City of Springfield v. Washington Public Power Supply System

752 F.2d 1423
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 4, 1985
DocketNos. 83-3927, 83-4024
StatusPublished
Cited by4 cases

This text of 752 F.2d 1423 (City of Springfield v. Washington Public Power Supply System) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Springfield v. Washington Public Power Supply System, 752 F.2d 1423 (9th Cir. 1985).

Opinion

FERGUSON, Circuit Judge:

This case involves a challenge to the validity of several contracts to construct and distribute power from nuclear power plants among (1) a number of Oregon, Washington and Idaho cities and public utility districts (the participants), (2) the Washington Public Power Supply System (Supply System or WPPSS), and (3) the Bonneville Power Administration (BPA). The district court rejected the argument that the participants lacked authority under local state law to enter into such agreements and upheld them under federal common law. We affirm, but with certain modifications.

FACTS

Congress established the BPA to serve as the federal marketing agency for electric power produced in the Pacific Northwest. 16 U.S.C. § 832 et seq. The BPA acquires hydroelectric and other power and distributes it to utility companies and other customers. WPPSS is a municipal corporation and joint operating agency under Washington law. Wash.Rev.Code § 43.52. It is an association of nineteen Washington public utility districts and four Washington cities, formed to finance, construct, own, and operate electrical generating facilities.

In the early 1970s, the BPA entered into a series of three-party contracts with various public utilities and WPPSS to build and distribute electricity from four nuclear power plants. These plants were designated the Trojan Nuclear Project and WPPSS Nuclear Projects No. 1, No. 2 and No. 3. The agreement relating to each project is an identical three-party contract consisting of a “Project Agreement” and a “Net Billing Agreement.” The “Project Agreement” provides “for financing, construction, ownership and operation” of the plant, and is executed by WPPSS and the BPA. The “Net Billing Agreement” provides for the distribution of electricity to the participants through BPA. A declared purpose of the net billing agreement is to “pool electric power and energy acquired hereunder with other power available to the [BPA] Administrator from the Federal Columbia River Power System so that any costs or losses associated with acquiring such power and energy will be borne by the [BPA] Administrator’s ratepayers through rate adjustments if necessary.” By such pooling, the effect of an unexpectedly great cost can be diluted by the use of cheaper and readily available energy from other sources.

The participants under the net billing agreements agreed to use a share or percentage of the electricity generated by the plant. The cost of that share is computed by multiplying the participant’s share by the amount of the annual budget (less funds payable from other sources). This cost is reflected in the “Billing Statement” prepared by WPPSS and must be paid by the participant “whether or not the Project is completed, operable or operating and notwithstanding the suspension, interruption, interference, reduction or curtailment of the Project output.”

The participants do not receive their share of the power produced by the plant directly, however. They “assign” the power to the BPA, which pools it with its other sources of power. The BPA then provides the participants with the amount of electrical power they need, and deducts the amount the participants paid directly to WPPSS from the cost of the power clelivered by BPA. Should the amount the participant paid to WPPSS exceed the cost of electricity actually delivered by BPA, the accumulated balance in favor of the participant “shall be paid in cash” to the participant by BPA, “subject to the availability of appropriations for such purposes.” 1 The [1426]*1426BPA Administrator is also authorized to “use his best efforts” to assign a participant’s excess share to another BPA customer.

In 1976, WPPSS entered into two-party-contracts with certain Northwest cities and utilities to construct and sell power from two additional nuclear power plants— Projects 4 and 5. Those two-party contracts do not involve the BPA. They [the Project’s 4 and 5 two-party contracts] require the cities and utilities to pay their percentage of the costs specified in the contracts, and to receive their percentage of the power directly from WPPSS, even if the amount of power received is zero. Construction of Projects 4 and 5 was abandoned in 1982, and the local entities became obligated under the contracts to pay their percentage of the costs even though they were receiving no power and no power could be produced. The supreme courts of Washington and Idaho subsequently held that these two-party contracts could not be enforced against the local utilities and cities as the contracts were not properly executed or exceeded the authority of the cities or utilities. Asson v. City of Burley, 105 Idaho 432, 670 P.2d 839 (1983); Chemical Bank v. WPPSS, 99 Wash.2d 772, 666 P.2d 329 (1983). The Oregon Supreme Court issued an opinion on March 20, 1984 holding that Oregon local utilities acted within their authority in executing the two-party agreements with WPPSS. DeFazio v. WPPSS, 296 Or. 550, 679 P.2d 1316 (1984).

This case was brought by the City of Springfield, Oregon, and sought a declaratory judgment that it either had “full legal authority to enter into the [three-party] Net killing Agreements on Projects 1, 2, 3 and Trojan by reason of Bonneville’s obligations thereunder,” or that, if it did not have authority, to enter into the agreements, “Bonneville is liable to Supply System to make such payment and estopped to claim its lack of obligation to do so.” The complaint was brought after the decision of an Oregon trial court which, in agreement with the courts of Washington and Idaho, held the two-party contracts for Projects 4 and 5 unenforceable. The Oregon Supreme Court has since reversed that court. DeFazio v. WPPSS, supra.

The City of Springfield joined as defendants all local participants in the net billing agreements, WPPSS and BPA. Springfield ratepayers, represented by Peter DeFazio, intervened, arguing that the case did not present “a genuine justiciable controversy” until the appeal of the Oregon trial court decision was decided and, in the alternative, that the city lacked authority to enter into the net billing agreements.

On a motion for summary judgment decided before the Oregon trial court was reversed, the district court upheld the validity of the net billing agreements and the authority of the local participants to execute them. City of Springfield v. WPPSS, 564 F.Supp. 90 (D.Or.1983). The court stated that “because BPA, a federal agency, has assumed the ‘dry-hole’ liability as to WPPSS plants 1, 2 and 3, the net billing agreements are contracts with the federal government whose interpretation is a matter of federal, not state concern.” Id. at 93-94. The court then concluded: “The utilities entering into these agreements thus merely entered into authorized contracts for power. If no power is provided, no power is paid for. There is no infirmity in this arrangement.” Id. at 95.

ISSUES

1. Is there a justiciable controversy involving all parties?

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
752 F.2d 1423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-springfield-v-washington-public-power-supply-system-ca9-1985.