Cleveland Thermal Energy v. Cei, Unpublished Decision (8-1-2002)

CourtOhio Court of Appeals
DecidedAugust 1, 2002
DocketNo. 80312.
StatusUnpublished

This text of Cleveland Thermal Energy v. Cei, Unpublished Decision (8-1-2002) (Cleveland Thermal Energy v. Cei, Unpublished Decision (8-1-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland Thermal Energy v. Cei, Unpublished Decision (8-1-2002), (Ohio Ct. App. 2002).

Opinion

JOURNAL ENTRY AND OPINION
This is an appeal from a judgment, entered after a bench trial before Judge Nancy Margaret Russo, that granted declaratory and injunctive relief to appellee, Cleveland Thermal Energy Corporation (CTEC). Appellant Cleveland Electric Illuminating Company (CEI) claims it was error to conclude it did not have an arbitrable contract claim against CTEC, in ruling alternatively that it had waived its right to arbitrate, and in enjoining it from demanding arbitration on its contract claim. Although the judge erred in finding the parties did not agree to arbitrate, we agree that CEI waived its right to arbitrate the current dispute, and affirm the judge's order to the extent that it enjoins CEI from arbitrating that dispute.

In December of 1987, CEI sold CTEC a steam heating system serving the downtown Cleveland area but retained ownership of an electrical network that shared underground space with the steam system's distribution pipes. Because of the shared space, the electrical network sometimes incurs damage from steam leaks, and the contract of purchase included a section outlining the parties' rights and obligations as to liability for those damages. Section 6.02 of the contract states:

Seller and Purchaser acknowledge that (i) in certain locations distribution pipes for the System1 share space with the Seller's electricity transmission system (the `Electricity Network'), (ii) leaks from the System can damage the Electricity Network and (iii) Seller instituted a program to upgrade the Electricity Network in order to protect the Electricity Network from leaks in certain locations from the System (the `Upgrades').

Any damage to the Electricity Network caused by the System prior to the closing date or to the Upgrades for a period of two (2) years after the Closing Date will be the responsibility of Seller and any damage to the Electricity Network caused by leaks from the System after the Closing Date will be the responsibility of the Purchaser, other than (i) to the Upgrades which, for a period of two (2) years from the Closing Date, will be the responsibility of Seller, and (ii) damage occurring at any of the hotspots listed on Exhibit `W' annexed hereto, for which Seller and Purchaser shall bear equal responsibility for a period of two (2) years from the Closing Date. Thereafter, Purchaser shall bear sole responsibility for damage to the Electricity Network caused by leaks from the System. Other than as otherwise provided with respect to the Upgrades and the hotspots listed on Exhibit `W', it is agreed that for purposes of this Section 6.02, the existence of wear and tear in the System and the Electricity Network prior to the Closing Date will not relieve the Purchaser from responsibility for leaks after the Closing Date.

The parties agree that the two year period after the Closing Date has passed, and that the current question concerns the interpretation of the thereafter clause requiring CTEC to bear sole responsibility for damage to the Electricity Network caused by leaks from the System. On March 1, 1999, CEI filed a complaint for damages in the common pleas court, alleging that in October 1998 a steam leak occurred beneath Superior Avenue between East 17th Street and East 18th Street that damaged its electrical network, and that CTEC was liable in both contract and negligence.

In its answer CTEC denied liability and alleged as an affirmative defense that the common pleas court lacked jurisdiction over the contract claim because the contract contained a mandatory arbitration clause. The arbitration provision, Section 11.10 of the contract, called for arbitration of [a]ny controversy, claim or dispute arising out of or relating to this Agreement * * * or the interpretation or breach thereof[.] CTEC, however, did not demand arbitration or request a stay under R.C. 2711.02.2

CEI voluntarily dismissed its complaint on August 13, 1999, and filed a demand for arbitration on September 1, 1999. CTEC then filed the declaratory judgment complaint at issue here, and sought a determination that CEI's claim for damages under Section 6.02 of the contract was not subject to arbitration or that CEI waived arbitration of its contract claim with respect to the event at issue. Count three of the complaint requested a pre-emptive interpretation of Section 6.02 in the event the judge found the dispute subject to arbitration, and requested reformation of the contract based on mutual mistake if the judge ruled that the plain language of Section 6.02 obligated CTEC to pay for all damage to the electrical network caused by steam leaks.

