C.L. Maddox, Incorporated v. Coalfield Services, Incorporated

51 F.3d 76, 1995 U.S. App. LEXIS 5811, 1995 WL 120804
Court of Appeals for the Seventh Circuit·Decided March 22, 1995·No. 94-2613·Published·Cited by 19 cases

Opinion

POSNER, Chief Judge.

The plaintiff, C.L. Maddox, Inc., had on January 18,1991, made a contract with Zeig-ler/Old Ben Coal Company that required Maddox to demolish a loading facility in one of the coal company’s mines, haul the demolished steel structure to the surface, fabricate a new loading facility for installation underground in the place of the demolished one, and install the new facility. Maddox decided to subcontract all of the job but the fabrication of the new facility. It asked the defendant, Coalfield Services, Inc., whether it would be interested in the subcontract. In February 1991, Coalfield’s president met with Maddox’s president for a few hours at the site of the mine, and at the end of the meeting he offered to do the job for $230,000. He didn’t think it necessary to go underground and inspect the facility, because Coalfield had done this sort of work before. He was confident that, provided his crew was allowed to work around the clock, he could do the job in three weeks, as Maddox wished because of its commitments to Zeigler/Old Ben.

Coalfield’s crew traveled to the mine on March 19 and on the same day Coalfield faxed a proposed contract to Maddox. The contract specified a price of $230,000 and completion within three weeks, provided that Coalfield was allowed to work day and night seven days a week. It also required biweekly progress payments based on Coalfield’s progress toward completion. There are other provisions but they are of a boilerplate character immaterial to this appeal. Maddox’s president called Coalfield’s president the same day, requesting the inclusion of a noncompetition clause; this was done by return fax and Maddox’s president told Coalfield’s president that he would sign the proposal as amended. He never did.

*78 Coalfield’s crew began work the next day, March 20. The crew encountered some difficulties in the work and, as the days passed, made slower progress than expected. Coalfield meanwhile was making repeated requests to Maddox to sign the proposal, receiving no replies, and getting nervous. Early in the morning of April '8, Coalfield ordered its crew to stop work and come to the surface with its tools and equipment. A few hours later it faxed Maddox a letter stating that it would not proceed with the work without acceptance by Maddox of the proposed contract and payment of an invoice for $103,500 enclosed with the letter. This was 45 percent of the contract price; Coalfield claimed that its crew was 45 percent of the way to completion of the job.

Maddox replied by fax the same day. Mr. Maddox was apologetic about not having responded to the proposed contract sooner. He said that although according to information he had received from his project superintendent “your 45% completion is a little high, ... we shall in good faith accept the 45% completion figure and pay accordingly less 10% retention.” But he appeared to condition this promise on Coalfield’s signing an “acceptance letter” that Maddox enclosed. (And there is evidence that Mr. Maddox told Coalfield’s president this in a phone conversation.) That letter agreed to most of the provisions in Coalfield’s proposal of March 19 but extended the deadline for completion of the work from three weeks to four in recognition of the fact that the crew had not been permitted to work on Sundays after all (because of “union disgruntlement,” according to Coalfield’s lawyer). Of much greater significance it added a liquidated-damages clause requiring Coalfield to pay Maddox $1,000 for every day that the job took beyond the four-week deadline. Coalfield balked. It had been working for three weeks already and the job was less than half finished. It estimated that completion would take another five or six weeks, which is to say four or five weeks beyond the new deadline fixed by Maddox, implying a potential liability for liquidated damages of $35,000 if it agreed to Maddox’s terms. Coalfield faxed a letter back to Maddox on April 8 rejecting the acceptance letter and refusing to complete the project unless Maddox not only paid the $103,500 invoice but also accepted the terms in Coalfield’s offer1 of May 19, with an exception for the date of completion. “The original schedule can not be met due to work stoppages and delays beyond our control, and also because of the unexpected thickness of liners in existing equipment and bins. With no additional delays, the project will take approximately five (5) to six (6) weeks.” The letter implicitly acknowledges that Coalfield’s ' action in removing the crew from the underground work site would cause a further delay, for it reads, “if you decide to accept the above conditions, we will proceed with work starting April 16, 1991” — eight days from the date of the fax.

Maddox replied that if Coalfield did not resume work by April 9, it would be in breach of their contract. Coalfield never resumed the work, and Maddox brought this suit, a diversity suit governed by the contract law of Illinois, for the damages it incurred when, Coalfield having abandoned the job midway to completion, Maddox had to pay to have it completed by another contractor in time to avoid a breach of its contract with Zeigler/Old Ben. Coalfield counterclaimed for the contract price multiplied by the fraction of the job that it had completed, the $103,500 (.45 x $230,000).

Both parties moved for summary judgment. Coalfield’s motion was based on the surprising ground that it had had no contract with Maddox. The district judge granted Maddox’s motion for summary judgment and denied Coalfield’s. It held that there had been a contract, as shown by Coalfield’s action in performing for three weeks and completing, as it conceded it had, 45 percent of the project, and that Coalfield had broken the contract by walking off the job on April 8. The judge directed Maddox to submit documentation of its damages for Coalfield’s breach. Later the judge changed his mind and agreed with Coalfield that he had jumped the gun in deciding that Coalfield had been the one to break the contract. The parties then consented to try the issue before a magistrate judge, who after a bench trial found that Maddox, not Coalfield, had broken the contract. Concerning damages for this *79 breach, the magistrate judge considered himself bound by what he considered to be the finding already made by the district judge that Coalfield had completed 45 percent of the work. He therefore awarded Coalfield the $103,500 that it was seeking for its partial performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

C.L. Maddox, Incorporated v. Coalfield Services, Incorporated, 51 F.3d 76, 1995 U.S. App. LEXIS 5811, 1995 WL 120804 (7th Cir. 1995).

51 F.3d 76 (C.L. Maddox, Incorporated v. Coalfield Services, Incorporated) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harborview Office Center, LLC v. Nash
2011 WI App 109 (Court of Appeals of Wisconsin, 2011)
Arlington LF, LLC v. Arlington Hospitality, Inc.
637 F.3d 706 (Seventh Circuit, 2011)
Hoppe v. GREAT WESTERN BUSINESS SERVICES, LLC
536 F. Supp. 2d 888 (N.D. Illinois, 2008)
ARC Ecology v. U.S. Dept. of Air Force
411 F.3d 1092 (Ninth Circuit, 2005)
Koch Materials Co. v. Shore Slurry Seal, Inc.
205 F. Supp. 2d 324 (D. New Jersey, 2002)
Timothy Herremans v. Carrera Designs, Inc.
157 F.3d 1118 (Seventh Circuit, 1998)
In Re Kids Creek Partners, L.P.
220 B.R. 963 (N.D. Illinois, 1998)
Curtis Lee Pride v. Howard Peters, III
72 F.3d 132 (Seventh Circuit, 1995)