Coker International, Inc. v. Burlington Industries, Inc.

747 F. Supp. 1168, 14 U.C.C. Rep. Serv. 2d (West) 409, 1990 U.S. Dist. LEXIS 18033, 1990 WL 160213
CourtDistrict Court, D. South Carolina
DecidedSeptember 27, 1990
DocketCiv. A. 6:90-734-17
StatusPublished
Cited by3 cases

This text of 747 F. Supp. 1168 (Coker International, Inc. v. Burlington Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coker International, Inc. v. Burlington Industries, Inc., 747 F. Supp. 1168, 14 U.C.C. Rep. Serv. 2d (West) 409, 1990 U.S. Dist. LEXIS 18033, 1990 WL 160213 (D.S.C. 1990).

Opinion

ORDER

JOE F. ANDERSON, Jr., District Judge.

Plaintiff Coker International, Inc. (“Coker”) brings this action seeking rescission of its contract to purchase 221 used textile looms from defendant Burlington Industries, Inc. (“Burlington”), and seeking particularly the return of a “non-refundable down payment” called for by the contract. Burlington has moved for summary judgment as to each of the causes of action advanced by Coker. For the reasons stated herein, the court grants Burlington’s motion for summary judgment as to each of Coker’s causes of action.

Factual Background

In support of its motion for summary judgment, Burlington has submitted two affidavits of David W. Ryan, its Manager, Used Equipment, dated June 15, 1990 and July 27, 1990, respectively. In opposition to the motion, Coker has submitted two affidavits of its president, Jackson R. Coker, dated July 13, 1990 and August 13, 1990, respectively. The affidavits are largely consistent with regard to the underlying facts. To the extent there may be factual disputes, the Court has accepted the facts as asserted by Coker for purposes of this motion.

The undisputed facts show that Coker and Burlington entered a contract whereby Coker would purchase 221 used textile looms from Burlington for a total price of $1,021,000. The parties agree that the contract was evidenced by a two-page Burlington invoice, which provided in relevant part:

Payment terms: 10% non-refundable down-payment to be received by close of business on January 8, 1988. If not received, Burlington may, at its option cancel this invoice and offer the looms for sale to others.
Balance to be paid prior to removal of looms. Removal to be completed by March 1, 1988.
Sold “as is, where is mill floor.”

Coker paid the down payment in the amount of $102,100, but did not pay the balance due by the contract date of March 1, 1988. During the months of March through June, 1988, Coker requested extensions of time and represented that it would pay the balance due and remove the looms *1170 by various dates. During that time, Coker did pay the balance due for a total of 34 looms, and removed those looms from the Burlington plant. Eventually, Burlington declared the contract terminated due to Coker’s breach and placed the remaining 187 looms back on the market, retaining the balance of the non-refundable down payment.

One document of particular interest is a letter agreement of May 4, 1988. Burlington had written to Coker on April 13, stating that it was terminating the agreement and retaining the non-refundable down payment. Coker protested, and its attorney wrote to Burlington asking that the parties meet “to attempt to resolve the differences.” Coker then proposed a schedule by which it would pay for and remove all looms by the week of June 6, 1988. In response, Burlington proposed the letter agreement of May 4, 1988, in which it reserved its rights under previous defaults but agreed to sell the remaining looms and give credit for the down payment if Coker paid the balance by May 31, 1988, and picked up all the looms by June 10, 1988. Coker signed and returned the letter agreement. There were no conditions concerning Coker’s ability to resell the equipment or the problems it was encountering with its contemplated resale.

Coker does not dispute any of these facts. Coker asserts that its non-performance resulted from the failure of its intended resale of the equipment to a customer in Peru due to actions taken by the government of Peru. Coker seeks rescission of the agreement and return of the down payment on several theories which are individually discussed in following sections of this Order.

Plaintiffs Motion To Amend

Coker has moved to amend its Complaint to add a third cause of action for breach of a covenant of good faith. Counsel for Burlington stated at the hearing that its opposition to the motipn was based solely on its position that the proposed amendment was without merit, and that Burlington would not oppose the amendment so long as its summary judgment motion was considered to apply to the amended Complaint. The motion to amend the Complaint is therefore granted.

Force Majeure Clause

Coker alleges the contract should be rescinded, and its down payment returned, due to the force majeure clause of the contract, based upon the actions of the government of Peru which prevented Coker’s intended resale of the equipment. Accepting as true Coker’s assertions regarding the actions of the government of Peru, the force majeure clause would not entitle Coker to rescind the contract or recover the non-refundable down payment.

The contractual force majeure clause provides in relevant part as follows:

Deliveries may be suspended by either party in case of act of God, ... or any cause beyond the control of such party, preventing the manufacture, shipment, acceptance, or consumption of a shipment of the Goods....

The actions of the government of Peru did not prevent Coker from accepting the looms that were the subject of the contract between Coker and Burlington. The language of the force majeure clause does not excuse nonperformance due to failure of a contract of resale, economic disadvantage resulting therefrom, or even a resulting inability to obtain the money for the goods. Subjective impossibility of performing does not relieve a party from the contract unless the contract so states. Moon v. Jordan, 390 S.E.2d 488 (S.C.App.1990). 1 The force majeure clause applies to objective events which directly affect the parties’ ability to perform the contract in question, not the ability to make a profit on resale of the goods.

Additionally, the force majeure clause provides only for suspension of deliveries, not rescission of the contract nor return of the non-refundable down payment.

*1171 Frustration Of Purpose

Coker’s Complaint does not expressly speak of frustration of purpose. However, it does allege the impossibility of performing its intended contract to resell the looms in question. Construing the allegations of the Complaint liberally in favor of Coker, the first cause of action could be construed to allege frustration of purpose. Coker devoted a major part of its argument at the hearing to this theory.

Both parties have cited and discussed the doctrine of frustration of purpose as stated in Restatement, Second, Contracts § 265:

Where, after a contract is made, a party’s principal purpose is substantially frustrated without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his remaining duties to render performance are discharged, unless the language or the circumstances indicate the contrary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kyocera Corp. v. Hemlock Semiconductor, LLC
886 N.W.2d 445 (Michigan Court of Appeals, 2015)
MPI SC v. Levy Center
Court of Appeals of South Carolina, 2011

Cite This Page — Counsel Stack

Bluebook (online)
747 F. Supp. 1168, 14 U.C.C. Rep. Serv. 2d (West) 409, 1990 U.S. Dist. LEXIS 18033, 1990 WL 160213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coker-international-inc-v-burlington-industries-inc-scd-1990.