging by plaintiff in wetlands.

Valentine personally operated heavy equipment on the job site in restricted wetland area. The plaintiff incident to excavating for piping both storm and sanitary and the installation of said piping did not sandbag the work to keep it in place, did not use plumber's plugs to keep out mud and silt, and did not cover the work at the end of each day to protect the same from the elements. The plaintiff, during May, June and July, hired Lynn Corporation on an hourly basis to provide equipment and personnel as needed and to work on the site under plaintiff's direction. Plaintiff's last day on the job site was August 1, 1988.

At the time the plaintiff left the job site, the work called for in the agreement was only partially performed.

The engineering firm for the overall project was Roland J. Harris and Associates.

The duties of defendant's site superintendent Charles Lundberg were to assist the various contractors, clarify drawings and expedite the project. Lundberg was on the site May through August 1988. Lundberg had 40 years experience in the construction trades. Lundberg provided the defendant with daily reports.

During most of the period March through August 1, 1988, plaintiff had no field engineer or surveyor on the site. See Plaintiff's Exhibit Q, letter from defendant to plaintiff indicating lack of experienced manpower, dependable equipment and requirement of a field engineer.

During the initial phase of the work, Valentine frequently appeared on the job site but after the first three or four weeks, his appearance was infrequent and sporadic. Weeks would go by without Valentine being on the job site to direct the grading, fill movement, excavation work and piping installation.

The manpower provided by plaintiff on the job site on CT Page 9357 occasion was adequate but not skilled. Equipment provided by plaintiff for the site work was inadequate, in some cases defective and not operated by skilled operators.

On one occasion, the Ames building being erected on a portion of the subject site was damaged by the unskilled operation of a front end loader operated by one of plaintiff's employees.

A surveyor hired by plaintiff, one Gomer Davis, appeared on the job site twice during the entire job on weekends.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rene Dry Wall Co. v. Strawberry Hill Associates
438 A.2d 774 (Supreme Court of Connecticut, 1980)
F & W Welding Service, Inc. v. ADL Contracting Corp.
587 A.2d 92 (Supreme Court of Connecticut, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 9353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colonial-contractors-v-burd-building-co-no-509144-nov-2-1993-connsuperct-1993.