The judge granted CTEC a preliminary injunction to prevent the arbitration from going forward while its declaratory judgment action was pending. On August 14, 2000, after the preliminary injunction but prior to trial, CEI filed an amended arbitration claim, in which it apparently abandoned its contractual claim for damages stemming from the October 1998 events, and instead requested a general ruling to resolve the interpretational dispute that had arisen under Section 6.02. On September 29, 2000, CEI refiled the complaint it had dismissed under Civ.R. 41(A)(1) because the statute of limitations on its negligence claim was set to expire.3 The complaint again asserted negligence and contract theories of recovery, but added a paragraph stating that it was alleging the contract action only in order to preserve the claim pending resolution of the declaratory judgment action.

The declaratory judgment action was tried to the judge on December 18 and 20, 2000. She granted directed verdicts in CEI's favor on counts three and four4 of CTEC's complaint and, on August 31, 2001, after the parties submitted post-trial briefs and proposals, ruled in CTEC's favor on the remaining issues.

In her findings of fact and conclusions of law, the judge repeated her earlier finding, made in the preliminary injunction ruling, that Section 6.02 was ambiguous, and thus cannot clearly exhibit an agreement to arbitration. She also found, however, that Section 6.02 did not make CTEC contractually liable for damages to the electrical network caused by steam leaks. In the alternative, the judge found that CEI had waived its right to demand arbitration on the underlying steam leak claim when it abandoned the claim in its amended demand for arbitration and refiled its previously dismissed complaint. In its grant of relief, the judge stated that Section 6.02 of the Agreement does not create special causes of action and is ambiguous. * * * CEI is permanently enjoined from arbitrating this cause of action. Finally, the judge awarded costs to CTEC pursuant to its request for relief, but did not award attorney's fees.

The first two of CEI's four assignments of error state:

I. The Trial Court Erred by Refusing Arbitration When the Parties Clearly Agreed to Arbitrate Pursuant to the All Encompassing Arbitration Clause, Article 11.10, of the Agreement.

II. The Trial Court Erred by Ruling on the Merits of Defendant-appellant's Contractual Claim Both in its Preliminary Injunction Order and in the Final Order.

These assignments of error are inextricably linked in the judge's ruling. Her determination that the parties did not agree to arbitrate CTEC's contractual obligation under Section 6.02 is possible only after the determination that CTEC had no contractual obligation to pay damages under that section.

The interpretation of unambiguous written contract terms is a matter of law that we review de novo.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Standard Roofing Co. v. John G. Johnson & Sons Construction Co.
376 N.E.2d 610 (Ohio Court of Appeals, 1977)
Andrews v. Ohio State Teachers Retirement System Board
404 N.E.2d 747 (Ohio Supreme Court, 1980)
Hounshell v. American States Insurance
424 N.E.2d 311 (Ohio Supreme Court, 1981)
Nationwide Mutual Fire Insurance v. Guman Bros. Farm
652 N.E.2d 684 (Ohio Supreme Court, 1995)
Council of Smaller Enterprises v. Gates, McDonald & Co.
687 N.E.2d 1352 (Ohio Supreme Court, 1998)
ABM Farms, Inc. v. Woods
692 N.E.2d 574 (Ohio Supreme Court, 1998)
Williams v. Aetna Finance Co.
83 Ohio St. 3d 464 (Ohio Supreme Court, 1998)
Nationwide Mut. Fire Ins. Co. v. Guman Bros. Farm
1995 Ohio 214 (Ohio Supreme Court, 1995)
Williams v. Aetna Fin. Co.
1998 Ohio 294 (Ohio Supreme Court, 1998)
ABM Farms, Inc. v. Woods
1998 Ohio 612 (Ohio Supreme Court, 1998)
Council of Smaller Enterprises v. Gates, McDonald & Co.
1998 Ohio 172 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Cleveland Thermal Energy v. Cei, Unpublished Decision (8-1-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-thermal-energy-v-cei-unpublished-decision-8-1-2002-ohioctapp-2002.