Cole v. Gerrick

113 P. 565, 62 Wash. 226, 1911 Wash. LEXIS 680
CourtWashington Supreme Court
DecidedFebruary 17, 1911
DocketNo. 9331
StatusPublished
Cited by7 cases

This text of 113 P. 565 (Cole v. Gerrick) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cole v. Gerrick, 113 P. 565, 62 Wash. 226, 1911 Wash. LEXIS 680 (Wash. 1911).

Opinions

Parker, J.

This is an action to recover damages from the defendants, alleged to be the result of their negligently causing the death of George Cole, the husband and father of the plaintiffs. A trial before the court and a jury resulted in a verdict and judgment in plaintiffs’ favor, from which the defendants have appealed.

The argument of learned counsel for appellants is directed almost wholly to the alleged error of the trial court in denying their challenge to the sufficiency of the evidence to support the verdict and judgment in respondents’ favor, made at the close of the trial and renewed in their motions for judgment notwithstanding the verdict and for a new trial.

The evidence was in serious conflict upon some of the important questions, but a careful review of the record convinces us that there was competent evidence sufficient to warrant the jury in concluding that the following facts were established. On February 19, 1910, the appellants were contractors engaged in constructing the iron framework of the Fidelity Trust building in Tacoma, and George Cole, the deceased, was then employed by them as a structural iron worker on the building. On that day Cole fell from the top of the north wall of the building, which was then up to the thirteenth floor, to the roof of another building some six stories lower, resulting in his death. At that time the iron framework and walls of the building had been completed up to the twelfth floor. The north wall had been completed up to the thirteenth floor, and the iron framework had been put in place on the thirteenth floor on a considerable portion of the north half of the building. There was placed about the center of the building on the twelfth floor a large derrick which was used for hoisting the material from the street, and also for placing the material at various points on the building as became necessary. This derrick had a long swinging boom, from the end of which hung the cable for handling the material. This cable ran from the iron or material to be handled, through a pulley at the outer end of the boom, down to [228]*228the foot of the derrick through a pulley, and on down to the engine situated six stories below. Another cable, permanently attached to the outer end of the boom, ran to the top of the derrick through a pulley and on down to the engine. By this cable the boom could be lowered so as to extend the outer end of it over the edge of the building, or could be raised so as to bring cable suspended from its outer end over any point between the foot of the derrick and the outer wall. Another cable ran from the derrick down to the engine, adjusted in such manner that the boom could thereby be swung around over any part of the building. The engine supplied the power which controlled all three of these movements. These various movements were controlled by the men in charge of the engine, in obedience to signals communicated to them by a bell and wire extending up to the story at which the work was progressing.

It will thus be seen that the material could, by this derrick, be placed at any point on the story being constructed, provided there was nothing to interfere with the raising, lowering or swinging of the boom. Immediately preceding the falling of Cole off of the north wall, he and another iron worker named Mitchell, and the forem'an, were attempting to place in permanent position an iron channel beam, about twelve feet long and weighing about 300 pounds, along the inner edge of the north wall at the thirteenth floor. At that time the framework of that floor on the north portion of the building so interfered with the lowering and swinging of the boom that it was not possible to suspend and lower this channel by the cable from the outer end of the boom exactly over the final resting place of the channel. The nearest it could be so suspended over its final position was about six feet to the west and about two feet to the south inside the wall. When put in position it was to be attached by rivets or. bolts at its east^ erly and westerly ends to I beams resting upon the wall, and running at right angles thereto towards the interior of the building. These I beams were then already in place. Cole [229]*229was to guide the easterly end of the channel into place, while Mitchell was to guide the westerly end into place, as the channel would be lowered. The channel had reached a position so it was suspended from the outer end of the boom at a point as nearly as possible over its final resting place; that is, about six feet west and about two feet south, parallel with the wall, and some five or six feet above the wall. It hung some thirty-five feet below the outer end of the boom, which enabled the men to move it to its proper position while being lowered. This process is called “drifting,” and except in handling all but very heavy pieces, renders it unnecessary to have them suspended and lowered with any great degree of precision over their final resting place.

While the channel was in this position, the foreman, standing on the westerly I beam immediately to the south of the suspended channel, took hold of it with his hands; while Mitchell, standing partly on the wall end of the westerly I beam and partly on the wall, being on the north side of the suspended channel, took hold of it with his hands. At the same time Cole stepped from his position at the wall end of the easterly I beam along the top of the wall to a point about half way between the I beams, which were about twelve feet apart, that being the length of the channel, for the purpose of taking hold of the easterly end of the channel and assisting in drifting it to its proper position as it would be lowered. He there took hold of the channel as the others did, reaching towards the interior of the building about two feet, where it was suspended. The foreman then communicated to one Lee, who • stood in a position some distance away towards the foot of the derrick, a signal to lower the channel. • This was given by word of mouth, was plainly heard by Mitchell, and must have been heard by Cole, who was then not over ten feet from the foreman. Lee in turn communicated a signal to one Huston, the bell man, who stood by the bell wire at the foot of the derrick, and who in turn communicated a bell signal to the men in charge of the engine below. The engine and the men [230]*230in charge of it were entirely beyond the view of those engaged in placing the channel. Neither could they hear the bell at the engine when a signal was given with it, so they could not tell the nature of the signal received by the men at the engine by hearing it. By some error occurring along the line of communication, or in obeying the signal, the men at the engine, instead of lowering the channel, swung the boom so as to carry the channel away from the wall towards the interior of the building, unexpectedly pulling it out of the hands of Mitchell and Cole. By this unexpected movement Cole was pulled towards the inside of the building before he could let go, and in attempting to regain his balance he fell outside of the wall, resulting in his death.

The wall had been built only the day before. It was green and had not yet set, so the bricks were easily displaced; and in attempting to regain his balance, Cole’s feet loosened a couple of bricks, thus rendering his footing less secure. There is evidence tending to- show that- this condition of the- wall was known to the foreman, but there is no evidence that Cole knew of it, or that its appearance indicated such insecure condition. There was a scaffold, which had been used by the masons in building the wall, some three to five feet below its top on the inside of the wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eckerson v. Ford's Prairie School District No. 11
101 P.2d 345 (Washington Supreme Court, 1940)
Seibly v. City of Sunnyside
35 P.2d 56 (Washington Supreme Court, 1934)
Lange v. Spokane & Inland Empire Railroad
180 P. 924 (Washington Supreme Court, 1919)
Hubbard v. Tacoma Eastern Railroad
172 P. 222 (Washington Supreme Court, 1918)
Seay v. Plunkett
1915 OK 602 (Supreme Court of Oklahoma, 1914)
Browning v. Smiley-Lampert Lumber Co.
137 P. 777 (Oregon Supreme Court, 1914)
Cole v. Gerrick
119 P. 829 (Washington Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
113 P. 565, 62 Wash. 226, 1911 Wash. LEXIS 680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-v-gerrick-wash-1911.