City of Springfield ex rel. Gilsonite Construction Co. v. Schmook

96 S.W. 257, 120 Mo. App. 41, 1906 Mo. App. LEXIS 371
CourtMissouri Court of Appeals
DecidedJune 5, 1906
StatusPublished
Cited by2 cases

This text of 96 S.W. 257 (City of Springfield ex rel. Gilsonite Construction Co. v. Schmook) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Springfield ex rel. Gilsonite Construction Co. v. Schmook, 96 S.W. 257, 120 Mo. App. 41, 1906 Mo. App. LEXIS 371 (Mo. Ct. App. 1906).

Opinion

GOODE, J.

This is an action to enforce the lien of three taxbills issued to pay for paving the street in front of a lot in the city of Springfield. Those of the defendants in whom the title to the lot is vested are the heirs or devisees of John Schmook, deceased, who was the owner of the lot when the proceedings in question occurred. The other defendants are interested as trustees or beneficiaries in deeds of trust. The property lies on the west side of Boonville street, a thoroughfare along which double street car tracks run. The improvement for which the taxbills were issued is an asphalt pavement and was laid by the Gilsonite Roofing and Paying Company, which assigned the taxbills to the Gilsonite Construction Company, to whose use the present action was brought. The judgment of the court below was in favor of the defendants. Several defenses were interposed, but the only one we find it necessary to consider is that the work was not completed within the time required by the contract between the city and the original contractor, the Gilsonite Roofing & Paving Company. The proceedings for the improvement of the street were started by two resolutions passed by the council of the city of Springfield, June 9, 1898. Under the ordinances of the city and the franchises by which the street railway company (the Springfield Traction Company) used the street, it was incumbent on it to pave that portion of the street occupied by its rails and two feet outside. One of the original resolutions declared it was necessary to improve the street by paving with asphalt that portion of the roadway on either side of the street car tracks and two feet from them, and the other resolution declared it was necessary to pave with the same [46]*46material the center of the street occupied hy the car tracks and two feet beyond the outer rails and ordered the Traction Company to lay that paving. The other work was to be let by the city to a contractor to be done in conformity to specifications on file in the office of the city engineer. Bids for the work were advertised for by the city and that of the Gilsonite Company was accepted by an ordinance approved July 20,1898. This ordinance said nothing about the time in which the work should be begun or finished; but the city entered into a contract with the Gilsonite Roofing & Paving Company, dated July 25, 1898, which contained a provision that the said company, as contractor, should complete the work according to specifications in ninety days from the time the contract took effect. We quote that clause of the contract:

“Now, therefore, the said party of the first part hereby agrees with the said city of Springfield, to do and complete said work according to specifications, without negligence, causing or tending to cause damage to private property for which the city might be held liable, furnishing all materials therefor at his own cost and expense, within ninety days from the time this contract goes into force and effect, according to such directions as the city engineer and street committee of the city of Springfield, may from time to time give in superintending the construction of said work, and in accordance with the plans and specifications of said work prepared by the city engineer for the letting of a contract for said work, and to the satisfaction and acceptation of the city engineer of the city of Springfield, and said specifications are attached hereto and made a part of this contract; provided, if the contractor is delayed by injunction or legal proceedings, or by any unavoidable cause, the time or completion shall be extended by the council covering said delay.”

At the time the contract was executed, a general [47]*47ordinance of the city of Springfield was in force which provided that every person who should hid for the job of constructing, should enter into a written contract within ten days and complete the improvement according to the plans, specifications and ordinances within the time agreed on, without negligence tending to cause damage to private property. On September 13, 1898, the council directed the mayor to notify both the Springfield Traction Company and the G-ilsonite Company to begin the improvement. Shortly afterwards the paving company started the work. The Traction Company refused to comply with the city’s resolution directing it to put in asphalt paving between the tracks and two feet on either side and in consequence litigation arose between it and the city. On account of the action of the Traction Company, the mayor pro tern of the city served a written notice on the Gilsonite Eoofing & Paving Company, October 17, 1898, directing it to cease work under its contract until the Traction Company could be compelled to proceed with the improvement it was bound to make, or until further notice from the city of Springfield.

The testimony tends to show that on receipt of this notice from the mayor, the paving company ceased work and. shortly thereafter the weather became unsuitable for laying asphalt paving. The dispute between the city and the Traction Company resulted' in allowing the latter to pave that portion of the street it had to pave with brick instead of asphalt. On January 19, 1899, the mayor of the city notified the paving company to go on with its work, the controversy with the Traction Company having been settled. There is testimony that early in the spring, and as soon as the weather permitted, the Gilsonite Company went ahead with the improvement and completed it as quickly as possible. It was finished early in July, 1899. The contract called for its completion within ninety days from July 25, 1898, [48]*48unless the Gilsonite Company was delayed by injunctions, legal proceedings or some'other unavoidable cause; in which case the period for completion should be extended by the council to cover the unavoidable delay. An attempt was made to prove that the acting mayor was authorized to serve notice on the Gilsonite Roofing & Paving Company to cease work until the dispute with the Traction Company was settled; but no such authority was, in fact, shown. In the court below no declarations of law were asked, or any findings of fact. At the conclusion of the evidence the court rendered a judgment in favor of the defendants; and on the facts the question for decision is, did it conclusively appear that the work was completed in due time so that the tax-bills were valid; or was the court justified in holding completion was so long delayed that the contract was not complied with by the paving company and, therefore, the taxbills were void? When the particular ordinance which orders an improvement, provides that it must be completed within a certain time and the prescribed time ' is exceeded, taxbills cannot be collected. [Heman v. Gilliam, 171 Mo. 258, 71 S. W. 163.] The law seems to be the same way when the particular ordinance is silent regarding the time for completion; but there is a gen- . eral ordinance relating to public improvements in force, requiring the work to be performed within the agreed time. [Allen v. Lobsap, 188 Mo. 692, 87 S. W. 926; Springfield v. Davis, 80 Mo. App. 574; Heman v. Gilliam, 171 Mo. loc. cit. 267, 71 S. W. 163.] The present contract was not rendered indefinite as to the time limit for finishing the work by prescribing a per diem forfeiture for failure to finish in the time stipulated, as was the contract is Hernán v. Gilliam. The Diavis case just cited, dealt with the same general ordinance of the city of Springfield with which we must deal in the present case, and the contract under which the work was done limited the time of completion to sixty days. Applying [49]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Paul
136 Mo. App. 524 (Missouri Court of Appeals, 1909)
Paul v. Conqueror Trust Co.
102 S.W. 1070 (Missouri Court of Appeals, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
96 S.W. 257, 120 Mo. App. 41, 1906 Mo. App. LEXIS 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-springfield-ex-rel-gilsonite-construction-co-v-schmook-moctapp-1906.