Clay v. Pennoyer Creek Improvement Co.

34 Mich. 204
CourtMichigan Supreme Court
DecidedJune 6, 1876
StatusPublished
Cited by20 cases

This text of 34 Mich. 204 (Clay v. Pennoyer Creek Improvement Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clay v. Pennoyer Creek Improvement Co., 34 Mich. 204 (Mich. 1876).

Opinion

Maeston, J:

Defendant in error is a corporation formed under ‘‘An act to authorize the formation of corporations for the purpose of improving the navigation of rivers,” approved April*. 5th, 1869, being chapter 85 of the Oomp. Laws.

Upon the 10th day of January, 1876, a petition was filed, on behalf of said corporation in the'probate court of Newaygocounty, praying the court to appoint three commissioners to> ascertain and determine whether it was necessary to the-public interests to take certain lands therein described, owned by David P. Clay, for the purpose proposed in said petition, and if so, to ascertain and determine the amount of damages; therefor.

The petition set forth the organization of the corporation, and that it ivas formed for the purpose of improvingPennoyer Creek; that the corporation had obtained the consent in writing of the governor and attorney general to the-proposed -improvement; that the necessary maps and plans; had been submitted to and approved by the board of control of St. Mary’s Falls Ship Canal; that in pursuance of their organization they had constructed three dams across, said creek, and had at great expense cleared the stream of certain obstructions, also where necessary the bed had been deepened and straightened; that the stream is, and was before such improvements were made, a navigable stream, but. that the practical navigation thereof was obstructed, which rendered it necessary to utilize and control the water in a lake at the head or source pf the stream; that there were large quantities of pine along and around said stream and lakes which could be most economically got to market in no other way, and that the improvements made and contemplated would benefit the entire stream and the navigation thereof; that the improvements proposed would affect certain therein described lands, the. property of said Clay, in that the water in said stream would be raised and backed up, and the use of said stream for water-power purposes be [206]*206lost to the owner of said lands, which would at times be •flooded, and that an easement therein or in a portion thereof was and would be necessary for the public use. The petition also alleged that they had attempted to agree with Clay upon the amount of compensation, but could not. Upon filing this petition, the 7th day of February, 1876, was fixed for the hearing thereof, and notice given by publication. At the time fixed, Clay appeared and filed objections to the jurisdiction of the court, which were overruled. An answer was then filed, a hearing had and commissioners appointed, when the proceedings were removed to this court by certiorari.

An objection was taken on the argument, that the writ of certiorari was improvidently issued, the order of the probate court being merely interlocutory. We do not so consider it. The appointment of the commissioners by the court was one of the essential steps in the case, and was, so far as that court' was concerned, final. The commissioners, after being appointed, proceed independent of the court in the performance of their duties, and after they have made the necessary examination and agreed upon a decision, they are to make and sign a report of their doings and file the same with the clerk of the court by which they were appointed, and which, without any action of the court whatever, is final and conclusive upon all persons ivho shall not, within fiftéen days thereafter, make and file with the clerk a motion to set the same aside. The proceedings upon this motion cannot well reach the question of their appointment. We think a party is not bound to wait, although he may do so, until after the commissioners have acted and made a report which has been confirmed, before testing the jurisdiction and power of the court to appoint them, but may do so at once upon the appointment having been made.

A number of interesting and important questions were raised an 1 discussed, but as there are fatal objections to be met with at the outset in this case, and as it would seem that additional legislation will be necessary in order to per-[207]*207feet the statute under which this corporation was organized, and the proposed improvement authorized, we' do not consider it proper to discuss all of them at this time, as they will likely be considered and removed should the legislature undertake to remedy the defects pointed out.

