CMI Contracting, Inc. v. Little River Lodging

CourtCourt of Appeals of South Carolina
DecidedJune 30, 2004
Docket2004-UP-421
StatusUnpublished

This text of CMI Contracting, Inc. v. Little River Lodging (CMI Contracting, Inc. v. Little River Lodging) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CMI Contracting, Inc. v. Little River Lodging, (S.C. Ct. App. 2004).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


CMI Contracting, Inc.,        Respondent,

v.

Little River Lodging, LLC and Construction Design Associates, Inc., Defendants,

of whom Little River Lodging, LLC, is,        Appellant.


Appeal From Horry County
J. Stanton Cross, Jr., Master-In-Equity


Unpublished Opinion No. 2004-UP-421
Submitted June 8, 2004 – Filed June 30, 2004


AFFIRMED


W. W. DesChamps, Jr., of Myrtle Beach, for Appellant.

Reese R. Boyd III, of Myrtle Beach, for Respondent.

PER CURIAM:  Little River Lodging, LLC, appeals the trial court’s order granting judgment in favor of CMI Contracting, Inc., on a mechanic’s lien in the amount of $73,620.75.  The order also awarded CMI $18,055.95 in prejudgment interest and $8,533.70 in attorney’s fees.  As an alternative but superceded ground for recovery, the trial court found Little River liable to CMI for the amount of the alleged mechanic’s lien on the basis of CMI’s unjust enrichment claim.  We affirm. [1]

FACTS

Little River is the owner of a parcel of real estate situated in Horry County, South Carolina upon which it sought to construct a commercial hotel development.  Through its owner and operator, Bhupendra Patel, Little River contacted co-defendant Construction Design Associates, Inc., (“CDA”), a general contractor, in February 2000 and asked CDA to begin working on the project.  CDA and Little River understood the first phase of this project to include clearing the parcel and filling some wetlands on the property.  Due to a longstanding professional relationship between CDA and Little River, CDA did not initially require a written agreement with Little River. 

Subsequent to these discussions concerning the property, CDA entered a subcontract agreement with CMI for the clearing and wetland work to be performed on the property.  The subcontract agreement included a cost estimate from CMI of approximately $118,000.  CMI began performing the agreed upon work in early March and completed the work on April 11, 2000.  CDA and Patel visited the work site during the months CMI performed the work specified in the subcontract agreement. 

Following the work’s completion, CMI submitted invoices to CDA for payment totaling $123,621.  CDA then submitted $50,000 in payment to CMI after receiving a check for the same amount and purpose from Patel of Little River.  This was the only payment CMI received for the work.  Although an internal CDA document recognized a $61,259 balance due CMI on the subcontracting work, Patel later claimed he understood the $50,000 payment to be the complete amount due CMI for the project. 

Little River and CDA did not memorialize their general contracting agreement for developing the property until October 2000.  The contract states work shall not commence until all of the following are accomplished: 1) financing is in place and designated for the project; 2) a building permit is obtained; and 3) written notice to proceed is received by CDA.  Because construction financing could not be obtained, CDA never commenced contract performance.  No hotel or other structure exists on the property today.

In the meantime, CMI served a summons, complaint, and notice and certificate of a mechanic’s lien on the property on Little River on July 18, 2000 and to CDA on August 11, 2000.  In addition to the mechanic’s lien, CMI asserted a claim against Little River for unjust enrichment.  The trial court awarded CMI a judgment of $100,210.40, the lien plus interest and attorney’s fees, against Little River.  The court order also stated CMI was entitled to $73,620.75 on its claim for unjust enrichment, but explained this award was “superceded by CMI’s judgment on its mechanic’s lien.”  This appeal followed.

STANDARD OF REVIEW

A proceeding to enforce a mechanic’s lien is an action at law.  Seckinger v. Vessel Excalibur, 326 S.C. 382, 386, 483 S.E.2d 775, 777 (Ct. App. 1997).  In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judge’s findings.  Townes Assocs. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).

LAW / ANALYSIS

I. Subject Matter Jurisdiction

Little River argues the mechanic’s lien foreclosure should be reversed because the trial court lacked subject matter jurisdiction over the matter due to untimely service.  We disagree.

South Carolina Code section 29-5-90 provides, in pertinent part:

[A] lien shall be dissolved unless the person desiring to avail himself thereof, within ninety days after he ceases to labor on or furnish labor or material for such building or structure, serves upon the owner . . . a statement of a just true account of the amount due him . . . together with a description of the property intended to be covered by the lien . . . with the name of the owner of the property, if known.

S.C. Code Ann. § 29-5-90 (Supp. 2003). [b1]    It is undisputed that CMI served this required notice and certificate of a mechanic’s lien on Little River after the statutorily mandated ninety-day period.  However, when questioned at trial regarding the sufficiency of the lien’s service, the following exchange occurred between the trial court and counsel for Little River:

THE COURT:  Is there an issue about the technical aspects of the mechanic’s lien such as the notice, the certificate was given, the timing of the foreclosure of the mechanic’s lien? All the technical aspects, is that an issue?

LITTLE RIVER:  I think the mechanic’s lien was served and everything.

THE COURT:  I don’t have the roll up here.

LITTLE RIVER:  I’ve got some other points to argue, but it’s not regarding service or whether the mechanic’s lien was properly prepared.

The sufficiency of the lien’s service was never again discussed or raised before the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.V.A. Construction Corp. v. Santee Wando Construction
400 S.E.2d 498 (Court of Appeals of South Carolina, 1991)
Johnson v. State
459 S.E.2d 840 (Supreme Court of South Carolina, 1995)
Knight Publishing Co. v. University of South Carolina
367 S.E.2d 20 (Supreme Court of South Carolina, 1988)
F & D Electrical Contractors, Inc. v. Powder Coaters, Inc.
567 S.E.2d 842 (Supreme Court of South Carolina, 2002)
Clo-Car Trucking Co. v. Clifflure Estates of South Carolina, Inc.
320 S.E.2d 51 (Court of Appeals of South Carolina, 1984)
Coon v. Coon
588 S.E.2d 624 (Court of Appeals of South Carolina, 2003)
Townes Associates, Ltd. v. City of Greenville
221 S.E.2d 773 (Supreme Court of South Carolina, 1976)
Hodge v. FIRST FEDERAL SAVINGS & LOAN ASSN.
227 S.E.2d 310 (Supreme Court of South Carolina, 1976)
Simpson Ex Rel. Estate of Demos v. Sanders Ex Rel. Estate of Demos
445 S.E.2d 93 (Supreme Court of South Carolina, 1994)
Wilder Corp. v. Wilke
497 S.E.2d 731 (Supreme Court of South Carolina, 1998)
Seckinger v. Vessel, Excalibur
483 S.E.2d 775 (Court of Appeals of South Carolina, 1997)
Thomas & Howard Co. v. TW Graham and Co.
457 S.E.2d 340 (Supreme Court of South Carolina, 1995)
St. Catherine's Church Corp. v. Technical Planning Associates, Inc.
520 A.2d 1298 (Connecticut Appellate Court, 1987)
McLendon v. South Carolina Department of Highways & Public Transportation
443 S.E.2d 539 (Supreme Court of South Carolina, 1994)
Baker v. Wolfe
510 S.E.2d 726 (Court of Appeals of South Carolina, 1998)
Padgett v. Mercado
533 S.E.2d 339 (Court of Appeals of South Carolina, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
CMI Contracting, Inc. v. Little River Lodging, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cmi-contracting-inc-v-little-river-lodging-scctapp-2004.