Collins Co., Inc. v. City of Decatur

533 So. 2d 1127, 29 Wage & Hour Cas. (BNA) 122, 1988 Ala. LEXIS 522, 1988 WL 119540
CourtSupreme Court of Alabama
DecidedSeptember 23, 1988
Docket86-1579
StatusPublished
Cited by16 cases

This text of 533 So. 2d 1127 (Collins Co., Inc. v. City of Decatur) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collins Co., Inc. v. City of Decatur, 533 So. 2d 1127, 29 Wage & Hour Cas. (BNA) 122, 1988 Ala. LEXIS 522, 1988 WL 119540 (Ala. 1988).

Opinion

The plaintiff, The Collins Company, Inc. ("Collins"), appeals from a judgment entered on a directed verdict on claims for negligence, breach of contract, fraud, and suppression, on behalf of the defendants, the City of Decatur ("City"), George Godwin, David L. Parks, and Paul B. Krebs Associates, Inc. ("Krebs"). This suit arises from events surrounding the construction of additions to the Dry Creek Wastewater Treatment Plant in Decatur, Alabama, and, in particular, from the application of the federal Davis-Bacon Act wage rates to that project.

I. The facts
Early in 1978, the City entered into an agreement with the Environmental Protection Agency ("EPA") for additions to the Dry Creek facility. Under the terms of this agreement, the EPA furnished 75 per cent of the necessary funding, and the City provided the remaining 25 per cent. In exchange, the City-EPA agreement required the City to pay laborers in accordance with wage rates determined under the federal Davis-Bacon Act. Subsequently, the City entered into a contract by which Krebs was to provide general engineering supervision, to draw plans and specifications, to prepare the project bid and construction documents, and to assist the City *Page 1129 in awarding the construction contract. The City retained authority to change construction specifications.

As part of the plans and specifications documents, Krebs provided each bidding contractor wage rate decisions that were furnished by the EPA. These wage rates are formulated by the United States Department of Labor based upon prevailing regional wage rates, and are published in the Congressional Record. Three wage rates applied to the Dry Creek project: building, heavy, and water and sewer. Krebs furnished a set of these plans and specifications to each bidder on the project, but did not reference an appropriate wage rate for each element of the construction project, as suggested by the EPA in two letters sent to Krebs in June 1978.

In addition, Krebs prepared invitation-to-bid documents that contained certain requirements for bidders submitting bids on this project. One requirement instructed bidders to comply with the Davis-Bacon wage scales. If any bidder had any doubt as to the meaning of any part of the plans, specifications, or other proposed contract documents, the bidder could submit a written request to the engineer for interpretation. Any interpretation of the contract document was to be made by a written addendum, and the owner would not be responsible for any other interpretation of the contract. In April 1979, Collins submitted the low bid and was selected as the general contractor. The requirement to comply with the Davis-Bacon wage scales was then incorporated into the contract between the City and its general contractor, Collins.

Collins never applied the three wage rates to the construction project; rather, it applied one rate, heavy, to all of the structures constructed at Dry Creek. On June 9, 1981, the Department of Labor visited the job site and conducted an investigation. A number of months later, it informally told Collins that Collins had improperly calculated its wage rates and owed its laborers an amount equivalent to the higher "building" wage rate. A Collins officer testified that he decided to "fight them." In January 1982, Krebs received another letter from the EPA asking that it "Be sure to double check promptly all payrolls, estimates, etc., and obtain any needed corrections to meet all Labor Standrads [sic] requirements." Krebs filed this letter, without notifying Collins of its contents or existence. In May 1982, the Department of Labor formally notified Collins in writing of its position regarding the wage rates. True to its word, Collins did litigate the issue with the Labor Department. The dispute was settled for less than the Department claimed, but at a cost of $130,000 to Collins.

