Colbath v. H. B. Stebbins Lumber Co.

144 A. 1, 127 Me. 406, 1929 Me. LEXIS 23
CourtSupreme Judicial Court of Maine
DecidedJanuary 1, 1929
StatusPublished
Cited by19 cases

This text of 144 A. 1 (Colbath v. H. B. Stebbins Lumber Co.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colbath v. H. B. Stebbins Lumber Co., 144 A. 1, 127 Me. 406, 1929 Me. LEXIS 23 (Me. 1929).

Opinion

Bassett, J.

Action on the case to recover under a written contract for an alleged excess of spruce and fir logs above an amount [408]*408stated in the contract. Plea, general issue with brief statement that there was in fact no excess and that any excess was not proved within the time provided by the contract. Verdict of $5,317.98 for plaintiff. Case comes up on exceptions and general motion.

The plaintiif and defendant, by its treasurer, H. B. Stebbins, entered into a written contract dated August 30, 1920, by which the plaintiif agreed to construct a rossing mill at Squa Pan Lake, and cut during the ensuing logging season, and sell and deliver, the last delivei'y to be shipped by December 1, 1921, to the defendant 8,000 coz’ds of z’ossed pulp wood and the defendant agreed to buy the pulp wood at specified prices.

The plaintiif by May 14,1921, had cut and pizt into the lake all the logs to be used under the contract and had delivered some of the pulp wood to the defendant.

The defendant, conditions havizzg changed, did not want to complete the contract. It was rescinded, the defendant agreeing to credit the plaintiif on his open account Avith an agreed sum for the logs in the lake, and the paz’ties making a neAv Avritten agreement Avhich Avas made up of tAvo paz'ts, both dated and executed ozi May 14.

By one of these parts, drawn first, the plaizztiif agreed to complete his sawmill on the lake and have it ready within thirty days to manufacture the logs then in the lake, the approximate amounts of which were stated, and to manufacture and ship the logs according to oz’ders furnished by the defezzdant and to pay the defendant a commission of five per cent on the selling pz’ice, the proceeds to be applied first upon a mortgage given that day by the plaintiif to the defendant upon the logs to secure in part an adAmzice payment of the balance due on stumpage of the logs, and of an amount not exceedizzg forty thousand dollars, to be advanced by the defendant to complete the mill. The plaintiif agreed to manufacture azzd ship on orders of the defezzdant a sufficient quantity of lumber to pay the moz'tgage on or before December 31,1921.

The defendant agreed to advance zzot exceeding forty thousand dollars to complete the mill and put it into condition to manufacture the lumber and to paj^ the balance due on stumpage azzd Avhen the mortgage had been paid, then to pay plaintiif the amount, less commission, of shipments made thereafter withizz sixty days of the date of shipment.

[409]*409On May 14 the plaintiff and defendant met and drew a second part, which is the center of the controversy, as follows:

“In connection with our agreement of May 14th, 1921 and of cancellation of our agreement of August 30, 1920, H. B. Stebbins Lumber Company agrees to turn over to G. M. Col-bath money required for labor bills in the manufacturing of logs under our agreement of May 14th, 1921, not to exceed $6.00 a thousand on lumber as it is shipped under that contract. If by December 31, 1921 it proves that G. M, Colbath now has cut and in Squa Pan Lake to apply on our contract of May 14th, 1921, Spruce and Fir logs in excess of 4,590,666, we will pay you an amount equal to $10.00 a thousand on such excess of Spruce and Fir logs, but not to exceed $8,355.00. If it should prove by December 31, 1921 that the amount of Spruce and Fir logs now cut, and in Squa Pan Lake to apply under our contract of May 14, 1921 is less than 4,590,666, G. M. Colbath agrees to pay H. B. Stebbins Lumber Company an amount equal to $10.00 a thousand on such shortage.”

The mill was completed about July 1 and the manufacture into lumber of the logs in the lake began and continued until about November 10 when the lake froze over and manufacturing was suspended until the following spring. During 1921 about half of the logs had been manufactured. During the winter of 1921-1922 the plaintiff landed on the ice of the lake another cut of logs, which were boomed. The logs in question were loose. The plaintiff from time to time shipped lumber manufactured from the logs in question upon orders of the defendant and the defendant received the stipulated commission. By August 23, 1922, all the logs were manufactured except 521 which became mixed with the new cut. On September 15, 1922, the plaintiff sent to the defendant the mill scale amount of the manufactured lumber which showed an excess above the 4,590,666 stated in the second part of the contract. The defendant refused to pay (1) because the scale included some lumber graded as “red rot,” (2) because the lumber had been sawed scant at the mill, thereby making the mill scale appear more than actually sawed, so that with scale bill corrected by rejection of red rot and reduction for scant sawing there was a shortage, not an excess, and [410]*410(3) because the amount of any excess had not been determined by December 31,1921.

