Clayco Const. Co. v. THF Carondelet Dev., L.L.C.

105 S.W.3d 518, 2003 Mo. App. LEXIS 665, 2003 WL 21003543
CourtMissouri Court of Appeals
DecidedMay 6, 2003
DocketED 82232
StatusPublished
Cited by4 cases

This text of 105 S.W.3d 518 (Clayco Const. Co. v. THF Carondelet Dev., L.L.C.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clayco Const. Co. v. THF Carondelet Dev., L.L.C., 105 S.W.3d 518, 2003 Mo. App. LEXIS 665, 2003 WL 21003543 (Mo. Ct. App. 2003).

Opinion

*520 PAUL J. SIMON, Presiding Judge.

THF Carondelet Development, L.L.C. (THF) appeals the judgment denying its motion to dismiss the first amended petition filed by Clayco Construction Company, Inc. and Forum Studio, Inc. (Clayco) on grounds that the alleged contract upon which Clayco based its breach of contract claim contained a mandatory arbitration provision which divested the trial court of subject matter jurisdiction. Clayco has filed motions to dismiss the appeal for lack of an appealable order and for sanctions for prosecuting a frivolous appeal, which were ordered taken with the case.

On appeal, THF contends: (1) this Court has appellate jurisdiction to consider this appeal because THF’s motion to dismiss Clayco’s first amended petition sufficiently raised the issue of arbitration; and (2) the trial court erred in denying THF’s motion to dismiss Clayco’s first amended petition because the alleged contract contains a mandatory arbitration provision which divested the trial court of subject matter jurisdiction in that a motion to dismiss is the appropriate method for contesting the subject matter jurisdiction of the trial court when the alleged contract contains a mandatory arbitration provision and the motion to dismiss the first amended petition should be granted where the facts alleged, if proven, require submission of all claims to arbitration. For reasons hereinafter stated, we dismiss the appeal pursuant to Clayco’s motion and deny the motion for sanctions.

The record reveals that on November 1, 2002, Clayco filed its first amended petition alleging that it entered into a written Shell and Core Agreement with THF, dated March 10, 2000, for the design and construction of The Plaza in Clayton, a complex and comprehensive project consisting of an office building, retail space, a parking structure, and a thirty-story residential tower containing eighty-two condominium units. Clayco alleged also in its first amended petition that on March 8, 2001, Clayco and THF executed a letter of intent to serve as an award notification that Clayco was selected to be the design-build contractor for the tenant finish work for the condominium building. Michael Staenberg (Staenberg), the agent, manager and principal operating executive of THF, signed the award notification on behalf of THF. Clayco and THF agreed that they would execute a final contract, which would follow a standard form entitled “Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM” (Condominium Agreement). Clayco alleged THF and its counsel stated that the parties would perform in accordance with the Condominium Agreement and that the Condominium Agreement would be based on the following exhibits to be attached to the final contract: (1) master outline specification for standard units; (2) master stacking plan for standard units; (3) floor plans for each standard unit fisted in master stacking plan; (4) master turnover schedule for standard units; and (5) master detailed cost estimate for eighty-two standard units. Clayco alleged that it immediately began providing materials and services for the tenant finish work.

Clayco further alleged that THF, Staen-berg, and their lawyers fully negotiated the terms of the Condominium Agreement, dated July 20, 2001, and that this document was prepared in order to follow through on the representations made by THF and Staenberg at the time the award notification was signed. An authorized representative of Clayco executed the Condominium Agreement and forwarded it to THF and Staenberg on August 29, 2001.

Clayco alleged that Staenberg held the signed Condominium Agreement, but did *521 not execute it on behalf of THF and attempted to disavow it. Clayco and its subcontractors provided materials and services related to the design and construction of the condominiums pursuant to the terms of the Condominium Agreement, and THF accepted performance by Clayco and made payments to Clayco for work performed under the Condominium Agreement.

Clayco alleged further that throughout the project, THF repeatedly failed to meet its scheduled dates, known as “release dates,” for permitting work on the condominium units, providing finishes, and permitting Clayco to complete finish work on the units. As a result, THF prevented Clayco from completing construction of individual units in accordance with the orderly plan set forth in the Condominium Agreement. In addition, Clayco alleged that THF ordered that Clayco make a number of changes in the agreed work thereby delaying completion of the project and causing substantial increases in cost and that THF refused to execute appropriate change orders or to reimburse Clayco for the reasonable value of that work. When Clayco protested, THF took the position that since it never executed the Condominium Agreement, no contract existed, and THF refused to pay for work done by Clayco in reliance on that agreement.

Clayco alleged that in July, 2002, THF and Clayco met to negotiate a proposed settlement of their dispute, and THF agreed with Clayco to settle all disputes with respect to the Condominium Agreement. Staenberg represented that he would execute a final settlement agreement that included the agreed upon terms, once it was prepared by counsel. As agreed by the parties, Clayco instructed its counsel to draft a written document confirming the terms of the settlement agreement, for delivery to THF on July 29, 2002. On July 27, 2002, Staenberg informed his fellow investor, Alan Born-stein, that he did not intend to honor the settlement agreement. Still, on July 29, representatives of THF visited the offices of Clayco and reviewed confidential and proprietary subcontractor information that Clayco had agreed to provide to THF as part of the settlement agreement. Clayco delivered the written confirmation of the settlement to THF’s representatives for THF’s review and signature, but THF disavowed and repudiated the agreement to settle the disputes with Clayco.

Clayco incorporated by reference a copy of the Condominium Agreement into its first amended petition and attached it as Exhibit 2. The Condominium Agreement incorporates by reference AIA Document A201-1997 entitled “General Conditions of the Contract for Construction” (General Conditions), which is included as part of Exhibit 2 to Clayco’s first amended petition. Provision 4.6 of the General Conditions contains a mandatory arbitration provision, which states in pertinent part:

4.6 ARBITRATION
4.6.1 Any claim arising out of or related to the [Condominium Agreement] ... shall be subject to arbitration.
[[Image here]]

After settlement negotiations failed, Clayco filed the instant action, seeking damages for fraud and breach of contract. On November 13, 2002, THF filed a motion to dismiss Clayco’s first amended petition and a memorandum in support thereof in which THF argued that the trial court should dismiss the first amended petition pursuant to Rule 55.27 of the Missouri Rules of Civil Procedure for the following reasons: (1) the Condominium Agreement upon which Clayco bases its breach of contract claim incorporates by reference the General Conditions which contains a mandatory arbitration clause; (2) Clayco is *522

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ishmon v. St. Louis Board of Police Commissioners
415 S.W.3d 144 (Missouri Court of Appeals, 2013)
Fleming & Hall Administrators, Inc. v. Response Insurance Co.
195 S.W.3d 458 (Missouri Court of Appeals, 2006)
Kagan v. Master Home Products Ltd.
193 S.W.3d 401 (Missouri Court of Appeals, 2006)
Webb v. American Employers Group
684 N.W.2d 33 (Nebraska Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
105 S.W.3d 518, 2003 Mo. App. LEXIS 665, 2003 WL 21003543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clayco-const-co-v-thf-carondelet-dev-llc-moctapp-2003.