Collins filed this suit on September 17, 1983, alleging that the defendants caused a disruptive wage investigation and backwage assessment by the Department of Labor when they failed to advise Collins on how to apply the multiple Davis-Bacon wage rates on the items of work contained in the contract documents. Collins further alleged that the defendants had withheld and incorrectly transmitted pertinent wage information provided them by the EPA, that the defendants had failed properly to monitor Collins's wage payments during the construction, and that the defendants had misrepresented and suppressed material wage information. In addition, Collins maintained that the City had wrongfully withheld a significant contract payment for five months after it came due. The complaint asserted claims for declaratory judgment; breach of contract by the City; breach of contract by the City and Krebs; breach of contract duties by the City arising under the EPA grant agreement, injuring Collins, a third-party beneficiary of that contract; misrepresentation of project wage information by the City and Krebs; suppression of project wage information by the City and Krebs; and breach of the City-Krebs contract by misrepresentation and suppression, injuring Collins, a third-party beneficiary of that contract.

At the close of the plaintiff's case and at the close of all the evidence, the defendants filed motions for directed verdict on all counts of the Collins complaint. The trial court granted the defendants' motions. The trial court denied post-trial motions by *Page 1130 Collins, and Collins appealed. The issue presented this Court for review is whether the trial court erred when it directed a verdict on all counts of the plaintiff's complaint.

II. The standard of review
The standard of review this Court applies to motions for directed verdict is identical to the standard used by the trial court in granting or denying the motion. Turner v. Peoples Bankof Pell City, 378 So.2d 706, 709 (Ala. 1979). Thus, when reviewing the trial court's ruling, we determine whether there is sufficient evidence below to produce a conflict warranting jury consideration. Baker v. Chastain, 389 So.2d 932, 934 (Ala. 1980). This Court will reverse a judgment entered on a directed verdict when the record contains any evidence supporting the theories of the complaint, and will affirm the granting of a motion for directed verdict only when the evidence is such that, when viewed in a light most favorable to the non-moving party, reasonable men must draw the same conclusion. See,Weatherly v. Hunter, 510 So.2d 151, 153 (Ala. 1987).

III. The plaintiffs claims on appeal
A. The breach of contract claims
Collins argues that the City, and Krebs as the City's agent, breached the City-Collins contract by failing to provide Collins with the information necessary for Collins to comply with the Davis-Bacon Act, by interfering with Collins's performance of its obligations under the contract, by refusing promptly to pay funds for Collins's work when approved and released for payment by EPA, and by failing to ensure that Collins complied with the Davis-Bacon Act.

Under Alabama law, whether an agreement is ambiguous is a question of law for the court to determine. Terry Cove North,Inc. v. Baldwin County Sewer Authority, Inc., 480 So.2d 1171,1173 (Ala. 1985). Where the contract is unambiguous, the court must determine the force and effect of the contract as a matter of law. Gold Kist, Inc. v. Ford

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riverstone Development Co. v. Garrett & Associates Appraisals, Inc.
195 So. 3d 251 (Supreme Court of Alabama, 2015)
Tull Bros. v. Peerless Products, Inc.
953 F. Supp. 2d 1245 (S.D. Alabama, 2013)
Glenn Construction Co. v. Bell Aerospace Services, Inc.
785 F. Supp. 2d 1258 (M.D. Alabama, 2011)
Custer v. Homeside Lending, Inc.
858 So. 2d 233 (Supreme Court of Alabama, 2003)
Holton v. Blue Cross & Blue Shield of South Carolina
56 F. Supp. 2d 1338 (M.D. Alabama, 1999)
Warren v. Warren
679 So. 2d 664 (Supreme Court of Alabama, 1996)
Ex Parte ReLife, Inc.
679 So. 2d 664 (Supreme Court of Alabama, 1996)
Keebler v. Glenwood Woodyard, Inc.
628 So. 2d 566 (Supreme Court of Alabama, 1993)
Henson v. Celtic Life Ins. Co.
621 So. 2d 1268 (Supreme Court of Alabama, 1993)
Weathers Auto Glass v. Alfa Mut. Ins.
619 So. 2d 1328 (Supreme Court of Alabama, 1993)
HUNTSVILLE AVIATION CORPORATION v. Ford
577 So. 2d 1281 (Supreme Court of Alabama, 1991)
Ramsey v. Taylor
567 So. 2d 1325 (Supreme Court of Alabama, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
533 So. 2d 1127, 29 Wage & Hour Cas. (BNA) 122, 1988 Ala. LEXIS 522, 1988 WL 119540, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-co-inc-v-city-of-decatur-ala-1988.