Cochran v. Yoho

75 P. 815, 34 Wash. 238, 1904 Wash. LEXIS 342
CourtWashington Supreme Court
DecidedMarch 8, 1904
DocketNo. 4356
StatusPublished
Cited by3 cases

This text of 75 P. 815 (Cochran v. Yoho) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cochran v. Yoho, 75 P. 815, 34 Wash. 238, 1904 Wash. LEXIS 342 (Wash. 1904).

Opinion

Per Curiam.

This action was commenced in the superior court of King county by C. D. Cochran and A. J. Webb, as plaintiffs, against-J. F. Yoho and Mary Yoho, his wife, as defendants. Plaintiffs allege in their amended complaint that, on or about the 14th day of December, 1900, they and one C. L. Huggins entered into a written' contract with J. K. Yoho, for the construction of four certain two-story frame buildings upon lot 4 in block 54 of the Second Addition to the city of Seattle. This contract is referred to as an exhibit, and is as follows:

“Seattle, Wash., Dec. 17th, 1901.
“We, the parties of the first part, C. L. Huggins, A. J. Webb and C. D. Cochran, and J. P. Yoho of the second part, do enter into a contract for the construction of four, four part tenement houses to be erected on lot 4, block 54, Sarah A. Bell’s 2nd addition to Seattle, Wash. The parties of the first part agree to furnish all material and labor for construction and completion of said buildings according to plans and specifications for the sum of forty four hundred dollars ($4400). Said buildings are to be commenced at once and completed as soon as possible. The party of the second part agrees to furnish a sufficient amount of money for the parties of the first part to get the material for said buildings, but at no time to pay any in advance. All bills to be receipted and turned into party of second part before final payment” [Signed, etc.]

The complaint further alleges that, immediately after the execution of this contract, O. L. Huggins abandoned said contract, and so notified these plaintiffs (Cochran and Webb), verbally, without giving any reasons therefor. That on the 17th day of December, 1900, these plaintiffs commenced to perform labor and furnish materials to be used in the construction of such buildings, the contract price [240]*240therefor being $4,400; that plaintiffs eontinned to perform said labor and furnish said materials up to and including the 9th day of March, 1901, and, before that time, had completed two of said buildings and delivered the same to said Yoho, who thereupon accepted the same; that on the 9th day of March, 1901, said J. IP. Yoho forcibly and unlawfully ejected these plaintiffs from said premises, and refused to allow them to complete said contract; that plaintiffs thereupon were compelled to and did cease to perform any further labor, or furnish any further materials, under such contract; that, when plaintiffs quit said work, an expenditure of $150 would have completed the two remaining buildings; that the contract price of each building was $1,100; that defendants are the owners and reputed owners of said premises; that J. F. Yoho advanced to plaintiffs $3,687.92 under said contract; that there is a balance due plaintiffs of $712.08, with interest thereon from March 9, 1901; and that, within ninety days after quitting work, plaintiffs made and filed their lien on said premises, for labor and materials so furnished, in the auditor’s office of said King county, and the same was duly recorded. Plain-' tiffs asked judgment for the above amount, and interest, for a foreclosure of their said lien, and costs, including an attorney’s fee of $150, and for general relief. Defendants filed a general demurrer to such complaint, which was overruled. Defendants, by their answer to such amended complaint, put in issue the material allegations thereof; and, for further defense and counterclaim, allege, in part, as follows :

*‘(2) That in accordance with the term's of said contract the said Cochran, Webb, and Huggins were to- construct the said buildings in accordance with certain plans and specifications furnished, and that it was also provided that the lumber furnished was to be of good quality, and that the said houses were to be completed as soon as pos[241]*241sible. (3) That contrary to the terms of said agreement the said lumber furnished was of an inferior quality and was not suitable for the use to which it was put, the buildings were not and are not constructed in accordance with the plans and specifications provided, and the work was performed in a careless, indifferent, and unworkmanlike manner. (4) That contrary to the terms of said contract after partially constructing said buildings and before the completion thereof and while the same were in an exposed and unfinished condition, these plaintiffs wilfully abandoned said labor, on or about March 9th, 1901, and then refused, and at subsequent times when notified by the said J. F. Yoho to complete the said buildings, refused to further perform labor or to further furnish material. (5) That up to and including the 9th day of March, 1901, when these plaintiffs abandoned said contract as above alleged, the said J. F. Yoho had paid these plaintiffs for use in the said houses the sum of four thousand twenty two dollars and twelve cents ($4022.12). (6) That the defendant J. F. Yoho was compelled to and did actually expend the further sum of five hundred sixty six dollars sixty nine cents ($566.69) for the completion of said houses in accordance with the terms of said contract.”

The defendants further allege damages in the sum of $1,500, and ask judgment against plaintiffs for $1,688.73 on their counterclaim. Plaintiffs in their reply deny each and all the material allegations of new matter contained in the answer.

The cause was tried to the court without a jury on the 6th day of January, 1902, and thereupon the following findings of fact, among others, were made by the trial court:

“(5) That on or about the 6th day of March, 1901, the defendant J. F. Yoho forcibly ejected the plaintiffs from said premises, and refused to allow them to further perform said contract, or to carry the same out or complete the same, and that thereupon the plaintiffs ceased to perform any further labor, or to furnish any further materials, [242]*242upon said houses; that all of said labor and materials under said contract were performed and furnished between the 17th day of December, 1900, and the 9th day of March, 1901. (6) That at the time when said defendant J. F. Yoho refused to allow the plaintiffs to further perform said contract, one hundred and fifty dollars would have completed said buildings, including all necessary material therefor. (7) That during the construction of said buildings, it had been agreed between the plaintiffs and the defendant, J. F. Yoho, that four chimneys might be omitted from said houses, for which the plaintiffs agreed to allow the defendants their reasonable cost. (8) That the reasonable costs of said chimneys would have amounted to eighty dollars. (9) That the labor performed and materials furnished, as aforesaid, to be used in and which were used in the construction of said buildings, were furnished to the said J. F. Yoho in accordance with the terms and conditions of said contract, except as in paragraph seven hereof stated.....(14) And the court further finds that it was agreed upon the trial of this cause between the plaintiffs and defendants and stipulated therein that, in case said lien was foreclosed and a decree rendered in favor of the plaintiffs, $150 was a reasonable attorney’s fee to be allowed the plaintiff in this cause.”

The court thereupon stated the following conclusions of law:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cowley v. Northern Pacific Railway Co.
123 P. 998 (Washington Supreme Court, 1912)
Smith v. Hopper
121 P. 77 (Washington Supreme Court, 1912)
O'Sullivan v. O'Sullivan
77 P. 806 (Washington Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
75 P. 815, 34 Wash. 238, 1904 Wash. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cochran-v-yoho-wash-1904.