Coastland Corp. v. County of Currituck

734 F.2d 175
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 11, 1984
DocketNos. 83-1658, 83-1723
StatusPublished
Cited by9 cases

This text of 734 F.2d 175 (Coastland Corp. v. County of Currituck) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastland Corp. v. County of Currituck, 734 F.2d 175 (4th Cir. 1984).

Opinion

ERVIN, Circuit Judge:

Coastland Corporation filed suit in district court seeking damages from Currituck County under 42 U.S.C. § 1983 and under the fifth and fourteenth amendments. Coastland’s amended complaint alleges due process violations actionable under § 1983 that arose from the County’s failure to enforce the liquidated damages clause of a water and sewer contract. The complaint also sets forth an inverse condemnation claim arising from the County’s land use regulation. The district court granted Currituck’s motion for summary judgment on the § 1983 claim but held that there were material questions of fact concerning the inverse condemnation claim.1 Because we conclude that Coastland did not have a property right under the water and sewer contract, we affirm the dismissal of its § 1983 claim. Finding that Currituck’s land use regulations did not constitute a taking, we reverse the district court’s order dismissing Currituck’s motion for summary judgment on the inverse condemnation claim.

I.

In 1971 Coastland bought 600 acres of land on the narrow Currituck Outer Banks. At that time, land to the north was owned by two developers, Kabler and Riggs, and by the United States Department of Interi- or. A road controlled by the Department of Interior provided the only access from the north to Coastland’s property. The only access road to the south crossed over private property owned by Earl F. Slick. Soon after Coastland drew up plans to develop its property, the Currituck Board of Commissioners (the Commissioners) declared a one-year moratorium on all development while it revised its land use plans to account for the increased development of the Outer Banks. These revisions resulted in a land use plan known as the Currituck Plan, which was distinctive in its emphasis on Planned Unit Developments (PUDs) and on central water and sewerage facilities. Coastland revised its subdivision plans to accord with these changes.

On March 14, 1973, the Commissioners held a meeting to determine whether to change Currituck’s zoning ordinance to accommodate Coastland’s Planned Unit Development. Various groups objected to Coastland’s plats because the plans increased the number of families on the property and did not provide for public access through the subdivision. The meeting was adjourned with an agreement that the question of access deserved further discussion. At a Commissioners meeting the following week, a motion passed to approve Coastland’s disputed plats if they included a public right of way.2

[177]*177On May 8, 1973, one-half of Coastland’s plats, those designated as Phase II, were approved. Those plats showed Ocean Trail, the main access road, as a private road. However, the approval of this portion of Ocean Trail as private was later characterized by the Currituck Commissioners as a mistake. In September of 1973, the Commissioners considered approval of Coastland’s Phase III plats. The northern developers Kabler and Riggs requested that the plats be disapproved because they did not provide for public access over Ocean Trail.3 The Commissioners did not approve the plats and instead asked the various developers to meet with one another to discuss the question of access.

On March 4, 1974, Coastland’s Phase III plats were approved with Coastland dedicating for public use the relevant sections of Ocean Trail. At a subsequent meeting, the Commissioners corrected their earlier mistake and declared the portions of Ocean Trail on the Phase II plats to be a public road. Coastland did not object to this declaration. The Phase IV and V plats were then approved on May 6 with Ocean Trail dedicated as a public road. Coastland’s president later stated in a sworn affidavit that county officials told Coastland before its Phase III plats were approved that “there would be no further plat approvals granted to Coastland unless access was provided to outer banks land to the north of [Coastland’s land] over Ocean Trail, and unless Coastland negotiated with [Kabler and Riggs] reasonable terms for access along the Slick easement.” (J.A. 146)

On March 22, 1973, Coastland presented Currituck with a water and sewer contract that Currituck approved on May 8. The Commissioners had earlier agreed that Coastland would finance the construction of water and sewerage facilities and that the County would maintain the facilities. The contract provided, inter alia, that once Coastland requested the County to begin construction, the County had to complete construction within six (6) months, weather permitting. The contract contained no liquidated damages provision.

On July 7, 1975, Currituck contracted with Hilco Company to construct the water and sewer system contemplated in the Currituek-Coastland agreement. The contract between Currituck and Hilco called for the system to be completed within 180 days after Currituck’s order to proceed. A liquidated damage provision required Hilco to pay Currituck $100.00 for each day’s delay. Currituck ordered Hilco to proceed on September 14, 1975, and Hilco finished 505 days late. This delay resulted in $50,-500.00 liquidated damages. After paying Hilco $91,132.18 for the system, the County sought reimbursement from Coastland. Coastland responded by insisting that Currituck recover $44,200.00 from Hilco in liquidated damages. The County chose not to recover any liquidated damages. Coast-land, only disputing a few small charges, thereafter paid Currituck $89,632.18. Coastland threatened to sue Currituck for not recovering the liquidated damages, but it never filed suit in state court.

II.

Coastland claims that the County’s decision not to recover liquidated damages and credit them to Coastland’s account, a decision made without giving Coastland a hearing on the subject, violated under color of state law Coastland’s fourteenth amendment right to due process. 42 U.S.C. § 1983 provides a civil remedy in federal court for deprivation of federal rights under color of state law. Coastland’s § 1983 claim is based on the premise that it had a property interest in the liquidated damages due Currituck under the Hilco-Currituck contract. This premise is a mistaken one.

For one to have a property interest in something, he must “have a legitimate claim of title to it.” Property interests

are created and their dimensions are defined by existing rules or understandings that stem from an independent source [178]*178such as state law — rules or understandings that secure certain benefits and that support claims of entitlement to those benefits.

Board of Regents v. Roth, 408 U.S. 564, 577, 92 S.Ct. 2701, 2709, 33 L.Ed.2d,548 (1972).

Coastland’s own argument undercuts its assumption that it had a property-interest in the liquidated damages due Currituck under thel975 Hilco-Currituck contract. Coastland argues that it was not an intended beneficiary of the contract between Currituck and Hilco and, therefore, that it had no right to sue for breach of contract in state court. The test to determine who is a third party beneficiary in North Carolina is whether the two principal parties entered into the contract “with the intention, express or implied, of benefit-ting a third party.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
734 F.2d 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastland-corp-v-county-of-currituck-ca4-1984.