City of Tell City v. Indiana Utility Regulatory Commission

558 N.E.2d 857, 1990 Ind. App. LEXIS 1089, 1990 WL 121920
CourtIndiana Court of Appeals
DecidedAugust 20, 1990
DocketNo. 93A02-8908-EX-417
StatusPublished
Cited by3 cases

This text of 558 N.E.2d 857 (City of Tell City v. Indiana Utility Regulatory Commission) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Tell City v. Indiana Utility Regulatory Commission, 558 N.E.2d 857, 1990 Ind. App. LEXIS 1089, 1990 WL 121920 (Ind. Ct. App. 1990).

Opinion

HOFFMAN, Presiding Judge.

Petitioner-appellant City of Tell City, Indiana appeals the denial of its petition for issuance of bonds by the Indiana Utility Regulatory Commission.

The facts relevant to this appeal reveal that on January 3, 1989, Tell City filed with the Commission its petition requesting ap[859]*859proval of a new schedule of rates and charges for services rendered by its municipal electric utility 1 and authority to issue bonds to pay for the cost of improvements to its electric facility. The requested bond issuance was in the total amount of $1,450,-000.00.

Tell City, through its municipal electric utility, also provides wholesale electric service to the Town of Troy. Tell City purchases its electrical power at wholesale from Southern Indiana Gas and Electric Company. The purpose of the requested bond issuance was to obtain funds to build a substation necessary to provide wholesale power to Troy when Stewart Warner-Southwind Corporation moves into Troy's service area as a new retail customer. The portion of the bond issue required to construct the substation was approximately $390,000.00

On June 29, 1989, the Commission issued its order denying Tell City's petition. The Commission found that a new substation is necessary to properly serve Stewart Warner. However, the new substation is to be built in Troy's service area. Therefore, Tell City must have Troy's permission to supply this new service. To date, Troy has not entered into a contract for the purchase of power at wholesale from Tell City to provide retail service to the Stewart Warner plant. In fact, the Commission found that Tell City had been negotiating with Stewart Warner for at least two months before notifying Troy of the negotiations. If the new substation were built and Troy refused to purchase power at wholesale from Tell City through the substation, then Tell City could incur costs of between $50,-000.00 and $100,000.00 in dismantling the substation. Evidence was presented that Troy could possibly purchase power directly from SIGECO, as done by Tell City, or enter into a joint ownership with Tell City of the substation whereby Troy would own the low voltage side of the substation as alternatives to purchasing power at wholesale from Tell City. The Commission concluded that it would not be in the public interest to issue bonds for a substation that might later have to be dismantled. Therefore without a contract between Troy and Tell City to provide retail service to Stewart Warner, Tell City's petition was denied. The Commission affirmed its decision on July 28, 1989.

Appellant's issues can be summarized as follows:

(1) whether the Commission erred in denying Tell City's petition;
(2) whether the Commission erred in admitting Alfred Snyder's prefiled testimony and certain exhibits; and
(8) whether the Commission erred in admitting the testimony of Jack Gaines and Robert Dew.

Tell City is a municipal utility within the meaning of the Public Service Commission Act of 1918, IND.CODE § 8-1-2-1 et seq. (1988 Ed.). As such, Tell City is required to have approval of the Indiana Utility Regulatory Commission for a bond issuance. IND.CODE § 8-1.5-2-19(a) (1988 Ed.).

This Court has jurisdiction pursuant to IND.CODE § 8-1-3-1 (1988 Ed.) which permits a public utility adversely affected by a final order of the Indiana Utility Regulatory Commission to appeal that order. There is a two-tier standard of review of the Commission's determination: first, the Commission's determination must contain specific findings of fact on all determinations material to its order and see-ond, there must be substantial evidence in light of the whole record to support the Commission's findings of basic fact. Habig Trucking v. Public Service Com'n (1984), Ind.App., 466 N.E.2d 484. However this Court will not reweigh the evidence or substitute its judgment for that of the Commission when reviewing the sufficiency of the evidence. Id. If a reasonably sound basis of evidentiary support exists, the Commission's findings will be upheld. Board of Dir. for Util. v. Office of Utility (1985), Ind.App., 473 N.E.2d 1043.

Appellant argues that the Commission's findings of fact do not support its [860]*860ultimate determination. The following are the Commission's finding of fact:

"(b) Petitioner's Evidence. Petitioner presented the testimony of Mr. Frederic M. Weyer, an employee of Wayne E. Seufert and Associates, Inc., an architectural engineering firm retained by Stewart-Warner-Southwind Corporation, concerning the relocation of their Indianapolis plant to the Tell City Industrial Park. Mr. Weyer testified that he had assumed Petitioner would be providing service to Stewart-Warner. He stated that he did not contact Intervenor [Troy] or its Utility Service Board until after the project was bid in December, 1988. He testified further that he never communicated with Intervenor with respect to the total electricity requirements of the Stewart-Warner plant because he was under the impression that Mr. Joyce, Petitioner's Superintendent, would be handling the project.
Mr. Wilbur W. Sterling, Manager of Manufacturing for Stewart-Warner, testified on behalf of Petitioner that occupancy of the new Stewart-Warner plant was scheduled for May 1, 1989, and that their new plant building was substantially completed. He testified that he did not recall how the estimates of Stewart, Warner's power cost were calculated but that he did not consider Intervenor's rates because all dealings were with Petitioner. On cross-examination by the Public, Mr. Sterling expressed his concern that a dispute between Petitioner and Intervenor might be costly and time-consuming.
Mr. James R. Schmitt, Chairman of Petitioner's Utility Service Board, testified on behalf of Petitioner that Petitioner and Intervenor have not entered into a contract, the terms and conditions of which would affect the financing proposed in this Cause.
Finally, Mr. Jack M. Joyce, Petitioner's Superintendent, testified on behalf of Petitioner that he had known in September, 1988 that the proposed Stewart-Warner plant was to be located in Intervenor's service area. He testified further that his notes had indicated that Intervenor would have to experience a substantial voltage drop in order to accommodate the Stewart-Warner plant; however, the witness did not communicate this information to Intervenor. In addition, Mr. Joyce stated that work on plans for the new substation began in October, 1988. He stated that Petitioner submitted a contract for wholesale power to Inter-venor on January 10, 1989, but that In-tervenor had not yet executed any contract. He testified that there had been meetings between Intervenor and Petitioner. He suggested that if Intervenor does not enter into a wholesale power contract with Petitioner and unless this Commission orders otherwise, Petitioner will build the proposed substation in In-tervenor's territory. He testified that later Petitioner might dismantle the substation or sell it to Intervenor. Mr. Joyee also stated that without a contract with Intervenor, Petitioner would be prohibited by law from providing retail power to Stewart-Warner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indiana Bell Telephone Co. v. Office of Utility Consumer Counselor
717 N.E.2d 613 (Indiana Court of Appeals, 1999)
State v. Butler
724 A.2d 657 (Court of Appeals of Maryland, 1999)
Hall v. State
560 N.E.2d 561 (Indiana Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
558 N.E.2d 857, 1990 Ind. App. LEXIS 1089, 1990 WL 121920, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-tell-city-v-indiana-utility-regulatory-commission-indctapp-1990.