Coliadis v. Holko Enercon, Inc.

2016 Ohio 8522
Ohio Court of Appeals·Decided December 30, 2016·No. 2016-T-0044·Published·Cited by 4 cases

Opinion

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT TRUMBULL COUNTY, OHIO

STEVE COLIADIS, f.d.b.a. : OPINION ROYAL LIGHTING, :

Plaintiff-Appellant, CASE NO. 2016-T-0044 :

- vs -

:

HOLKO ENERCON, INC., :

Defendant-Appellee.

:

Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2014 CV 00427.

Judgment: Affirmed.

Michael D. Rossi, Guarnieri & Secrest, P.L.L., 151 East Market Street, P.O. Box 4270, Warren, OH 44482 (For Plaintiff-Appellant).

Thomas E. Schubert, 138 East Market Street, Warren, OH 44481 (For Defendant- Appellee).

DIANE V. GRENDELL, J.

{¶1} Plaintiff-appellant, Steve Coliadis, formerly doing business as Royal Lighting, appeals from the Judgment Entry of the Trumbull County Court of Common Pleas, ordering judgment in favor of defendant-appellee, Holko Enercon, on Coliadis’ claim for breach of contract. The issue to be determined in this case is whether a breach of contract occurs when a roof is installed that the purchaser believes should have prevented all moisture from occurring inside of a building and there is conflicting

testimony about the cause of the moisture. For the following reasons, we affirm the decision of the lower court.

{¶2} On February 26, 2014, Coliadis filed a Complaint in the Trumbull County Court of Common Pleas. It stated that he paid $39,800 to have a roof installed by Holko, which “failed to substantially perform its own obligations under the contract, resulting in a failure of consideration and thereby excusing Plaintiff’s performance thereof.” Coliadis requested a judgment “declaring a rescission of the parties’ contract.”

{¶3} An attached contract, dated April 2, 2004, referred to the job as “re-roofing the Royal Lighting building.” Specifically, it stated that a roof would be installed over the existing “prepared roof surface,” and gave details relating to the installation and flashing. It also stated: “Entire roof system installed to current GAF [the roofing manufacturer] specifications for their 15 Year Material & Labor Warranty.”

{¶4} Holko filed an Answer on May 21, 2014.

{¶5} On May 5, 2015, Holko filed a Trial Memorandum, in which it moved the court to dismiss the Complaint. It argued that, since Coliadis had replaced the roof in 2011, there was a substantial change in the nature of the contract, rescission was not a proper remedy, and Coliadis failed to seek rescission in a reasonable timeframe.

{¶6} A trial was held on May 5, 2015, before a magistrate. The following testimony was presented:

{¶7} In 2004, Holko placed a new roof over the existing one on Coliadis’

business, Royal Lighting. Coliadis indicated that, after this roofing work in 2004, he left the country for a few months and returned to find water on the carpets and moisture

within the building. He believed that the water was leaking from the ceiling area, where there was mold.

{¶8} Coliadis testified that he had no problem with condensation or other water in the building prior to 2004. Coliadis contacted Holko several times. Holko did not believe there was an issue with the roof, but installed additional vents between 2007 and 2009. Holko suggested several other problems, such as foundation issues, that may be the cause of the moisture. Coliadis had work performed based on these suggestions that did not remedy the problem.

{¶9} In 2011, Coliadis had a new roof installed. Since then, he has not experienced problems with mold or condensation. He believed the roof installed by Holko was the problem, since it went over the pre-existing roof and could not “breathe.” Coliadis testified that Roth Brothers Roofing said water got trapped between the two roofs, causing the leaking/water problems. No one from that company testified. Coliadis did not remember making a statement, documented in a GAF inspection report, that “the building was not venting properly after [the] roof was installed.”

{¶10} George Holko, part-owner of Holko Enercon, looked at Coliadis’ roof in 2004, at which time he observed some water damage on the ceiling. He was asked by Coliadis for a quote to reflash parapet walls on the roof. Holko noted that the roof was old and would likely need to be replaced, and gave Coliadis an estimate for doing a “recover” of the roof, placing a new roof over the existing one.

{¶11} While Coliadis complained about the roof and leaks several times following installation in 2004, Holko and his company found no leaks and he never saw external water coming through the roofing membrane. Holko believed that temperature

fluctuations occurring in the building led to any water/moisture problems. He opined that since the building was often left closed for several months at a time during Coliadis’ vacations, moisture became trapped inside, causing condensation. This conclusion was based on observations that the heat is not turned on at all times, with Holko once noting the temperature inside was 55 degrees, and utilities such as gas were turned off. When the heat was ultimately turned on, it could have caused sweating at the ceiling/steel deck.

{¶12} GAF also found no leaks in the ceiling after performing roof investigations.

GAF suggested Coliadis find a design specialist to attain proper ventilation. Holko had also recommended that Coliadis get ventilation in the building to create air movement.

{¶13} On June 4, 2015, a Magistrate’s Decision entered judgment in favor of Coliadis for the return of the contract price, $39,800. The magistrate found that the installation of the roof in 2004 “created a condensation and moisture problem,” finding that the building had no issues after the new roof was installed in 2011, that it had a moisture problem between 2004 and 2011, and that a change had occurred between that time period in the building’s “heating, air movement or closure” due to the roof installation.

{¶14} Holko filed an Objection to the Magistrate’s Decision on June 10, 2015, and a Brief in Support on August 18, 2015. Coliadis filed an opposing Memorandum.

{¶15} On April 20, 2016, the trial court issued a Judgment Entry, finding the objections to the Magistrate’s Decision to be well-taken, rejecting the Magistrate’s Decision, and entering judgment for Holko. The court found no evidence of a breach of

contract, that the evidence showed Holko installed the roof, and noted Coliadis failed to offer expert testimony to show that the roof was defective so as to constitute a breach.

{¶16} Coliadis timely appeals and raises the following assignment of error:

{¶17} “The trial court erred in rejecting the Magistrate’s Decision and entering final judgment for Appellee.”

Free access — add to your briefcase to read the full text and ask questions with AI

Coliadis v. Holko Enercon, Inc., 2016 Ohio 8522 (Ohio Ct. App. 2016).

2016 Ohio 8522 (Coliadis v. Holko Enercon, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Schreiber v. Robsinson
Ohio Court of Appeals, 2026
Hezebicks v. Hezebicks
Ohio Court of Appeals, 2026
Seal Team 6 Asphalt Ceiling Co., L.L.C. v. Ford
2026 Ohio 1116 (Ohio Court of Appeals, 2026)
Lavrich v. Snyderburn
2025 Ohio 2636 (Ohio Court of Appeals, 2025)
Morgan228, L.L.C. v. Miavitz
2025 Ohio 1974 (Ohio Court of Appeals, 2025)
McNichols v. Gouge Quality Roofing, L.L.C.
2022 Ohio 3294 (Ohio Court of Appeals, 2022)
Brownfield Restoration Group, L.L.C. v. Trickett
2018 Ohio 4473 (Ohio Court of Appeals, 2018)