C.M. Moore Division K.S.H., Inc. v. The United States

940 F.2d 678, 37 Cont. Cas. Fed. 76,160, 1991 U.S. App. LEXIS 26671, 1991 WL 136499
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 26, 1991
Docket91-1056
StatusUnpublished

This text of 940 F.2d 678 (C.M. Moore Division K.S.H., Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.M. Moore Division K.S.H., Inc. v. The United States, 940 F.2d 678, 37 Cont. Cas. Fed. 76,160, 1991 U.S. App. LEXIS 26671, 1991 WL 136499 (Fed. Cir. 1991).

Opinion

940 F.2d 678

37 Cont.Cas.Fed. (CCH) 76,160

Unpublished Disposition
NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
C.M. MOORE DIVISION K.S.H., INC., Appellant,
v.
The UNITED STATES, Appellee.

No. 91-1056.

United States Court of Appeals, Federal Circuit.

July 26, 1991.

Before ARCHER, Circuit Judge, COWEN, Senior Circuit Judge, and MAYER, Circuit Judge.

DECISION

COWEN, Senior Circuit Judge.

The appellant (Moore) appeals from the quantum decision of the Postal Service Board of Contract Appeals (Board), which granted Moore recovery in the amount of $2,978.77 on its certified claim of $494,007.98 against the United States Postal Service (Postal Service or agency) for breach of contract. The Board also granted the Postal Service recovery for the difference between the sum of $56,184.01 which the contracting officer had paid Moore and the $2,987.77 awarded Moore by the Board. C.M. Moore Division K.S.H., Inc., PSBCA No. 2208, 90-3 BCA p 23,174, July 30, 1990, (hereinafter, "Moore II "). We reverse-in-part, affirm-in-part, and remand the case to the Board for further proceedings in accordance with this opinion.

OPINION

* Background

On February 20, 1981, Moore and the Postal Service entered into a contract for the production of plastic letter trays, using injection molds to be furnished by the Postal Service. Initially, the Postal Service furnished Moore with three 2933 molds and later, at Moore's request, the Service supplied three 3051 molds. The Postal Service was aware that Moore planned to use standard size 450- and 500-ton molding machines to perform the contract. Moore encountered substantial production difficulties in using the molds furnished by the Postal Service and at the completion of the contract, filed a claim for breach of contract with the contracting officer. In the initial appeal from his decision, the Board rendered its entitlement decision, C.M. Moore Division K.S.H., Inc., PSBCA No. 1131, 85-2 BCA p 18,110, May 14, 1985, aff'd on recon., 86-1 BCA p 18,573, Nov. 25, 1985, aff'd, 818 F.2d 874 (Fed.Cir.1987), (hereinafter Moore I ).

In Moore I, the Board held that the contractor would be entitled to recover damages, if proved, because of the following:

(1) The Postal Service's failure to disclose its superior knowledge that unless modified, the molds furnished by the agency would cause production problems, and (2) the agency's failure to disclose its special knowledge that the trays which it proposed to furnish had an inherent design deficiency which caused bottom warpage and tray rejection.

II

The Unmodified Mold Issue

There is a sharp dispute between the parties regarding the correct interpretation of the Board's entitlement (Moore I ) decision. We rely on the Board's statement (A71) that its holding regarding superior knowledge is based on its Findings 41-48 in Moore I. We summarize those findings deemed most pertinent to the issue:

1. On July 23, 1980, the Postal Service observed a molding trial run by Manton Industries (Manton), a contractor who was then undertaking to perform a similar contract for the manufacture of plastic trays, and as a result, the Postal Service concluded that the 500-ton molding machine used by Manton did not have sufficient clamping pressure. (A37, F.O.F. 42).1

2. On September 10, 1980, Manton submitted a proposal to modify the molds furnished by the agency by adding ejectors on the stationary half and spring loading the core. He had already modified two of the 3051 molds on his own initiative. (A38, F.O.F. 43.)

3. In an internal memorandum of November 3, 1980, the Postal Service's Research and Development Laboratories concluded that the 500-ton molding machine used by Manton was inadequate for manufacturing the trays and caused release and stability problems, extending cycle time; that while Manton's machine might require modifications, these would not be necessary for machines with a 750-or 1000-ton clamping pressure. It was also recommended that the Postal Service should not contract for any further work on the molds, but should make future bidders responsible for any modifications or refurbishment which would be necessary to produce acceptable trays, since these bidders would be given the opportunity to inspect the molds before bidding. Therefore, the Postal Service made no modification of any of the molds. (A38-39, F.O.F. 44).

4. Before awarding the contract, the Postal Service knew that Moore intended to use two molding machines with clamping pressures of 450- and 500-tons, but the Service did not disclose the agency's prior knowledge that the machines which Moore intended to use were inadequate for molding the trays without the modifications proposed by Manton. (A39-40, F.O.F. 46).

5. Moore's 450- and 500-ton machines were standard machines for molding the trays, but based on the Postal Service's own observations and conclusions, the Board found that Moore's use of these small machines may have caused release and stability problems which would not have been present with a larger machine. (A39-40, F.O.F. 46-47).

Based on these findings the Board concluded that:

Respondent was aware, before awarding the subject contract that Appellant planned on using 450- and 500-ton molding machines and contemplated a 60-second cycle time. However, despite a concern that Appellant had underbid, it did not disclose its knowledge that, without modification, use of the 2933 molds on these machines could be expected to cause stability and release problems, extending cycle time (F.O.F. 9, 10, 45, and 47, supra ).

We conclude that these facts conform to the elements of "superior knowledge" set forth in section C of this decision. Considered as a whole, the record reflects that Respondent possessed special information not reasonably available to Appellant other than through disclosure. (A60.)

In applying its entitlement decision to its quantum decision, the Board ignored material and important findings made by a preceding board in Moore I and limited the Postal Service's liability by holding that the superior knowledge withheld by the Postal Service consisted only of the modification to the molds proposed by Manton in its letter of September 10, 1980. We agree with Moore that the Board thereby committed reversible error, which resulted in the Board's decision that Moore was entitled to recover nothing on this portion of its claim.

The superior knowledge which the Postal Service failed to disclose was not only the specific mold modifications proposed by Manton.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
940 F.2d 678, 37 Cont. Cas. Fed. 76,160, 1991 U.S. App. LEXIS 26671, 1991 WL 136499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cm-moore-division-ksh-inc-v-the-united-states-cafc-1991.