Coker International, Incorporated v. Burlington Industries, Inc.

935 F.2d 267
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 21, 1991
Docket90-2494
StatusUnpublished

This text of 935 F.2d 267 (Coker International, Incorporated v. Burlington Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coker International, Incorporated v. Burlington Industries, Inc., 935 F.2d 267 (4th Cir. 1991).

Opinion

935 F.2d 267
Unpublished Disposition

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
COKER INTERNATIONAL, INCORPORATED, Plaintiff-Appellant,
v.
BURLINGTON INDUSTRIES, INC., Defendant-Appellee.

No. 90-2494.

United States Court of Appeals, Fourth Circuit.

Submitted May 22, 1991.
Decided June 11, 1991.
As Amended June 21, 1991.

Appeal from the United States District Court for the District of South Carolina, at Greenville. Joe F. Anderson, Jr., District Judge. (CA-90-734-6-17)

H.W. Pat Paschal, Greenville, S.C., for appellant.

Jack H. Tedards, Jr., Leatherwood, Walker, Todd & Mann, P.C., Greenville, S.C., for appellee.

D.S.C., 747 F.Supp. 1168.

AFFIRMED.

Before WIDENER, K.K. HALL, and SPROUSE, Circuit Judges.

PER CURIAM:

Coker International, Inc. ("Coker") is seeking rescission of its contract for the purchase of used textile looms from Burlington Industries, Inc. ("Burlington"), and the return of a "non-refundable downpayment." The district court granted Burlington's motion for summary judgment as to each of Coker's causes of action. We granted a joint motion to submit this case for decision on the briefs, without oral argument. Upon consideration of the briefs and joint appendix, we affirm the district court's order.

I. STANDARD OF REVIEW

In reviewing the district court's order granting summary judgment, we must apply the same standard as the trial court. Helm v. Western Md. Ry. Co., 838 F.2d 729, 734 (4th Cir.1988). Upon a motion for summary judgment, the court must view the facts, and the inferences to be drawn from those facts, in the light most favorable to the party opposing the motion. Ross v. Communications Satellite Corp., 759 F.2d 355 (4th Cir.1985). Summary judgment is proper where there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). However "[t]he mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact." Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986).

II. FACTS

Sometime around December 21, 1987, Coker entered a contract with Burlington whereby it agreed to purchase 221 used textile looms as well as loom beams, remaining harness frames, and assorted loom parts, a stainless steel size pump, and two cloth doffing trucks. The total purchase price for these items was to be $1,021,000. The terms of the sale were as follows:

10% NON-REFUNDABLE DOWNPAYMENT TO BE RECEIVED BY CLOSE OF BUSINESS ON JANUARY 8, 1988. IF NOT RECEIVED, BURLINGTON MAY, AT ITS OPTION CANCEL [THE CONTRACT] AND OFFER THE LOOMS FOR SALE TO OTHERS.

BALANCE TO BE PAID PRIOR TO REMOVAL OF LOOMS. REMOVAL TO BE COMPLETED BY MARCH 1, 1988.

SOLD "AS IS, WHERE IS MILL FLOOR"

The sale was also subject to other terms and conditions attached to the contract. Relevant to this lawsuit is the force majeure provision. This paragraph states:

Deliveries may be suspended by either party in case of act of God, war, riots, fire, explosion, flood, strike, lockout, injunction, inability to obtain fuel, power, raw materials, labor, containers, or transportation facilities, accident, breakage of machinery or apparatus, national defense requirements or any cause beyond the control of such party, preventing the manufacture, shipment, acceptance, or consumption of a shipment of the Goods or of a material upon which the manufacturer of the Goods is dependent.

Coker informed Burlington that it intended to resell the looms. In response to Burlington's standard inquiry regarding whether its products would be resold to possible competitors, Coker stated its intent to resell the equipment to customers in Peru.1 The contract was silent as to the existence of potential purchasers or contracts for sale to third parties by Coker.

Coker paid the required down payment, albeit ten days late. None of the looms were picked up or paid for by the deadline required by the contract, March 1, 1988. Several extensions of time were granted by Burlington in order for Coker to obtain financing and remove the equipment. By April 11, Coker had paid $166,800 against the total invoice of $1,021,000 and had removed only 16 looms.

After extensive discussion and correspondence between the parties, they entered into a supplemental letter agreement in yet another attempt on Burlington's part to accomodate Coker.2 Under the agreement, Burlington agreed to sell Coker the remaining looms and give Coker credit for the non-refundable down payment on the same terms as in the original contract, provided that the balance due was to be paid in full by May 31, 1988. The agreement further provided that Coker would pay in advance for all looms picked up between May 4 and May 31, 1988. The final deadline for removal was to be June 10, 1988. Finally, Burlington would be entitled to place all looms not paid for by May 31, 1988, back on the open market.

By letter dated May 27, 1988, Coker informed Burlington that it had removed 12 looms. It further informed Burlington that payment and removal of the remainder of the looms would take place by June 30, 1988. The letter indicated that Coker had received a commitment from a buyer in San Fernando, S.A., and was awaiting the necessary license to import, and a letter of credit which was expected to follow. Burlington agreed to the extension to June 30, but warned Coker that it would be the last. It also informed Coker that it would be charged for storage. By July 6, 1988, the payment had not been received by Burlington. Burlington declared its intent to treat the original agreement as breached and to put the looms back on the open market. At that time, Coker had taken delivery of 34 of the looms and paid a total of $239,750.

By letter dated November 17, 1988, Coker wrote to Burlington to demand a solution which would give Coker credit or refund for the down payment. Coker also referred to the force majeure provision of the contract and stated that its customer in Peru could not accept delivery for reasons beyond Coker's control, and argued that it was therefore entitled to a refund of the down payment.

III. LEGAL DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
935 F.2d 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coker-international-incorporated-v-burlington-indu-ca4-1991.