Clint Casto v. Kanawha County Commission

CourtWest Virginia Supreme Court
DecidedApril 17, 2015
Docket14-0683
StatusPublished

This text of Clint Casto v. Kanawha County Commission (Clint Casto v. Kanawha County Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clint Casto v. Kanawha County Commission, (W. Va. 2015).

Opinion

STATE OF WEST VIRGINIA

SUPREME COURT OF APPEALS

Clint Casto, FILED Petitioner Below, Petitioner April 17, 2015 RORY L. PERRY II, CLERK vs) No. 14-0683 (Kanawha County 14-AA-14) SUPREME COURT OF APPEALS OF WEST VIRGINIA

Kanawha County Commission, Respondent Below, Respondent

MEMORANDUM DECISION Petitioner Clint Casto, appearing pro se, appeals two orders of the Circuit Court of Kanawha County. In the first order, entered April 30, 2014, the circuit court denied petitioner’s petition for writ of certiorari challenging Respondent Kanawha County Commission’s January 9, 2014, order denying petitioner’s appeal of the site approval for a cell phone tower adjacent to his property. In the second order, entered June 17, 2014, the circuit court denied petitioner’s motion for reconsideration of its April 30, 2014, order.1 Respondent, by counsel Andrew T. Gunnoe and Michael W. Taylor, filed a response.

The Court has considered the parties’ briefs and the record on appeal. The facts and legal arguments are adequately presented, and the decisional process would not be significantly aided by oral argument. Upon consideration of the standard of review, the briefs, and the record presented, the Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the circuit court’s order is appropriate under Rule 21 of the Rules of Appellate Procedure. Petitioner’s property lies 156 feet from a site that has been approved by the Kanawha County Planning Commission (“Planning Commission”) for a new cell phone tower in the Big

1 Respondent argues that petitioner may appeal only the circuit court’s June 17, 2014, order denying his motion for reconsideration of its April 30, 2014, order because petitioner did not file a separate notice of appeal as to the April 30, 2014, order and that petitioner’s motion for reconsideration pursuant to Rule 60(b) of the West Virginia Rules of Civil Procedure did not toll the running of the appeal time as to that order. Pursuant to Rule 5(b) of the West Virginia Rules of Appellate Procedure, a party must file his notice of appeal within thirty days of the entry of the order he desires to appeal, and, pursuant to Rule 5(f), must perfect his appeal within four months of the order entry. Of these two time periods, only the time frame in which to perfect an appeal is jurisdictional. See W.Va. Code § 58-5-4; W. Va. Dept. of Energy v. Hobet Min. and Const. Co., 178 W.Va. 262, 264, 358 S.E.2d 823, 825 (1987). Pursuant to this Court’s July 21, 2014, scheduling order, the deadline for perfecting the appeal was October 20, 2014. Because petitioner perfected the appeal as directed in this Court’s scheduling order, we find that the appeal of both orders is timely. 1 Chimney area of Kanawha County. Beacon Towers-VA, LLC (“Beacon Towers”) will construct and own the tower, while AT&T Wireless (“AT&T”) will be its tenant and place antenna equipment on the tower to provide improved cellular service.

The Planning Commission held the first of two public hearings on Beacon Towers’ application for the cell phone tower on September 11, 2013. Petitioner and a neighbor, John Coulter, spoke against approving Beacon Towers’ application. Specifically, Mr. Coulter noted numerous discrepancies within the application. The Planning Commission continued the hearing on the application so that Beacon Towers could make necessary corrections.

The Planning Commission held its second public hearing on the application for a new cell phone tower on October 9, 2013. At the October 9, 2013, hearing, Sammy Black represented Beacon Towers and stated that all of the discrepancies within its application had been corrected. Four area residents including petitioner, petitioner’s mother, and Mr. Coulter spoke against approving the tower, while three others spoke in favor of the tower. One of the persons speaking in favor of the tower was Ashley Meadows, who stated that a new cell phone tower would increase the safety of her and her young daughter. Ms. Meadows stated that when she had an automobile accident two years prior, the lack of cell phone coverage caused her to have to walk with her daughter a number of miles in order to obtain help. Following the hearing, the Planning Commission approved Beacon Towers’ application for a new cell phone tower in the Big Chimney area.

Petitioner appealed the approval of the new tower to respondent, which held a third public hearing on Beacon Towers’ application on December 19, 2013. At the December 19, 2013, hearing, an AT&T representative stated that the tower was necessary to improve and extend cellular phone service in the area. In response to a question from respondent’s president, a Beacon Towers representative confirmed the tower will be constructed according to its permit and the requirements of the Kanawha County Wireless Telecommunications Facilities Ordinance (“Ordinance”). Petitioner and Mr. Coulter again spoke against the tower, while Ms. Meadows and one other area resident advocated for the tower’s approval. Ms. Meadows repeated that after her automobile accident, she had to walk miles with her daughter to obtain help as a result of the lack of cell coverage. Respondent noted that while other persons did not speak individually, “when asked[,] various members of the public located in the back of the meeting expressed support for the tower.” Following the hearing, respondent voted to deny petitioner’s appeal and affirm the Planning Commission’s approval of the new cell phone tower. Petitioner filed a motion to have respondent reconsider its decision to affirm the tower’s approval. Respondent considered petitioner’s motion at its January 9, 2014, meeting. Respondent left its affirmation of the tower’s approval undisturbed.

In its written order denying petitioner’s appeal, dated January 9, 2014, respondent made the following conclusions:

5. After holding three public hearings on this matter, it appears the primary argument of those in opposition to the tower is that increased coverage and service is not needed in the Big Chimney area. Based on the representations 2 of AT&T, Beacon Towers, and statements of several local residents, [respondent] finds that increased coverage and service is needed in the area surrounding the cell tower.

6. That “perceived health risks” as set forth in the Petition for Appeal, and as voiced by those in opposition during the public meeting, are not a sufficient basis to deny this application.

7. The sentiment that this cell tower will be an unsightly or visually unappealing structure is not a sufficient reason to deny the application. Likewise, [respondent] finds that this tower will not have an unreasonable adverse impact on the scenic resources within Kanawha County.

8. That new wireless communications technologies may be available is not a sufficient reason to deny the application.

9. Upon review, [respondent] finds that the application of Beacon Towers meets the rigorous requirements for approval as set forth in the [Ordinance].

10. [Respondent] finds that the Petition for Appeal contains no basis on which to deny the tower application of Beacon Towers.

11. For the above reasons, the Petition for Appeal is DENIED. The decision of the [Planning Commission] approving the application of Beacon Towers is AFFIRMED.

On February 4, 2014, petitioner filed a petition for writ of certiorari in the Circuit Court of Kanawha County challenging respondent’s decision to affirm the Planning Commission’s approval of a new cell phone tower.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Virginia Department of Energy v. Hobet Mining & Construction Co.
358 S.E.2d 823 (West Virginia Supreme Court, 1987)
Wolfe v. Forbes
217 S.E.2d 899 (West Virginia Supreme Court, 1975)
Powderidge Unit Owners Ass'n v. Highland Properties, Ltd.
474 S.E.2d 872 (West Virginia Supreme Court, 1996)
Harry Kaufman & Gold Construction Co. v. Planning & Zoning Comm.
298 S.E.2d 148 (West Virginia Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Clint Casto v. Kanawha County Commission, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clint-casto-v-kanawha-county-commission-wva-2015.