City of Springfield v. Washington Public Power Supply System

564 F. Supp. 90, 1983 U.S. Dist. LEXIS 17393
District Court, D. Oregon·Decided April 27, 1983·No. Civ. 82-1387-RE·Published·Cited by 2 cases

Opinion

REDDEN, District Judge:

This action concerns three nuclear power plants whose construction was financed un *92 der the terms of net billing agreements between the Bonneville Power Administration (BPA), Washington Public Power Supply System (WPPSS), and more than one hundred utilities in Oregon, Washington, Idaho, Montana, Nevada and Wyoming. The plants, known as WPPSS plants 1, 2 and 3, face a somewhat uncertain future. Two other such plants, WPPSS plants 4 and 5, have been terminated in mid-construction, and work has ceased on one of these three plants.

WPPSS plants 1, 2 and 3 share a significant characteristic distinguishing them from WPPSS plants 4 and 5: BPA is a signatory to the contracts governing the financing of their construction. BPA, a federal agency, has assumed the key role in financing the plants through the mechanism of net billing agreements.

In this action, plaintiff City of Springfield, Oregon, seeks a declaration that it had authority to enter into the net billing agreements. The federal defendants, including BPA, seek a further declaration that all participants had authority to enter into the agreements under their respective state laws. The parties now move for summary judgment.

In deciding these motions, I will address several issues. First, I must decide whether this case presents a justiciable controversy. Second, I must decide whether abstention is appropriate and third, I must decide what law governs the interpretation of the net billing agreements. Finally, I must decide the merits of the motions for summary judgment. These issues interrelate significantly and it is appropriate to summarize the background and history of this litigation.

BACKGROUND TO THIS LITIGATION AND ITS PROCEDURAL HISTORY

BPA was established in 1937 with the purpose of developing the Northwest’s hydroelectric resources and providing low cost energy to the region. In 1966, forecasts of a rapid growth in the power needs of the Northwest caused BPA to urge the construction of nuclear power plants to fill the projected shortfall in the region’s energy needs. Between 1970 and 1973 BPA, its customers and WPPSS executed a series of contracts, called net billing agreements, providing for the construction of the nuclear plants. In 1976, WPPSS commenced construction of two more nuclear plants, WPPSS plants 4 and 5. BPA did not participate in those projects, although 88 Northwest utilities did join WPPSS in “participation agreements” for plants 4 and 5.

The predicted sharp growth in Northwest energy demands failed to materialize. As a result, the region faces the prospect of bond payments for the construction of plants which may never generate saleable power. Litigation, however, has certainly been generated, and pends in several state courts, as well as in this court. Meanwhile, WPPSS faces the prospect of a financial meltdown.

In DeFazio, et a1. v. Washington Public Power Supply System, Lane County Circuit Court No. 16-81-11344, ratepayers of the city of Springfield challenged the authority of their city to enter into the participation agreements underlying dormant WPPSS plants 4 and 5. The ratepayers secured a ruling that forbade Oregon public utilities, including Springfield, from paying WPPSS in order to retire the debt created by plants 4 and 5. The Lane County Circuit Court ruled that, in entering into the participation agreements without a public vote, the Oregon participants had violated provisions of the Oregon Constitution and various statutes forbidding municipalities from incurring debt without voter approval. DeFazio, now on appeal, sent a shockwave through the Northwest and the municipal bond markets, because it held that Oregon utilities were not liable for the indebtedness for WPPSS plants 4 and 5 and raised the possibility that WPPSS would default on the bonds.

Other litigation, filed in this court, sought a ruling to the effect that DeFazio was wrongly decided and has been dismissed on abstention grounds. That suit, Chemical Bank v. City of Bandon, et al., 562 F.Supp. 704 (D.Or.1983), concerned WPPSS plants 4 and 5, in which BPA owns no interest.

*93 This suit, by contrast, concerns WPPSS plants 1, 2 and 3, in which BPA does have a crucial role. It is argued that BPA has in fact assumed the “dry-hole” risk as to these plants, that is, the obligation of payment if the plants are never completed or never produce saleable power. Thus, it is argued, the utilities which entered into net billing agreements will not be required to retire debts through the use of their taxing power or general revenue, and this, it is further argued, distinguishes DeFazio. Moreover, the federal involvement in these plants, and the prospect of federal responsibility if the “dry-hole” risk comes to fruition, arguably requires that federal law, not the law of Oregon or any other state, govern these contracts. See Clearfield Trust v. United States, 318 U.S. 363, 63 S.Ct. 573, 87 L.Ed. 838 (1943); City of Springfield v. WPPSS, et al., 564 F.Supp. 86, (Opinion on motions to dismiss filed March 15, 1983), at n. 2.

A preliminary issue, however, is whether this case is in fact justiciable, and whether abstention is appropriate in deference to the pending appeal of DeFazio. I address these matters first.

THIS SUIT IS JUSTICIABLE; ABSTENTION IS NOT APPROPRIATE

When this suit was originally filed, some parties moved to dismiss on the grounds that there was no “case or controversy” concerning the net billing agreements, or that the controversy was not justiciable because the parties to this suit did not have adverse interests. I reserved decision on this issue until litigation of the summary judgment motions on the merits. City of Springfield, supra (Opinion on motions to dismiss).

Since the time of the original argument of those motions some parties have altered their positions and others have entered this suit. At the present time it is clear that, far from being a case in which all parties “desire precisely the same result,” see Moore v. Charlotte-Mecklenburg Bd. of Ed., 402 U.S. 47, 48, 91 S.Ct. 1292, 1293, 28 L.Ed.2d 590 (1971), this is a case in which unanimity on any issue is lacking. Some parties argue that the net billing agreements are markedly different in effect from the participation agreements invalidated by DeFazio. Other parties take the opposite position, arguing that the net billing agreements are identical, in effect, with the participation agreements, and therefore either DeFazio was correctly decided and the net billing agreements are invalid or DeFazio was “aberrational,” and Oregon utilities did have authority to enter into both kinds of agreements. While some parties argue that federal law governs this case as a result of the federal involvement, others argue that federal law is inapplicable. Some parties argue that abstention is appropriate, others disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Springfield v. Washington Public Power Supply System, 564 F. Supp. 90, 1983 U.S. Dist. LEXIS 17393 (D. Or. 1983).

564 F. Supp. 90 (City of Springfield v. Washington Public Power Supply System) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related