Colonial Construction Co. v. Sharp Industries, Inc.

421 S.W.2d 551, 1967 Mo. App. LEXIS 624
CourtMissouri Court of Appeals
DecidedOctober 2, 1967
DocketNo. 24653
StatusPublished
Cited by6 cases

This text of 421 S.W.2d 551 (Colonial Construction Co. v. Sharp Industries, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colonial Construction Co. v. Sharp Industries, Inc., 421 S.W.2d 551, 1967 Mo. App. LEXIS 624 (Mo. Ct. App. 1967).

Opinion

MAUGHMER, Commissioner.

This dispute concerns one-half ($8,-614.15) of a “change order” payment made under a rather large United States Government construction contract. The plaintiff prevailed and had the verdict and judgment for the exact amount sued for. The defendant has appealed.

We first must introduce and become acquainted to some extent with the principals that were deeply involved in this controversy and the events out of which it arose. In the spring of 1957, the United States of America, acting by and through the United States Corps of Engineers, was in the process of constructing a radar screen along the Atlantic coastline of the United States and Canada. Bids were about to be taken and a contract let for the construction of ten communication installations known as “Operation Gap Filler” at sites near Labrador and Newfoundland along the Atlantic shoreline of the Dominion of Canada.

The plaintiff, Colonial Construction Co., Ltd., in its petition named as defendants Sharp Industries, Inc., Sharp Bros. Contracting Co. and Don E. Sharp. Sharp Bros. Contracting Co. is and has been for many years a solvent and successful Missouri corporation. Its president and managing officer was at all times Mr. Don E. Sharp. Colonial Construction Co., Ltd., is a corporation duly organized and existing under the laws of Newfoundland. Its general manager, insofar as the present subject matter is concerned, was Mr. Harlo Haagenson. These two organizations determined to make an effort to obtain the Operation Gap Filler contract. It was required that corporate bidders be domiciled in Canada. Management of Sharp Bros. Contracting Co. apparently did not deem it advisible to involve that company directly in the proposed project and so organized Sharp Industries, Inc., primarily and probably solely, for the purpose of functioning on Operation Gap Filler. The bid of this group was accepted and the contract awarded. Again Don E. Sharp was president, but his brother, Raymond D. Sharp, then living in New York City, was made general manager. The rights and obligations of Sharp Industries and Colonial Construction were enumerated in a written Joint Venture Agreement.

The parties also entered into and this case was tried in part under a Stipulation of Facts. We recite certain pertinent parts of that stipulation:

(1) “Plaintiff Colonial Construction Co., Ltd., and defendant Sharp Industries, Inc. duly entered into a joint venture agreement dated May 21, 1957, under the terms of which the parties agreed to act as joint venturers under the name ‘Colonial Construction Company, Ltd., and Sharp Industries, Inc., d/b/a Colonial Construction Co.—Sharp Industries, Inc., a joint venture’; that said joint venture would bid on a construction project known as ‘Operation Gap Filler’, and, if successful, construct said project as joint venturers, pursuant to the terms of said joint venture agreement.”

(2) The joint venture group did bid, was successful, was awarded the contract and started construction. We interpose here to state that the Joint Venture Agreement provided in effect that the parties share equally in expenses and profits. It further provided that Mr. Raymond D. Sharp of New York, brother of Don. E. Sharp, should be employed as general manager of the joint venture and should “receive all payments and disburse all funds”.

More than one year thereafter and for reasons which are not quite clear from the record, but which are not of great importance, Sharp Industries, Inc. on December 24, 1958, agreed in writing with Colonial that it would and it did, assume complete control of the construction project from that date on. This control covered construction, management and carried authority to receive payments and endorse and cash all checks and drafts received from [553]*553the Government. Colonial was paid an agreed cash consideration and all payments thereafter made by the contractor were to belong to Sharp Industries, Inc. except such as might be made for “change orders”, that is, for changes ordered by the Corps of Engineers in modification of the original specifications. Colonial was still to receive one-half of all such “change order” payments. It was stipulated that for the year 1960, only Sharp Industries was authorized to act for the joint venture, including collection and disbursements of checks and monies.

Only one payment is in controversy. It was stipulated that on or about January IS, 1962, Sharp Industries, Inc. received from the United States Government a check in the amount of $17,228.30 (as reduced to United States dollars) and the same represented the amount due under Modification No. 14 and all remaining “change orders”. The uncontroverted evidence shows that Sharp Industries, Inc. endorsed this check to Sharp Bros. Contracting Co. for payment of indebtedness due, namely advancements made by Sharp Contracting to Sharp Industries to provide capital for carrying out the construction contract. It is conceded that plaintiff Colonial was entitled to receive one-half ($8,614.15) of this amount. Defendant contends that payment of this sum was made to plantiff or its authorized representative. Although the total payments by the Government under the contract amounted to nearly two million dollars, this particular item is the only one in litigation and in dispute. Actually the only fact issue is — did Sharp Industries, Inc. or someone for it pay this sum of $8,614.15 or a sum which Colonial agreed to accept in satisfaction of the obligation, to Colonial or to its authorized representative?

Mr. Don E. Sharp, then a defendant and president of both Sharp companies, testified. He said that in 1959, Mr. Rolf Sief-kin, president, and Mr. Harlo Haagenson, general manager of Colonial, telephoned him on numerous occasions, asking for a settlement in advance for Colonial’s share in the payments to be made under pending Modifications No. 13 and No. 14. Mr. Sharp said he refused to do this as he did not know either the exact or the probable amount of such payments. Then payment for Change No. 13 came through and admittedly Colonial was paid its share. Mr. Don E. Sharp testified that in May, 1960, he received a telephone call from New York City and a three way conversation ensued among himself, his brother Raymond D. Sharp and Harlo Haagenson, Colonial’s general manager. He said his brother Raymond and Mr. Haagenson told him that they had been informed by the Corps of Engineers that the payment for Modification No. 14, would be between $17,000 and $20,000 — likely about $18,000 —and asked him to exchange Colonial’s share of this money, which was coming due, for a like share of the retention money, all of which belonged to Sharp Industries, so that Colonial might realize some immediate cash. Don E. Sharp said he immediately called the Corps of Engineers himself and received verification that the figure of $18,000 was approximately correct. Mr. Sharp asserted that he then contacted his brother and Mr. Haagenson and made an oral “gentleman’s agreement” with them under which Haagenson, representing Colonial, would be paid $9,000 out of the retention money as fast as they could collect it and in return therefor Colonial was to relinquish its right to share in the payment to be made later under Modification No. 14. Mr. Sharp said that after he made this gentleman’s agreement he received no further telephone calls from his brother or from Mr. Haagenson. The payment under Modification No. 14 was made by the Government about January 15, 1962.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lindsey Masonry Co. v. Jenkins & Associates Inc.
897 S.W.2d 6 (Missouri Court of Appeals, 1995)
Leehy v. Supreme Express & Transfer Co.
646 S.W.2d 786 (Supreme Court of Missouri, 1983)
Swindell v. J. A. Tobin Construction Co.
629 S.W.2d 536 (Missouri Court of Appeals, 1981)
Lewis v. Bucyrus-Erie, Inc.
622 S.W.2d 920 (Supreme Court of Missouri, 1981)
City of Gladstone v. Knapp
458 S.W.2d 885 (Missouri Court of Appeals, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
421 S.W.2d 551, 1967 Mo. App. LEXIS 624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colonial-construction-co-v-sharp-industries-inc-moctapp-1967.