Cleveland Electric Illuminating Co. v. Village of Mayfield

371 N.E.2d 567, 53 Ohio App. 2d 37, 23 P.U.R.4th 197, 7 Ohio Op. 3d 29, 1977 Ohio App. LEXIS 6973
CourtOhio Court of Appeals
DecidedJuly 14, 1977
Docket36070 and 36074
StatusPublished
Cited by4 cases

This text of 371 N.E.2d 567 (Cleveland Electric Illuminating Co. v. Village of Mayfield) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland Electric Illuminating Co. v. Village of Mayfield, 371 N.E.2d 567, 53 Ohio App. 2d 37, 23 P.U.R.4th 197, 7 Ohio Op. 3d 29, 1977 Ohio App. LEXIS 6973 (Ohio Ct. App. 1977).

Opinion

Peyatel, J.

The Cleveland Electric Illuminating Company (CEI) is a regulated public utility which provides electric service throughout northeastern Ohio. It is constructing an electric transmission line and a substation which will convert electricity carried in bulk to voltages suitable for distribution to consumers in eastern Cuyahoga County along Interstate 271.

This project passes through a portion of the village of Mayfield (appellant herein) which was a non-charter municipality until January 1, 1975. The company is in the process of building through the village a 138 kv double circuit transmission line (known as the “Lark Line”) on single steel pole supporting structures and a dependent substation (known as the “Lark Substation”) to be located at the intersection of Interstate 271 and Wilson Mills Road. The project extends from Bedford Heights in the south to Eastlake in the north, running along 1-271, with a series of substations along the route. Its purpose is to answer the increasing needs for electric energy in the area.

In 1969, CEI approached the village officials concern *39 ing the location of the substation site. At the request of the village, the company selected the site at the intersection of 1-271 and Wilson Mills Road, The village had previously refused to issue a permit for a service (gas) station here (which was a permissible use) preferring to have the substation located at this site (which was a nonpermissible use) thus requiring a variance. Again, upon the advice of the village officials, the company and the landowner applied for a variance to allow for the construction of an electric substation at the site. The variance was granted in 1970 and provided that “all plans and specifications for all buildings and structures thereon shall be approved by the Planning and Zoning Commission and the Architectural Board of Review.”

After the variance was allowed the company purchased the property at a substantial cost. Since the location of the substation was to be on the east side of 1-271, CEI decided to build the transmission line which would serve the substation on the easterly side of the interstate area. Rights-of-way were then acquired along the route.

CEI also sought a permit from the village to cross certain streets with the transmission lines and such a permit was issued by the then mayor. At that time the company planned to energize the line at only 33 kv to provide relief to its existing overloads in the Mayfield area. However, the present construction is essentially the same as originally proposed.

In 1971, the plans for the proposed substation were submitted to the village for review by the village engineer. There were no requests for additional plans. The village engineer did suggest that the fence be covered with vinyl.

The record is not clear as to why, but a controversy arose over the construction of the transmission line itself. The village enacted an ordinance requiring underground construction. CEI contends that such construction would increase the cost from $400,000 a mile to $2,140,000-$2,750,-000 a mile or $4,500,000-$6,100,000 in the village of May-field without considering the termination structures which would add another million dollars to the cost. ' - '

The village then raised the question of the substation *40 location and its plans and enacted or amended ordinances affecting the construction of the project; thereupon, CEI instituted an action against the village of Mayfield to declare certain ordinances unreasonable etc., as well as seeking injunctive relief.

CEI brought this action on August 7,1974, seeking:

“(1) A declaration that certain ordinances of the village of Mayfield were unreasonable local regulations in conflict with Revised Code Section 4905.65 (the Ohio “Hot Wires Act”), which authorizes CEI to construct its Lark Transmission Line, together with its appurtenances thereto, in and through the village of Mayfield;
“(2) A declaration that CEI is not required to obtain additional permits, permissions, or other consents from the village of Mayfield or its officials or, alternatively, that the village or any proper official be required to issue any permits which may be required; and
“(3) A preliminary and permanent injunction against the village of Mayfield and its officers, agents and employees enjoining them from interfering with CEI’s construction and operation of the Lark Line and its appurtenances, including the Lark Substation, in and through the village of Mayfield.”

On September 5, 1974, the village of Mayfield filed its answer to the complaint asserting, among other defenses, that CEI failed to exhaust its administrative remedies, failed to obtain from the village of Mayfield certain building permits and permits for the cutting or removing of trees as required by law, and failed to obtain the consent of the village to construct a transmission line through the streets within the village of Mayfield.

On November 12, 1974, intervenor, the third party defendant-appellant Aintree Park Homeowners Association, Inc., filed a cross-complaint which asserted that the zoning variance issued by the Board of Zoning Appeals of the village of Mayfield on November 9, 1970, expressly authorizing the use of certain land within the village of Mayfield by CEI as an electrical substation, was without legal justification and invalid.

*41 The action was tried to the court without a jury in June of 1975. On January 15, 1976, the trial court entered a judgment in favor of CEI, finding that from all the evidence the requirements of R. C. 4905.65(B), the “Hot Wires Act,” were fully satisfied. The court declared that CEI was not required to obtain additional permits, permissions or other consents from the village and it enjoined the village from interfering with the construction and operation of the Lark Line, including the Lark substation. The court held that the Aintree Park Homeowner’s Association, Inc., and members of the class which it represented lacked standing to attack the November 9, 1970, use variance granted by the village of Mayfield Board of Zoning Appeals.

On January 20, 1976, the village of Mayfield filed a request for separate findings of fact and conclusions of law, pursuant to the provisions of Civil Eule 52. The findings of fact and conclusions of law were journalized on March 31, 1976.

The village of Mayfield filed its timely notice of appeal from the trial court’s judgment on February 13, 1976. Aintree Park Homeowner’s Association filed a timely notice of appeal as well. Both appeals have been consolidated herein.

The village of Mayfield, in Case No. 36074, assigns five errors, the first three of which will be treated jointly with assignment of error 1 of Aintree Park, in Case No. 36070.

The village of Mayfield assigns as error:

“1. The court’s finding that the requirements of Ohio Eevised Code Section 4905.65(B) were fulfilled by the plaintiff-appellee is contrary to the weight of the evidence.
“2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conkle v. Somc, Unpublished Decision (7-29-2005)
2005 Ohio 3965 (Ohio Court of Appeals, 2005)
Joseph v. Ohio Power Co.
546 N.E.2d 970 (Ohio Court of Appeals, 1988)
Angel v. United States
650 F. Supp. 434 (S.D. Ohio, 1986)
Cleveland Electric Illuminating Co. v. City of Lakewood
415 N.E.2d 297 (Ohio Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
371 N.E.2d 567, 53 Ohio App. 2d 37, 23 P.U.R.4th 197, 7 Ohio Op. 3d 29, 1977 Ohio App. LEXIS 6973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-electric-illuminating-co-v-village-of-mayfield-ohioctapp-1977.