Collier Development Co. v. Jeffco Construction Co.

25 Pa. D. & C.4th 193, 1995 Pa. Dist. & Cnty. Dec. LEXIS 157
CourtPennsylvania Court of Common Pleas, Alleghany County
DecidedApril 13, 1995
Docketno. GD 93-17798
StatusPublished
Cited by1 cases

This text of 25 Pa. D. & C.4th 193 (Collier Development Co. v. Jeffco Construction Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Alleghany County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collier Development Co. v. Jeffco Construction Co., 25 Pa. D. & C.4th 193, 1995 Pa. Dist. & Cnty. Dec. LEXIS 157 (Pa. Super. Ct. 1995).

Opinion

FRIEDMAN, J.,

INTRODUCTION

Defendant Hartford Fire Insurance Company, incorrectly identified as ITT Hartford Insurance Company, has filed “preliminary objections raising questions of fact” in response to plaintiff’s complaint. The other defendant, Jeffco Construction Company, has filed its answer and new matter.

[194]*194Hartford, in its first preliminary objection, contends that plaintiff is obligated by contract to submit all but a small portion of its claims to arbitration. Hartford’s theory is that plaintiff, a subcontractor, is bound by all the terms agreed to by the general contractor, including the agreement to arbitrate, simply because the “general contract” was, allegedly, incorporated by reference into the “subcontract.”

In addition, Hartford demurs to Count II which seeks punitive and compensatory damages under Pennsylvania’s insurance bad faith statute found at 42 Pa.C.S. §8371:

“In an action arising under an insurance policy, if the court finds that the insurer has acted in bad faith toward the insured, the court may take all of the following actions:
“(1) Award interest on the amount of the claim from the date the claim was made by the insured in an amount equal to the prime rate of interest plus 3 percent.
“(2) Award punitive damages against the insurer.
“(3) Assess court costs and fees against the insurer.”

Hartford contends that a surety bond (such as the one at issue here, which is designed to protect the owner of a construction project by ensuring payment of subcontractors and suppliers) is not covered by section 8371. One reason for this is said to be that a surety has a right of indemnification against the general contractor who purchased the bond for the owner’s benefit. Hartford also points out that the purpose of section 8371 is to punish insurers who wrongfully deny coverage to their insureds. In other words, under Hartford’s analysis, section 8371 does not provide a bad faith claim [195]*195in favor of those injured by an insured’s conduct. Therefore, it should not be interpreted as providing a bad faith claim in favor of subcontractors such as plaintiff who are simply third party beneficiaries of the surety bond issued by Hartford to protect the owner and paid for by the general contractor. Hartford’s position would seem to be that the societal goals achieved by insurance policies are too different from those achieved by surety bonds to allow the insurance law of bad faith to apply to the conduct of the issuers of surety bonds.

Lastly, Hartford demurs to Count III, a claim under the Contractor and Subcontractor Payment Act, 73 P.S. §501 et seq., on the grounds that this Act was only approved on February 17, 1994, is effective as of 60 days thereafter, and applies only “to construction contracts executed on or after the effective date.” Plaintiff agrees that Hartford is correct on this point, so there will be no further discussion of this issue.

After preliminary oral argument, the parties agreed to submit this case for decision on briefs, which were submitted to the court, more or less as scheduled, by April 5, 1995.

It should also be noted that defendant Jeffco raises these same legal issues by way of its new matter, which is not before this court.

DISCUSSION

1. There Is No Express Agreement To Arbitrate Contained in the Subcontracts Between Plaintiff and Defendant Jeffco

The six page subcontract attached to Hartford’s preliminary objections as exhibit A is dated July 10, 1991 and involves the Cranberry Wal-Mart Store, no. 1770. [196]*196Paragraph 26 of that subcontract is entitled “settlement of disputes.” It refers to Jeffco’s right to compel plaintiff’s performance in a court of equity and fails to specify or require any form of arbitration. Hartford agrees that there is no contract to arbitrate this dispute because it does not incorporate by reference any arbitration clause in someone else’s contract. However, Hartford suggests that judicial economy would require arbitration of this claim along with the others, despite the absence of any agreement to arbitrate.

Similarly, Hartford concedes that the subcontract attached to the preliminary objections as exhibit B does not require arbitration, but still requests that the court order it for reasons of judicial economy.

However, Hartford maintains that the subcontracts attached to its preliminary objections as exhibit C and exhibit D do call for arbitration. These contracts have the same “settlement of disputes” paragraph as are in the aforesaid exhibits A and B. The paragraph is as follows:

“Settlement of disputes
“(28) Notwithstanding any of the other provisions of the contract, subcontractor shall continue diligently and uninterruptedly to perform the work and/or supply the material required by him under this contract until completion thereof.
“Jeffco Construction Company shall also have the right to apply a court of equity to compel performance on the part of the subcontractor of the latter’s obligations under this contract. Jeffco Construction Company shall also have the right to obtain another person or firm to perform and complete the obligations required from the subcontractor under this contract, and in such case [197]*197the subcontractor shall be liable for and pay Jeffco Construction Company the excess costs and expenses so incurred by Jeffco Construction Company over and above the contract price herein.
“The rights available to Jeffco Construction Company for subcontractor’s failure to comply with any of the terms of this contract are cumulative, and any one or all of such rights may be exercised at the option of Jeffco Construction Company. Failure at any time of Jeffco Construction Company to enforce any one or more of the rights available to him shall not be deemed as a waiver of such rights or of any default of the subcontractor. On the other hand, the exercise by Jeffco Construction Company of any of the rights available to him shall not constitute a waiver by him of the other rights available to him.”

Hartford would have the court ignore the part of Jeffco’s actual subcontract with plaintiff that purports to deal with the “settlement of disputes” in favor of an obscure and contorted interpretation of so-called incorporation clause found under the heading “special conditions and/or exceptions ” which follows the first section of the subcontract, “scope of work. ”

The section of exhibit C called “special conditions and/or exceptions ” requires the following for the project named “West Hills OTB:”

“(3) Samples, drawings and/or shop drawings to be submitted to Jeffco Construction Company for approval within 10 days of contract date prior to purchase of material.
“(a) A list of major material manufacturers and suppliers for various component items proposed for use on this project must be submitted prior to ordering with shop drawings and/or supplies.
[198]*198“(b) Contract documents, not attached hereto are part of this contract and incorporated herein by reference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
25 Pa. D. & C.4th 193, 1995 Pa. Dist. & Cnty. Dec. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collier-development-co-v-jeffco-construction-co-pactcomplallegh-1995.