CMM-CM, LLC. v. VCON, LLC

CourtDistrict Court, D. Nevada
DecidedJune 23, 2021
Docket2:21-cv-00542
StatusUnknown

This text of CMM-CM, LLC. v. VCON, LLC (CMM-CM, LLC. v. VCON, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CMM-CM, LLC. v. VCON, LLC, (D. Nev. 2021).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 DISTRICT OF NEVADA 6 * * *

7 CMM-CM, LLC, d/b/a MULLER Case No. 2:21-CV-542 JCM (VCF) CONSTRUCTION, 8 ORDER Plaintiff(s), 9 v. 10 VCON, INC., et al., 11 Defendant(s). 12

13 Presently before the court are defendant VCON, LLC’s (“VCON”) motions to compel 14 arbitration and to stay this case. (ECF Nos. 10, 11). Plaintiff CMM-CM, LLC, dba Muller 15 Construction (“Muller”), did not respond and the time to do so has passed. 16 Also before the court are Muller’s motions to remand and to stay this case. (ECF 17 Nos. 12, 13). VCON responded in opposition (ECF No. 15) to which Muller replied (ECF 18 No. 16). 19 I. BACKGROUND 20 Subcontractor Muller alleges that general contractor VCON owes $283,411.73 for 21 framing and drywall work done on the Vineyard Main Street Henderson construction project. 22 (Compl., ECF No. 1-1 ¶ 7). The property is owned by Vineyard Main Street Henderson, 23 LLC (“Vineyard”). (ECF No. 10 at 4). Muller alleges that the project “suffered significant 24 delays from poor on-site management.” (ECF No. 12 at 2). VCON’s project manager sent 25 Muller three non-compliance notices, prompting Muller to respond that the issues on the site 26 were “a direct result of the project manager’s negligence.” (ECF No. 1-1 ¶ 11). Muller 27 “performed all of its duties” until they were instructed by VCON to stop work. (Id. ¶ 15). 28 1 “Despite continuous attempts to contact VCON, Muller was never given clearance to 2 continue, and Muller’s contract for work was never terminated.” (ECF No. 12 at 2). Muller 3 recorded a $283,411.73 mechanic’s lien on the project property. (ECF No. 1-1 ¶ 16). 4 VCON, as principal, later recorded a mechanic’s lien release bond, naming North American 5 Specialty Insurance Company (“NASIC”) as the surety. (Id. ¶ 18). 6 Muller sued VCON and NASIC in Nevada state court for breach of contract and to 7 enforce its mechanic’s lien. (ECF No. 1-1). VCON removed the case to this court (ECF No. 8 1) and now moves to compel arbitration. (ECF No. 10). Muller—a Nevada LLC— 9 responded with a motion to remand, arguing that because NASIC is an insurer of Vineyard— 10 also a Nevada LLC according to Muller—it is treated as a Nevada citizen under 28 U.S.C. § 11 1332(c)(1)(A), thus destroying complete diversity and depriving this court of diversity 12 jurisdiction. (ECF No. 12 at 3). 13 II. LEGAL STANDARD 14 A. Motion to Remand 15 Federal courts are courts of limited jurisdiction. Owen Equip. & Erection Co. v. 16 Kroger, 437 U.S. 365, 374 (1978). Accordingly, there is a strong presumption against 17 removal jurisdiction. Hunter v. Philip Morris USA, 582 F.3d 1039, 1042 (9th Cir. 2009). 18 Under the removal statute, a defendant may remove any civil action over which the federal 19 district court has original jurisdiction. 28 U.S.C. § 1441(a). 20 A plaintiff can challenge removal with a motion to remand. 28 U.S.C. § 1447(c). 21 The removing defendant must prove by a preponderance of the evidence that the court has 22 original jurisdiction. Gaus v. Miles, Inc., 980 F.2d 564, 566 (9th Cir. 1992). Thus, if 23 removal is based on diversity jurisdiction, the removing defendant must show by a 24 preponderance of the evidence that there is complete diversity and that the amount in 25 controversy exceeds $ 75,000. 