The first exception raises the question, whether, in determining the “excess” or “shortage” under the second part of the contract, lumber graded as “red rot,” of which thei'e was admittedly 433,204 feet board measure, should be excluded. In view of other instructions deemed to be erroneous and prejudicial, bearing on the plaintiff’s right now to maintain his claim for an alleged excess, we think it is unnecessary to consider further this exception other than to say the question was properly left to the jury and the exception cannot be maintained.

The second exception raises the question of the effect of the date, December 31,1921, in the second part of the contract, the defendant contending that it was of the essence of the contract.

The parties on May 14 in executing the second part of the contract had in mind a liquidation of the damages to the plaintiff for not carrying out the rescinded contract. They had agreed upon a sum, which was credited to the plaintiff based upon an agreed amount of logs in the lake, which amount the plaintiff believed to be less than the actual amount and the defendant believed to be more than, or at least not less than, the actual amount.

The completion of the first part of the contract was in no way dependent upon any difference between the actual and the fixed amount of logs in the lake as agreed upon in the second part of the contract. In fact the two contracts are in no way dependent on each other. By the second part, the defendant promised that, if by December 31 it was proved there were in the lake on May 14 more than the stated amount of logs, he would pay the plaintiff a computed amount of money, and the plaintiff making a mutual and similar promise in case of shortage. Proving or determining by December 31 was not an impossible condition, nor at the date of the contract did it appear to be so. If to prove it would require taking the logs from the lake and piling them, “banking them” before and manufacturing them after the lake froze or running the plant more hours in the twenty-four, that would not, though causing additional expense, be an excuse for non-fulfillment of the condition.

[411]*411The defendant requested an instruction “that the alleged overrun not having been proved before December 31, 1921, the plaintiff cannot recover.”

This was refused and the jury were instructed, “Now I charge you . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lukas v. Pickus
Maine Superior, 2015
OFFICEMAX INC. v. Sousa
773 F. Supp. 2d 190 (D. Maine, 2011)
Raisin Memorial Trust v. Casey
2008 ME 63 (Supreme Judicial Court of Maine, 2008)
Drinkwater v. Patten Realty Corp.
563 A.2d 772 (Supreme Judicial Court of Maine, 1989)
Wachovia Bank & Trust Co., N.A. v. Rubish
293 S.E.2d 749 (Supreme Court of North Carolina, 1982)
Chapman v. Bomann
381 A.2d 1123 (Supreme Judicial Court of Maine, 1978)
Interstate Industrial Uniform Rental Service, Inc. v. Couri Pontiac, Inc.
355 A.2d 913 (Supreme Judicial Court of Maine, 1976)
Canaras v. Lift Truck Services, Inc.
322 A.2d 866 (Court of Appeals of Maryland, 1974)
Evelyn v. Raven Realty, Inc.
138 A.2d 898 (Court of Appeals of Maryland, 1958)
Dolloff v. Gardiner
91 A.2d 320 (Supreme Judicial Court of Maine, 1952)
Meade v. Collins Realty Co.
75 A.2d 705 (Superior Court of Delaware, 1950)
Hill v. Day
215 P.2d 219 (Supreme Court of Kansas, 1950)
Medomak Canning Co. v. York
57 A.2d 745 (Supreme Judicial Court of Maine, 1948)
Levine v. Reynolds
54 A.2d 514 (Supreme Judicial Court of Maine, 1947)
Fortin v. Wilensky
53 A.2d 266 (Supreme Judicial Court of Maine, 1947)
Wall Investment Co. v. Schumacher
125 S.W.2d 838 (Supreme Court of Missouri, 1939)
Bryne v. Bryne
196 A. 402 (Supreme Judicial Court of Maine, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
144 A. 1, 127 Me. 406, 1929 Me. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colbath-v-h-b-stebbins-lumber-co-me-1929.