Coalition for Canyon Preservation, Inc. v. Hazen

788 F. Supp. 1522, 1990 U.S. Dist. LEXIS 19783, 1990 WL 341707
CourtDistrict Court, D. Montana
DecidedDecember 28, 1990
DocketCV 90-141-M-CCL
StatusPublished
Cited by4 cases

This text of 788 F. Supp. 1522 (Coalition for Canyon Preservation, Inc. v. Hazen) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coalition for Canyon Preservation, Inc. v. Hazen, 788 F. Supp. 1522, 1990 U.S. Dist. LEXIS 19783, 1990 WL 341707 (D. Mont. 1990).

Opinion

OPINION AND ORDER

LOVELL, District Judge.

The court denied Plaintiffs’ application for temporary restraining order and preliminary injunction. This opinion explains the reasons for the court’s ruling.

BACKGROUND

Plaintiffs filed their application seeking to stop the Federal Highway Administration (FHWA), the Army Corps of Engineers, and Frontier West from constructing a replacement bridge across the North Fork of the Flathead River near Pole-bridge, Montana. Plaintiffs allege defendants have violated various procedural requirements of the Clean Water Act, the Wild and Scenic Rivers Act, and the National Environmental Policy Act (NEPA). In essence, plaintiffs are opposed to construction of the bridge for two reasons: first, the location of the proposed bridge 350 feet upstream from the old site allegedly will cause significant impact to the wild and scenic river values of the North Fork, and second, the proposed two lane bridge should be a one lane bridge, which in their opinion, is more consistent with the historic and natural qualities of the area. 1

In 1988, the Red Bench forest fire destroyed several major structures in the Po-lebridge developed area of Glacier National Park. The bridge at Polebridge which crosses the North Fork of the Flathead River, a wild and scenic river, was among those structures destroyed. Since the Pole-bridge area is a major access point to Glacier, the Park Service budgeted emergency funds to replace the structures and embarked on an accelerated planning schedule for the area which included preparing an environmental assessment (EA) to determine if replacement of the buildings ■ and bridge would result in any significant adverse impacts.

*1524 On August 1, 1989, the Park Service made a finding of no significant impacts and determined it would proceed with replacement of the structures at Polebridge, Montana.

Because the proposed bridge would be placed across a navigable stream, the FHWA with which the Park Service had entered into an agreement to install the bridge, made application to the Corps of Engineers for a 404 permit under the Clean Water Act. On April 25, 1990, the Army Corps of Engineers notified the public that the FHWA had applied for a 404 permit for the bridge project.

Based on its environmental assessment, the Corps determined that there would be no significant adverse impacts from the project and issued the 404 permit.

Thereafter the FHWA received bid solicitations for construction of the bridge and issued a contract on November 7, 1990, to Frontier West. Frontier West began to move its material and equipment onto the job site in order to start work in early December and plaintiffs filed suit against defendants.

DISCUSSION

To prevail on its motion for preliminary injunction, plaintiffs must show (1) probable success on the merits, (2) possible irreparable injury, 'and (3) a public interest favoring plaintiff. Caribbean Marine Services Co. v. Baldrige, 844 F.2d 668 (9th Cir.1988). A plaintiff may meet its burden by demonstrating a combination of probable success on the merits and a possibility of irreparable harm. Id. at 674. In the alternative, where the balance of hardships tips decidedly toward the plaintiff, the court need not require a robust showing of likelihood of success on the merits and may grant relief if the plaintiffs moving papers raise “serious questions” on the merits. Id.

Here, the scale does not decidedly tip in plaintiffs’ favor. Although plaintiffs may be able to show some immediate disturbance to the river, the facts indicate such effects will not be serious or permanent. Moreover, the testimony of the Park Service and the construction contractor show that if the plaintiffs were successful in obtaining at least one of their stated objectives, i.e., placement of the bridge at the old location, the present temporary bridge would have to be removed and yet another temporary “work” bridge would need to be installed, to facilitate construction of the permanent bridge at the old site. Thus, considerably more disturbance of the river would occur under plaintiffs’ proposal.

Although plaintiffs argue that the proposed bridge at the new site would have long-term effects on the natural, historic and aesthetic values, plaintiffs are not the only ones concerned. According to FHWA, the bridge currently in place is a temporary structure with an estimated life of five to ten years. Without significant maintenance to both the bridge super and substructure, there is risk of structural and hydraulic failure, 2 i.e., the bridge could fall apart. As the Park Service noted in its EA, the bridge at this location provides 24,000 members of the public with entry to Glacier National Park each year. If the bridge project is stopped, the public will continue to be exposed to problems of safe and inadequate access to and from the Park. Finally, the evidence shows that bridge contractor, Frontier West, as well as several subcontractors could suffer substantial financial loss if the court were to grant the restraining order.

Because the balance of hardship does not tip decidedly toward the plaintiffs, they must do more than raise serious questions by their motion. In this case, the court finds that plaintiffs have not demonstrated a likelihood of success on the merits and for the reasons set forth below, the court denied their application to enjoin temporarily and permanently defendants from constructing the bridge across the North Fork of the Flathead River.

1. Failure to take a “hard look”:

Citing various statutory and regulatory violations, Plaintiffs allege that Defen *1525 dant Corps of Engineers failed to give primary emphasis to the wild and scenic river values; to consider other relevant values; to consider practicable alternatives; and failed to perform an environmental impact statement.

The basis for each of these allegations is that the Corps failed to take the requisite “hard look” at the project. Foundation for North American Wild Sheep v. U.S., 681 F.2d 1172 (9th Cir.1982).

In support of these allegations, plaintiffs called Sharlon Willows, a member of the Coalition for Canyon Preservation and Resources Unlimited. She testified that the Corps failed to consider the wild and scenic river values when it chose the new site 350 feet upstream from the old site where the Coalition insists the bridge should be built, to avoid new impacts. Significantly, in response to a question from the court concerning public safety, Ms. Willows conceded that the new bridge must be a two lane structure. In addition, she stated she was not opposed to the design or configuration. 3 The bridge is a low profile bridge that utilizes a single pier and will be constructed from colored, rough finished concrete, weathering steel and rustic log guardrails.

Ms. Willow stated that in her opinion the old site is part of the historic value of the area because a bridge has been located at that site since 1916.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Double R Ranch Trust v. Nedd
284 F. Supp. 3d 21 (D.C. Circuit, 2018)
Double R Ranch Trust v. Bail
District of Columbia, 2018
Sierra Club North Star Chapter v. Pena
1 F. Supp. 2d 971 (D. Minnesota, 1998)
Oregon Natural Resources Council v. Marsh
845 F. Supp. 758 (D. Oregon, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
788 F. Supp. 1522, 1990 U.S. Dist. LEXIS 19783, 1990 WL 341707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coalition-for-canyon-preservation-inc-v-hazen-mtd-1990.