Cnf Constructors, Incorporated v. Donohoe Construction Company, a Division of the Donohoe Companies, Incorporated

57 F.3d 395, 32 Fed. R. Serv. 3d 29, 1995 U.S. App. LEXIS 14530, 1995 WL 351884
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 13, 1995
Docket94-1609
StatusPublished
Cited by110 cases

This text of 57 F.3d 395 (Cnf Constructors, Incorporated v. Donohoe Construction Company, a Division of the Donohoe Companies, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cnf Constructors, Incorporated v. Donohoe Construction Company, a Division of the Donohoe Companies, Incorporated, 57 F.3d 395, 32 Fed. R. Serv. 3d 29, 1995 U.S. App. LEXIS 14530, 1995 WL 351884 (4th Cir. 1995).

Opinion

Affirmed by published per curiam opinion.

OPINION

PER CURIAM:

Donohoe Construction Company (Donohoe) appeals from a district court ruling that arbitration of a construction contract dispute between Donohoe and CNF Constructors, Inc., (CNF), must take place pursuant to the rules and procedures of the American Arbitration Association (AAA). For the reasons that follow, we conclude that Donohoe’s motion for clarification, upon which the district court ruled and Donohoe appeals, is best characterized as a motion for reconsideration of a final judgment under Fed.R.Civ.P. 60(b). Although we express a number of difficulties with the manner in which the district court resolved the motions before it, we nevertheless affirm the denial of Donohoe’s motion for clarification.

I.

This lawsuit centers around the construction of a new Human Studies facility at the University of North Carolina at Chapel Hill. The State of North Carolina, the owner of the facility to be constructed, hired Donohoe as the primary contractor for the site. Do-nohoe, in turn, entered into a subcontract with CNF, under which CNF would perform the mechanical work on the project, such as plumbing and process piping. As the project proceeded, the construction crews encountered unexpected site conditions and problems with installation of the building’s caissons, which substantially delayed the project schedule. The parties essentially dispute who should be held financially responsible for the increased costs arising from the construction delays.

On March 22, 1993, CNF instigated this action in federal court by filing a motion to compel arbitration under the Federal Arbitration Act pursuant to 9 U.S.C. § 4 (1988), and to appoint an arbitrator pursuant to 9 U.S.C. § 5 (1988). Donohoe responded by filing a motion to dismiss and a motion to strike, essentially arguing that the contract entered into by the parties did not provide for arbitration.

The district court issued two orders that are relevant to this appeal. In the first *397 order, issued on November 4, 1993, the district court stated it was considering all of the motions filed by both parties. After detailing the negotiation process leading up to the construction contract between the parties, the district court held that the contract bound the parties to arbitrate their dispute. Accordingly, the district court granted CNF’s motion to compel arbitration and denied Donohoe’s motions to strike and dismiss. Although the district court specifically stated at the beginning of its order that it was addressing CNF’s motion to appoint an arbitrator, it did not specify whether it was granting or denying the motion at the conclusion of the order. That same day the Clerk of the Court administratively closed the case.

On January 20, 1994, over two months after the district court issued the order compelling arbitration, Donohoe filed a “Motion for Clarification of Judge Boyle’s Order Granting CNF’s Motion to Compel Arbitration.” According to the motion, the American Arbitration Association interpreted the district court’s November 4th order as providing the organization with the authority to conduct the arbitration and, more specifically, to compel Donohoe to attend AAA hearings in Atlanta, Georgia. In its motion for clarification, Donohoe requested that the district court (1) direct CNF to dismiss the action pending before AAA, (2) find that the arbitration was to take place at or near Raleigh, North Carolina, and (3) appoint an arbitrator pursuant to 9 U.S.C. § 5. CNF responded that the district court lacked authority to reconsider its prior order because the motion for clarification was not filed within ten days of the entry of the order, as required by Fed.R.Civ.P. 59(e). Furthermore, CNF maintained that the district court’s November 4th order clearly established that AAA was to conduct the arbitration and that there was no need to revisit the issue months later.

In its second order, entered on April 6, 1994, the district court addressed the issues raised in Donohoe’s motion for clarification. Without touching upon the jurisdictional basis for addressing the motion, the district court essentially ruled that it had already decided in its first order that the parties were bound under their contract to arbitrate their dispute and that the arbitration was to proceed according to the rules of AAA. The district court concluded its order not by denying the motion for clarification, but instead by stating that “the court orders that its November 4, 1993, order be enforced and arbitration [ ] continue pursuant to the AAA.” (J.A. 240.)

Donohoe timely appealed to this Court from the district court’s second order.

II.

On appeal, Donohoe asks this Court to reverse the district court’s second order, entered April 6, 1994, disposing of Donohoe’s motion for clarification. Specifically, Dono-hoe asks that we (1) order CNF to dismiss the arbitration proceedings before AAA, (2) order that the arbitration take place within the Eastern District of North Carolina, and (3) appoint an arbitrator to resolve the arbitration. Donohoe’s appeal raises interesting and difficult questions as to the procedural intricacies surrounding the arbitration process, as well as to the jurisdictional powers of the district court and this Court to resolve those intricacies.

Before we can consider Donohoe’s requests on their merits, however, we must determine the extent of our own appellate jurisdiction to review the district court’s two orders in this case. 1 Although the lack of *398 clarity in the district court’s orders makes our analysis somewhat more complex, we will still proceed through a step-by-step jurisdictional analysis of the two orders. First, we will look to whether the district court’s initial order, entered on November 4, 1993, was an appealable final order. The importance of whether this initial order was final should not be underestimated. On one hand, if the November 4th order was a final order, then we can only review the district court’s second order on Donohoe’s motion for clarification if it was a proper post-judgment motion. On the other hand, if we conclude that the first order was not a final order, then we must consider whether the second order on the motion for clarification constitutes a final order over which we have jurisdiction.

Second, because we conclude that the first order was a final order susceptible to appeal, we look to whether Donohoe’s motion for clarification, from which the second order was issued, was a proper postjudgment motion over which the district court had jurisdiction. As to this portion of the appeal, we conclude that the district court did not abuse its discretion in ruling on the motion for clarification, although we resolve this issue, in large part, upon different grounds than those offered by the district court.

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. Select Bank
W.D. Virginia, 2025
MSP Recovery Claims, Series LLC v. Lundbeck LLC
130 F. 4th 91 (Fourth Circuit, 2025)
Rivers v. Iredell County
W.D. North Carolina, 2024
Hartnett v. Hardenbergh
E.D. Virginia, 2024
Guzman v. Acuarius Night Club LLC
D. South Carolina, 2024
McSheffrey v. Wilder
E.D. Virginia, 2024
Burrell v. Mayer
E.D. Virginia, 2024
McDonald v. United States
W.D. North Carolina, 2024
Jones v. Del Toro
E.D. Virginia, 2024
Allen v. John/Jane Doe
D. Maryland, 2024
Johnson-El v. Mitchell
W.D. North Carolina, 2024
Scott v. Hudgins
W.D. North Carolina, 2024
Frank Morgan v. J. Tincher
90 F.4th 172 (Fourth Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
57 F.3d 395, 32 Fed. R. Serv. 3d 29, 1995 U.S. App. LEXIS 14530, 1995 WL 351884, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cnf-constructors-incorporated-v-donohoe-construction-company-a-division-ca4-1995.