The act under which this corporation was formed, and the proceedings in this case taken, seems to contemplate t’he improvement of navigable rivers,' and not the creation of navigable rivers out of creeks or streams which could not in their natural condition be considered “navigable in any sense of the term. The title of the-act is to authorize the formation of corporations for the improvement of navigable rivers.” The first section authorizes persons to associate for the purpose of improving the navigation of any river in this state. Indeed, this question or idea of improvement of navigable rivers runs all through the act. Whether, therefore, it applies to streams strictly private, might become important, as the powers granted by such statutes are not usually to be enlarged by intendment. But this is a question we need not pass upon in the present case.

The petition is jurisdictional, and must set forth all the facts necessary to show that this corporation is authorized to make the proposed improvement, before it can ask for the appointment of commissioners to condemn lands for such purposes. It must show, or at least allege, the organization of a corporation; that it has obtained the approval and assent of the necessary officers and boards to make the proposed improvements; that certain lands are necessary in making such improvements; that they have attempted to treat with the owners of such lands and have been unable to agree, and therefore ask for the appointment of commissioners. And a failure to allege that they have -taken all these necessary steps will be fatal, and will give the court no jurisdiction in the premises. The petition upon its face must show a substantial compliance with and adherence to the course prescribed by the constitution and statutes relat[208]*208i?ig thereto. — Kroop v. Forman, 31 Mich., 145; Powers’ Appeal, 29 Id., 504; Cooley’s Const, him., 528.

The petition alleges that “the said Penn oyer ereelc is a navigable stream, and was such before the improvementshereinbefore'enumerated werema’do;” that the contemplated improvements are the deepening and straightening the stream and the construction of three dams across the stream, which will cause the water in said stream to be raised and backed up, and the use of the stream for a water-power be lost to the’ owner of the lands, and that said lands or portions thereof will sometimes be flooded. It being thus alleged that Pennoyer creek was a navigable stream, the petition should have alleged affirmatively, that the corporation had obtained authority from the board of supervisors of Newaygo county to dam this stream. The constitution is clear and emphatic that “no navigable stream in this state shall be bridged or dammed without authority from the board of supervisors -of the proper county under the provisions oí law.” —Article XYIII., § 4. There is no allegation that such authority was obtained. The petition does set forth the assent of the governor and attorney general, and the approval of the board of control of the St. Mary’s Falls Ship Canal, as required by tlie act. But this assent and approval is something additional to the authority of the board of supervisors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lapeer County Clerk v. Lapeer Circuit Court
665 N.W.2d 452 (Michigan Supreme Court, 2003)
Midland Township v. State Boundary Commission
236 N.W.2d 551 (Michigan Court of Appeals, 1975)
Advisory Opinion Re Constitutionality of 1972 PA 294
1972 PA 294 (Michigan Supreme Court, 1973)
Alan v. Wayne County
200 N.W.2d 628 (Michigan Supreme Court, 1972)
Department of Conservation v. Connor
32 N.W.2d 90 (Michigan Supreme Court, 1948)
Murphy v. Metropolitan Utilities District
255 N.W. 20 (Nebraska Supreme Court, 1934)
City of Allegan v. Iosco Land Co.
236 N.W. 863 (Michigan Supreme Court, 1931)
City of Big Rapids v. Big Rapids Furniture Manfg. Co.
177 N.W. 284 (Michigan Supreme Court, 1920)
Hunt v. City of Montevideo
161 N.W. 154 (Supreme Court of Minnesota, 1917)
Detroit United Railway v. Barnes Paper Co.
138 N.W. 211 (Michigan Supreme Court, 1912)
United States Gypsum Co. v. Kent Circuit Judge
114 N.W. 666 (Michigan Supreme Court, 1908)
Valentine ex rel. Dudley v. Berrien Springs Water-Power Co.
87 N.W. 370 (Michigan Supreme Court, 1901)
Simpson v. Simpson
26 N.W. 285 (Michigan Supreme Court, 1886)

Cite This Page — Counsel Stack

Bluebook (online)
34 Mich. 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clay-v-pennoyer-creek-improvement-co-mich-1876.