C.J. Hughes Constr. Co. v. Eqm Gathering Opco, LLC

358 F. Supp. 3d 486
CourtDistrict Court, W.D. Pennsylvania
DecidedFebruary 14, 2019
DocketCivil Action No. 2:18-cv-168
StatusPublished
Cited by2 cases

This text of 358 F. Supp. 3d 486 (C.J. Hughes Constr. Co. v. Eqm Gathering Opco, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.J. Hughes Constr. Co. v. Eqm Gathering Opco, LLC, 358 F. Supp. 3d 486 (W.D. Pa. 2019).

Opinion

Re: ECF No. 35

PETER J. PHIPPS, UNITED STATES DISTRICT JUDGE

This dispute arises over responses to eight requests for admission that were served 18 days late. By operation of Federal Rule of Civil Procedure 36(a)(3), untimely responses to requests for admission constitute admissions. The issue here is not whether the requests for admission are admitted - they are presently - but whether a motion to withdraw and amend those admissions through subsequent responses should be granted. For the reasons set forth below and on the facts presented here, the motion to withdraw and amend is granted.

BACKGROUND

This discovery dispute takes place in the context of a lawsuit over the construction of a gas pipeline. Defendant EQM Gathering OPCO, LLC, a Delaware Corporation, with a principal place of business in Pittsburgh, Pennsylvania, solicited bids for two pipeline construction projects, referred to as Segment A and Segment D. See Compl. ¶¶ 5-8, ECF No. 1 (Feb. 6, 2018); id. ¶ 2; Answer ¶ 2, ECF No. 20 (July 5, 2018). Plaintiff C.J. Hughes Construction Company, Inc., a West Virginia corporation with a principal place of business in Huntington, West Virginia, submitted bids for those projects, and defendant issued purchase orders for those pipeline construction projects to plaintiff. See Compl. ¶¶ 9-11; id. ¶ 1; Answer ¶ 1. Plaintiff claims that the purchase orders entailed more labor and expense than indicated on defendant's requests for proposals: the pipeline projects required more fittings than specified; the pipe walls were thicker than represented; and defendant's inspectors imposed additional requirements. See Compl. ¶¶ 12-24. With an amount in controversy in excess of $ 75,000, plaintiff commenced this suit under diversity jurisdiction, see 28 U.S.C. § 1332, for breach of contract, for violation of the Pennsylvania Contractor and Subcontractor Payment Act, and alternatively for unjust enrichment. See Compl. ¶¶ 25-54. Defendant raises several defenses, going to the scope of plaintiff's obligations under the purchase orders as well as to the quality of the work plaintiff provided. See Answer, Aff. Def. ¶¶ 1-16.

Discovery in this case is ongoing. Although it was originally scheduled to close on February 4, 2019, upon defendant's motion, ECF No. 33, discovery has been extended by 45 days, until March 21, 2019. See Order, ECF No. 34 (Dec. 18, 2018).

The present controversy stems from defendant's untimely response to eight requests for admission served by plaintiff on November 1, 2018. See Def.'s Mot., Ex. 1, ECF No. 35-1 (Dec. 21, 2018). Defendant's responses to those requests for admission were due by December 3, 2018. See Fed. R. Civ. P. 36(a)(3). A week after the responses were due, defendant's counsel contacted plaintiff's counsel to request an extension of time. The next day, plaintiff's counsel declined and noted that untimely responses to requests for admission constitute *488admissions. Ten days later, defendant served responses to the eight requests for admission on plaintiff, see Def.'s Mot., Ex. 2, ECF No. 35-2 (Dec. 21, 2018), and filed a motion to withdraw or amend its deemed admission, ECF No. 35.

The issue has been fully briefed. See Def.'s Mot., ECF No. 35; Pl.'s Opp., ECF No. 36 (Jan. 4, 2019); Def.'s Reply, ECF No. 40 (Jan. 8, 2019); Pl.'s Surreply, ECF No. 43 (Jan. 14, 2019). In their briefing, the parties present several issues.

Defendant asks the Court for permission to amend its responses. Defendant starts by contextualizing the missed deadline, culminating in the following explanation:

Defendant['s] failure to respond to the Requests to Admit in a timely manner was due to the inadvertent failure of counsel for the Defendant to docket the response date, together with commencement of travel within 2 days of receipt of the Requests to Admit, and 22 days of travel and the observance of the Thanksgiving holiday during that period.

Def.'s. Mot. at 2, ¶ 10, ECF No. 35. Defendant also contends that the merits of the lawsuit are implicated, with the requests for admission covering more than 90% of plaintiff's total claim. See Def.'s Reply at 2, ECF No. 40. In addition, defendant argues that plaintiff is not prejudiced by the 18-day delay because "nothing occurred during the interval between the due date and the service of the Responses ... and discovery is not closed." Id. at 6. In short, defendant submits that "the short delay in receipt of the responses to the Requests to Admit does not prejudice the Plaintiff, and will promote the presentation of the merits of the disputes presented in this lawsuit." Def.'s. Mot., at 4, ¶ 19, ECF No. 35.

Plaintiff opposes defendant's motion on several grounds. Plaintiff contends that treating defendant's untimely responses as admissions "would not eliminate a presentation of the merits of the case," Pl.'s Opp. at 1, ECF No. 36, because the "requests focus on discrete issues, rather than broad attempts to have [defendant] admit full liability for all claims." Id. at 3; see also Pl.'s Surreply at 1, ECF No. 43. Plaintiff further submits that it would be prejudiced by the 18-day delay because defendant did not seek an extension "until after the deadline passed," because defendant "waited nearly two additional weeks to respond to the requests," and because defendant "has repeatedly demonstrated a conscious disregard for its discovery obligations." Pl.'s Opp. at 3-4, ECF No. 36; see also Pl.'s Surreply at 4-5, ECF No. 43.

ANALYSIS

The procedural framework for requests for admissions is straightforward. Responses to requests for admission are due within 30 days of service. See Fed. R. Civ. P. 36(a)(3). If no response is provided, then the requests are deemed admitted, see id. , but only for purposes of the litigation, and not "for any other purpose," and the admission cannot "be used against the party in any other proceeding." Id. 36(b). Thus, by not responding timely to plaintiff's requests for admissions, defendant is deemed to have admitted those statements for purposes of this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valez v. Rent (In re Valez)
601 B.R. 351 (M.D. Pennsylvania, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
358 F. Supp. 3d 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-hughes-constr-co-v-eqm-gathering-opco-llc-pawd-2019.