28 U.S.C. § 1332(a). Complete diversity exists where “the 26 citizenship of each plaintiff is diverse from the citizenship of each defendant.” Caterpillar 27 Inc. v. Lewis, 519 U.S. 61, 68 (1996). When removing a case, defendants are “merely 28 required to allege (not to prove)” the citizenship of the parties. See Kanter v. Warner- 1 Lambert Co., 265 F.3d 853, 857 (9th Cir. 2001). Ambiguities are resolved in favor of 2 remand. Hunter, 582 F.3d at 1042. 3 B. Motion to Compel Arbitration 4 Congress passed the Federal Arbitration Act (“FAA”) nearly 100 years ago “in 5 response to widespread judicial hostility to arbitration agreements.” AT&T Mobility LLC v. 6 Concepcion, 563 U.S. 333, 339 (2011). An arbitration provision in a written contract 7 affecting interstate commerce “shall be valid, irrevocable, and enforceable, save upon such 8 grounds as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2. The 9 statute reflects a strong federal policy in favor of arbitration and requires the court to “place 10 arbitration agreements on an equal footing with other contracts.” Concepcion, 563 U.S. at 11 339; see also Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24 (1983). 12 The court’s limited role under the FAA is to determine (1) whether a valid agreement 13 to arbitrate exists and (2) whether the agreement covers the dispute at issue. Nguyen v. 14 Barnes and Noble, Inc., 763 F.3d 1171, 1175 (9th Cir. 2014). In making these 15 determinations, the court must apply state contract law and resolve all ambiguities in favor of 16 arbitration. Id. The FAA leaves no discretion to the court; it must stay judicial proceedings 17 and compel arbitration of claims covered by a written and enforceable arbitration agreement. 18 Id.; see also Dean Witter Reynolds v. Byrd, 470 U.S. 213, 218 (1985). 19 III. DISCUSSION 20 As a preliminary matter, the court will decide Muller’s motion to remand (ECF No. 21 12)—which argues that the court lacks diversity jurisdiction—before VCON’s motion to 22 compel arbitration (ECF No. 10). See Countrywide Home Loans, Inc., v. Mortg. Guar. Ins. 23 Corp., 642 F.3d 849, 854 (9th Cir. 2011) (“In order for a court to adjudicate an FAA 24 claim, . . . it must have proper jurisdiction over the conflict even assuming the parties had 25 never entered into an agreement to arbitrate” because the FAA “does not confer federal 26 jurisdiction.”). 27 . . . 28 . . . 1 A. Muller’s Motion to Remand 2 Muller’s remand motion turns on whether NASIC is an insurer of the project property 3 owner Vineyard. If it is, then it takes on Vineyard’s purported Nevada citizenship under the 4 diversity statute which would destroy complete diversity. The diversity statute states that “in 5 any direct action against the insurer of a policy or contract of liability insurance . . . to which 6 action the insured is not joined as a party-defendant, such insurer shall be deemed a citizen of 7 every State and foreign state of which the insured is a citizen.” 28 U.S.C. § 1332(c)(1)(A). 8 Muller briefly argues that NASIC is an insurer of Vineyard because “a bonding 9 agreement is a contract of insurance.” (ECF No. 12 at 4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Owen Equipment & Erection Co. v. Kroger
437 U.S. 365 (Supreme Court, 1978)
Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Caterpillar Inc. v. Lewis
519 U.S. 61 (Supreme Court, 1996)
In Re W.W. Jarvis & Sons
671 S.E.2d 534 (Court of Appeals of North Carolina, 2009)
Hunter v. Philip Morris USA
582 F.3d 1039 (Ninth Circuit, 2009)
Day v. Volkswagenwerk Aktiengesellschaft
451 F. Supp. 4 (E.D. Pennsylvania, 1977)
Kevin Nguyen v. Barnes & Noble Inc.
763 F.3d 1171 (Ninth Circuit, 2014)
Burgoyne v. Frank B. Hall & Co. of Hawaii, Inc.
781 F.2d 1418 (Ninth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
CMM-CM, LLC. v. VCON, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cmm-cm-llc-v-vcon-llc-nvd-2021.