City of Tecumseh v. Burns

1911 OK 495, 120 P. 270, 30 Okla. 503, 1911 Okla. LEXIS 487
CourtSupreme Court of Oklahoma
DecidedDecember 12, 1911
Docket1348
StatusPublished
Cited by10 cases

This text of 1911 OK 495 (City of Tecumseh v. Burns) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Tecumseh v. Burns, 1911 OK 495, 120 P. 270, 30 Okla. 503, 1911 Okla. LEXIS 487 (Okla. 1911).

Opinion

Opinion by

ROBERTSON, C.

This action was begun in the district court of Pottawatomie county by the defendants in error, who hereinafter will be called plaintiffs, against the city of Tecumseh, hereinafter designated as defendant, to recover the *504 sum of $1,050, alleged to be due them by virtue of a certain written contract purporting to have been executed by said parties on November 21, 1905.

Said contract consists of three separate items, the first of which provides for the making of a preliminary survey preparatory to the installation of a system of waterworks in said city, and which preliminary survey was to be made by the plaintiffs for said city, and for which the city was to pay the sum of $150. Under this item,, the plaintiffs made the preliminary survey, and made a report to the city, and were paid therefor the sum of $150. This item is not in dispute in this case, so far as the contention of the city is concerned; nor do the plaintiffs claim that the city owes them under said item. It is the contention of plaintiffs that the contract sued on is single and indivisible, and embraces but one employment, and that by its terms they were employed by the city to make the complete survey, plans, and specifications for the waterworks system, and after the completion of the preliminary survey to immediately proceed, under items 2 and 3, and complete the permanent and final survey, plans, and estimates. The city, on the contrary, insists that this contract is divisible, and embraces two separate propositions of employment, the validity of the second of which depends upon the performance of certain conditions precedent, i. e., the adoption by the city of the preliminary plans and estimates provided for in item 1, and also the voting of bonds, or the raising of funds by some other method, for the construction of the waterworks system, as provided in said preliminary survey; and that, unless the city council approved and adopted the said plans and estimates submitted by plaintiffs, under the provisions of item 1, then no further expense should accrue under items 2 and 3.

It was on this theory that the case was tried in the court below, and on page 57 of the record, the court, in sustaining the objection of plaintiffs to the introduction of certain evidence by the city, tending to establish a defense on a different theory, said:

“The theory under which this case will proceed is this: The plaintiffs were not authorized to do any work prior to the voting *505 of the bonds, and before any bonds were voted they were instructed not to do the work. Then any work they did after that time was voluntarily done for the purpose of attempting to enforce the contract. Now it seems to me that the measure of damages would be, in this contract, if they are entitled to recover, first, nominal damages for breach of contract, if any; and, secondly, the difference between the contract price for this work and the sum, or whatever would be required to do the work— the cost of doing the work.”

No objection was made by counsel for the plaintiffs to this declaration or statement on the part of the court, and immediately after such statement by the court plaintiffs asked leave to reopen their case and submit proof as to the amount of damage incurred, according to the ruling of the court above set out (Record, page 59), which permission was granted by the court. It is apparent, therefore, that this was the theory upon which plaintiffs tried the case, and, of course, they will not be permitted to abandon that theory here, and proceed upon another, which may be more favorable. At the close of plaintiffs’ testimony, the city demurred to the evidence, which demurrer was by the court overruled, and the city assigns this ruling of the court as error, and relies upon the same for a reversal.

The preliminary survey provided for by item 1 of-the contract was completed and submitted to the city some time in January, 1906. On the 5th of March, 1906, the city council decided that the further services of Burns & McDonnell would not be required, and ordered the clerk to notify them to that effect. At the same meeting, however, it was decided to call an election for waterworks bonds in the sum of $60,000. On the 15th day of March, 1906, by resolution, the mayor and the city clerk of said city were authorized to sign a contract with the O’Neil Engineering Company for plans and specifications for the construction of a waterworks system in the city of Tecumseh. It thus appears that the preliminary survey, as furnished by the plaintiffs, was not satisfactory to the city, and was not approved and accepted by the city, but, on the contrary, a different set of plans and specifications were desired, and, as the record shows, the water *506 works were constructed in accordance with the terms of the latter contract. Some two years after this the plaintiffs filed suit against the city for the full amount which would have been due them, had the city adopted their plans and constructed the waterworks system in accordance therewith, which at 2 per cent, of the contract price would amount to $1,050, less $150, for item 1, which had already been paid.

The plaintiff R. E. McDonnell testified in his own behalf at the trial, and, among other things, stated that, while he prepared the permanent plans and specifications under items 2 and 3, yet he never presented them to the city, for the reason that their contract had been terminated (Record, page 38) ; also, in answer to a question propounded:

“Q. Then all the work done under 2 was done while you were doing work under item 1, complying with the contract? A. Yes, sir.” Record page 45. And: “Q. Was there anything else you did in regard to the second item before this notice was served on you ? A. No; I don’t recall anything else. Q. Do you state to this court and jury that you did any work under item 2 after you received that notice? A. I can’t recollect whether I did any work, or whether I had it all completed at the time.” Record, page 48. “Q. Now, when did you furnish that to the city? [Meaning the final plans.] A. I never submitted these to the city after wé received notice.” Record, page 49. “Q. And all the data you had in and about this preparation you obtained from this preliminary survey that you were paid for, is that right? A. Yes, sir.”

Thus it will be seen — in fact, it is not denied anywhere in the record — that the entire work in and about the preparation of the final plans and specifications was completed long before any bonds were voted, and also before notice had been sent to plaintiffs by the city that their preliminary plans would not be adopted; and it also appears that all the data used by plaintiffs in preparing the final plans and specifications were secured by them while making the preliminary plans and specifications, and that they never, at any time, notified the city that they were making the final plans and specifications; nor did they ever furnish them to the city, either before or after the notice from the city that the preliminary *507

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Com'rs of Kingfisher County v. Vahlberg
1947 OK 100 (Supreme Court of Oklahoma, 1947)
Cities Service Gas Co. v. Kelly-Dempsey & Co.
27 F. Supp. 547 (N.D. Oklahoma, 1939)
Phoenix Oil Co. v. Mid-Continent Petroleum Corp.
1936 OK 250 (Supreme Court of Oklahoma, 1936)
Continental Supply Co. v. Levy
1926 OK 449 (Supreme Court of Oklahoma, 1926)
Goble v. Bell Oil & Gas Co.
1924 OK 71 (Supreme Court of Oklahoma, 1924)
Gypsy Oil Co. v. Ponder
1923 OK 532 (Supreme Court of Oklahoma, 1923)
Prowant v. Sealy
1919 OK 304 (Supreme Court of Oklahoma, 1919)
Gem Oil Co. v. Callendar
1918 OK 269 (Supreme Court of Oklahoma, 1918)
Union Trust Co. v. Shelby Downard Asphalt Co.
1916 OK 160 (Supreme Court of Oklahoma, 1916)
Brown v. Coppadge
1915 OK 1064 (Supreme Court of Oklahoma, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
1911 OK 495, 120 P. 270, 30 Okla. 503, 1911 Okla. LEXIS 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-tecumseh-v-burns-okla-1911.