Cohen v. G/C Contracting Corp., 2006 Ca 102 (9-21-2007)

2007 Ohio 4888
CourtOhio Court of Appeals
DecidedSeptember 21, 2007
DocketNo. 2006 CA 102.
StatusPublished
Cited by14 cases

This text of 2007 Ohio 4888 (Cohen v. G/C Contracting Corp., 2006 Ca 102 (9-21-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cohen v. G/C Contracting Corp., 2006 Ca 102 (9-21-2007), 2007 Ohio 4888 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Ira S. Cohen appeals from a judgment of the Greene County Court of Common Pleas, which granted summary judgment to G/C Contracting Corporation on whether the parties were subj ect to a mandatory arbitration provision and stayed this action pending arbitration. For the following reasons, the trial court's judgment will be reversed and the cause remanded for *Page 2 further proceedings. .

{¶ 2} According to Cohen's amended complaint, on September 3, 2003, Cohen, dba Ira S. Cohen Associates, sent a proposal to G/C Contracting, a company bidding on a project to construct a replacement fire station for the Beavercreek Board of Trustees. Cohen's proposal offered to fabricate and erect miscellaneous architectural steel, structural steel, joists, deck, and accessories in connection with the Beavercreek project for $193,431. Beavercreek selected G/C Contracting to be the general contractor for the fire station project, and G/C Contracting began discussions with Cohen about the steelwork aspects of the job. On October 4, 2003, G/C Contracting "gave [Cohen] the verbal go-ahead to commence work on the project."

{¶ 3} On October 23, 2003, G/C Contracting sent Cohen a draft of a written contract to review and sign. According to Cohen, the parties did not execute the written agreement. Cohen alleged that he substantially completed all labor and furnished substantially all materials by August 8, 2004, at which time he was improperly terminated from the project. Cohen alleged that he has not been fully paid by G/C Contracting. He stated that the total contract price was $194,558 plus approximately $250,000 in agreed-upon extras.

{¶ 4} On February 15, 2005, Cohen brought suit against G/C Contracting and others, asserting claims of breach of contract, lien foreclosure, for payment pursuant to R.C. 1311.32, unjust enrichment, fraud, bad faith, and tortious interference with a business relationship.1

{¶ 5} On March 19, 2005, G/C Contracting filed a motion to dismiss and/or for a more definite statement and/or to stay. G/C Contracting asserted that the relationship between Cohen *Page 3 and G/C Contracting was governed by a written contract, which was executed on October 20, 2003. In its motion, G/C Contracting argued that "Plaintiffs failure to attach the contract between the parties subjects the complaint to either dismissal or requires a more definite statement. The Contract that should have been attached contains a valid alternative dispute resolution clause. Once that clause is given full effect, this case should either be dismissed or stayed." G/C Contracting also argued that certain causes of action should be dismissed. G/C Contracting attached a "Contractor and Subcontractor Agreement" signed by Cohen. A preprinted portion of the Agreement stated that it was "made on" October 20, 2003.

{¶ 6} In his memorandum in opposition to the motions, Cohen asserted that no written contract was entered into by the parties. He indicated that the alleged contract attached by G/C Contracting to its motion should have included an "Exhibit G," which contained many proposed modifications to the terms of the agreement. Cohen notes that G/C Contracting did not sign the contract, and there was no meeting of the minds as to what the written instrument would say. Cohen provided an affidavit that detailed the negotiations between Cohen and G/C Contracting and stated that no written contract was executed.

{¶ 7} In response, G/C Contracting asserted that G/C Contracting's signature was not required for the contract to be binding on the parties. Moreover, it denied that any exhibit was attached to the contract when it was returned to G/C Contracting. It attached the affidavit of Justin Conger, Vice President of G/C Contracting, to substantiate its assertions.

{¶ 8} On July 11, 2005, the trial court stated that "[i]t appears from the fact patter[n] of this case that alternative dispute resolution has not been exhausted and, as such, Plaintiff s claim should be pled with particularity as to why said alternative dispute resolution provisions are not *Page 4 applicable in [s]aid contract between Plaintiff and Defendants." The court granted the motion to dismiss, stay or for more definite statement, indicating that several counts needed to be pled with more particularity.

