City of Wamego v. L. R. Foy Construction Co.

675 P.2d 912, 9 Kan. App. 2d 168, 1984 Kan. App. LEXIS 281
CourtCourt of Appeals of Kansas
DecidedJanuary 12, 1984
Docket55,042
StatusPublished
Cited by12 cases

This text of 675 P.2d 912 (City of Wamego v. L. R. Foy Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Wamego v. L. R. Foy Construction Co., 675 P.2d 912, 9 Kan. App. 2d 168, 1984 Kan. App. LEXIS 281 (kanctapp 1984).

Opinion

Parks, J.:

This action for breach of a construction contract was filed by the City of Wamego against defendants L. R. Foy Construction Company and its bonding company. Defendants sought to submit the dispute to arbitration as permitted by the terms of the contract by filing a motion to stay the civil suit and compel arbitration pursuant to K.S.A. 5-402. This motion was denied by the court and defendants appeal that order. K.S.A. 5-418(a)(l).

In the spring of 1981, plaintiff invited bids for the construction of certain sanitary sewer improvements. Defendant Foy was the apparent low bidder with a bid of $224,971 while Walters Construction Company was the second lowest bidder with a bid of *169 $238,138. On April 21, 1981, the bids were opened. The City conditionally accepted Foy’s bid and awarded the contract for construction to Foy subject to approval of the project by the Environmental Protection Agency (EPA). Foy was notified of this action by the City and it returned the executed contract documents to the City on May 6. The bid form which became a part of the contract documents included the following terms:

a) no bidder may withdraw the bid for a period of sixty (60) days after opening of the bids.
b) written notice of award, which may be by telegraph, must be given the bidder (Foy) by the City within sixty (60) days after date of opening the bids.
c) construction shall commence thirty (30) calendar days following notice to proceed.
d) construction shall be completed three hundred (300) calendar days following notice to proceed.

The City submitted all of the necessary information to the EPA but became concerned that federal approval would not be received in time to give Foy final written acceptance of its bid within the 60 days required by the bid form. The City contacted the three low bidders advising them of the potential time problems and requesting a 60-day extension within which to formally award the contract. Foy responded that it would honor the contract for an additional 90 days on the condition that the contract bid price be increased by 5 %% due to the expected increases in costs for labor and materials. The City made no response to this proposal. On June 19, the City received notice that the EPA had approved the project. A telegram formally accepting Foy’s bid was immediately dispatched and a mailgram confirming the contents of the telegram was also sent. The telegram was received in Foy’s office between 4:45 p.m. and 5:00 p.m. on June 19, 1981 — fifty-nine days after the bids were opened.

At a preconstruction conference on June 29, 1981, the city engineer gave Foy oral notice to proceed with the project effective June 30 and distributed executed contract documents. Dennis Lyne, general superintendent of Foy, refused to receive Foy’s three copies of the contract and accompanying documents stating, in substance, that Foy had not received notice of acceptance until the 62d day after opening of the bids and that there *170 was no contract in effect. The City contended that it had mailed conditional notice of acceptance of its bid on the 6th day and final unconditional acceptance had been received by Foy on the 59th day. It refused to recognize Foy’s demand for a 5 %% increase as having any effect and argued that any claim for extra compensation would have to be submitted in writing with full justification for approval by both the EPA and the City. The City demanded performance in a letter stating that construction shall commence within 30 calendar days (by July 30, 1981) and shall be completed within 300 calendar days (by April 26, 1982).

Foy’s attorney responded with a letter to the city engineer which stated in part as follows:

“L. R. Foy Construction Co., Inc. still wants to do this job but finds it necessary to have a solid agreement as to the 5 %% increase and to have a sound footing as far as interpretation of all contract documents. We are hopeful that you can respond within seven days. After that time, the bonding company of L. R. Foy Construction will be asked to withdraw all bid bonds and the L. R. Foy Construction Co., Inc. will withdraw from all negotiations of the intended project.” (Letter of July 7, 1981.)

Subsequent correspondence from Foy’s legal counsel included two letters including the following language:

“On behalf of the L. R. Foy Construction Co., Inc., this office hereby gives notice that said L. R. Foy Construction Co., Inc., withdraws from all negotiations concerning the contract for the construction of the above referenced project. As a result thereof, said L. R. Foy Construction Co., Inc., respectfully requests that the bid bond executed and forwarded to the City of Wamego, Kansas, be returned to this office at the earliest practical opportunity.” (Letter of July 17, 1981.)
“I am in receipt of your letter dated July 21, 1981. Please.understand that the L. R. Foy Construction Co., Inc. submitted a bid for the award of the contract for the above reference project, however, the contract documents were not forwarded to said Construction Company within 90 days. Due to that fact expected raises in material and labor accrued causing a 5 %% increase in the total contract price. The city denied Foy’s request to increase the contract by 5 %% to accommodate this problem, and in return, Foy withdrew from the contract negotiations. Foy cannot be expected to begin performance of the contract on the above project without ample time to plan and purchase the necessary construction equipment. “Because of the fact that a delay on your part in turn delayed the forwarding of the contract to Foy, Foy feels fully justified in its withdrawal. In addition to the return of the bid bond we respectfully ask for the return of the performance and the labor and material payment bond executed on the engineers’ form no. 7815-2, CS-I, and CS-2.” (Letter of July 22, 1982.)

The City continued to demand performance by Foy according *171 to the terms of the contract and did not negotiate any proposed price changes.

A meeting between representatives of Foy and the City took place on August 18, at which time Foy took the position that unless the City agreed to an additional $4.50 to $5.00 per foot compensation or an unlimited time extension for the project’s completion, there was no contract. The City turned to the next lowest bidder and inquired whether its bid was still firm. Walters Construction agreed to perform the job for the amount of its original bid and entered into a contract with the City. The City filed this suit for breach of contract seeking damages amounting to the difference between the Foy and Walters bids.

Foy filed its motion to compel arbitration premised on the following clause included within the contract documents:

“29. ARBITRATION:
29.1 General:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyons Ex Rel. Lawing v. Holder
163 P.3d 343 (Court of Appeals of Kansas, 2007)
Anderson v. Dillard's, Inc.
153 P.3d 550 (Supreme Court of Kansas, 2007)
City of Andover v. Southwestern Bell Telepnone, L.P.
153 P.3d 561 (Court of Appeals of Kansas, 2007)
Holmes v. Howard
8 F. Supp. 2d 1269 (D. Kansas, 1998)
Malarky Enterprises v. Healthcare Technology, Ltd.
962 F. Supp. 1427 (D. Kansas, 1997)
Zenda Grain & Supply Co. v. Farmland Industries, Inc.
894 P.2d 881 (Court of Appeals of Kansas, 1995)
Southwest National Bank v. Simpson & Son, Inc.
799 P.2d 512 (Court of Appeals of Kansas, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
675 P.2d 912, 9 Kan. App. 2d 168, 1984 Kan. App. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-wamego-v-l-r-foy-construction-co-kanctapp-1984.