{¶ 9} On September 9, 2005, Cohen filed an amended complaint. Cohen specifically alleged that G/C Contracting had sent a draft written contract, which Cohen signed and returned with numerous material changes to bring the contract in line with the project specifications. Cohen attached the alleged draft "Contractor and Subcontract Agreement," which was signed by Cohen, as well as Exhibit G. G/C Contracting subsequently filed counterclaims, alleging breach of contract, breach of implied warranty, and negligent construction.

{¶ 10} On September 27, 2005, G/C Contracting moved to dismiss Cohen's amended complaint. It argued that G/C Contracting and Cohen had either a written or an implied contract that required mandatory arbitration to resolve this dispute. G/C Contracting attached the draft "Contractor and Subcontractor Agreement" along with Exhibit G. Cohen opposed the motion, again arguing that there was no written contract between the parties and, thus, no valid and binding arbitration clause.

{¶ 11} On February 9, 2006, the trial court converted the motion to dismiss on the issue of mandatory arbitration to a motion for summary judgment, and it provided the parties an additional period of time to supplement the record. Neither party submitted additional materials to the court.

{¶ 12} On August 3, 2006, the court granted G/C Contracting's motion for summary judgment and it stayed the litigation pending arbitration. The court stated:

{¶ 13} "Relevant facts of this case are as follows: G/C Contracting Corp. contracted *Page 5 with Beavercreek Township for a construction project relating to a Beavercreek Replacement Fire Station No. 1. In October, 2003, Ira Cohen as subcontractor, contracted with G/C Contracting Corp. to provide in part: All labor, Materials, Equipment, Supervision, and Coordination forthe following: Architectural Miscellaneous Steel, Structural Stell [sic], and Joists Per Specs Sections o5100 [sic], 05200, 05300, 05500,and 05712 . . . Plaintiff was to be paid $194,558.00. For one reason or another a dispute arose related to the contract between G/C Contracting and Ira Cohen leading to the instant lawsuit. Defendant, G/C Contracting maintains the matter should never have been filed in the common pleas court because of a[n] existing contractual agreement between the parties that sends disputes to mediation and binding arbitration. In response Plaintiff argues there was no contract because there was no meeting of the minds as to an offer and acceptance. Specifically, the parties proceeded under a verbal understanding . . ., a quote from Plaintiff,and the plans and specifications. The Court notes Plaintiff has not attached an affidavit in support to his response memorandum filed October 18, 2005, which was filed in response to Defendant's motion on the amended complaint, but has previously filed the affidavit of Ira Cohen on April 18, 2005.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arch Bay Holdings, L.L.C. v. Brown
2012 Ohio 4966 (Ohio Court of Appeals, 2012)
Fifth Third Mtge. Co. v. Bihn
2012 Ohio 637 (Ohio Court of Appeals, 2012)
Brittingham v. Gen. Motors Corp.
2011 Ohio 6488 (Ohio Court of Appeals, 2011)
Burgin v. Eaton
2011 Ohio 5951 (Ohio Court of Appeals, 2011)
Barwick v. State Farm Fire & Cas. Ins. Co.
2011 Ohio 5689 (Ohio Court of Appeals, 2011)
Carpenter v. Long
2011 Ohio 5414 (Ohio Court of Appeals, 2011)
CitiMortgage, Inc. v. Lucas
2011 Ohio 3724 (Ohio Court of Appeals, 2011)
AO Freight Corp. v. Snyder Computer Sys., Inc.
2010 Ohio 4778 (Ohio Court of Appeals, 2010)
KeyBank National Ass'n v. Mazer Corp.
935 N.E.2d 428 (Ohio Court of Appeals, 2010)
Banks v. Jennings
920 N.E.2d 432 (Ohio Court of Appeals, 2009)
Corn v. Whitmere
916 N.E.2d 838 (Ohio Court of Appeals, 2009)
Citibank v. Wood
894 N.E.2d 57 (Ohio Court of Appeals, 2008)
Dayspring of Miami Valley v. Carmean, 2007 Ca 28 (12-28-2007)
2007 Ohio 7159 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 4888, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cohen-v-gc-contracting-corp-2006-ca-102-9-21-2007-ohioctapp-2007.