This text of 420 F.3d 440 (City of Shoreacres v. Waterworth) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Shoreacres v. Waterworth, 420 F.3d 440, 2005 WL 1864251 (5th Cir. 2005).

Opinion

420 F.3d 440

CITY OF SHOREACRES; et al., Plaintiffs,
City of Shoreacres; City of Taylor Lake Village, Texas; Galveston Bay Conservation and Preservation Association; Texas Committee on Natural Resources; Galveston Bay Foundation; Houston Yacht Club; Professionals Involved in Seafood Concerned Enterprises; Gulf Restoration Network; City of Seabrook; City of El Lago, Plaintiffs-Appellants,
v.
Leonard D. WATERWORTH, Colonel, District Engineer, Galveston District-U.S. Army Corps of Engineers; Robert B. Flowers, Lieutenant General, Commander and Chief of Engineers, U.S. Army Corps of Engineers; Les Brownlee, Acting Secretary of the Army; United States Army Corps of Engineers, Defendants-Appellees,
Port of Houston Authority, Intervenor Defendant-Appellee.

No. 04-20527.

United States Court of Appeals, Fifth Circuit.

August 8, 2005.

COPYRIGHT MATERIAL OMITTED COPYRIGHT MATERIAL OMITTED James B. Blackburn, Jr. (argued), Blackburn & Carter, Houston, TX, for City of Shoreacres, City of Taylor Lake Village, Texas, Galveston Bay Conservation and Preservation Ass'n, Texas Committee on Natural Resources, Galveston Bay Foundation, Houston Yacht Club, Professionals Involved in Seafood Concerned Enterprises, Gulf Restoration Network and City of El Lago.

Judith R. Blakeway, Strasburger & Price, San Antonio, TX, for City of Seabrook.

John A. Bryson (argued), U.S. Dept. of Justice, Environment & Natural Resources Div., Washington, DC, for District-U.S. Army Corps of Engineers, Robert B. Flowers, Les Brownlee and United States Army Corps of Engineers.

Sharon M. Mattox (argued), Vinson & Elkins, Houston, TX, for Port of Houston Authority.

Nathan Allan Wesely, Royston, Rayzor, Vickery & Williams, Houston, TX, for West Gulf Maritime Ass'n, Amicus Curiae.

Gregory Thomas Broderick, Pacific Legal Foundation, Sacramento, CA, for Pacific Legal Foundation and John A. Rapanos, Amici Curiae.

Anthony G. Buzbee, Buzbee Law Firm, Galveston, TX, for International Longshoremen's Ass'n Local No. 24, International Longshoremen's Ass'n Local No. 28, International Longshoremen's Ass'n Local No. 1530 and International Longshoremen's Ass'n Local No. 1351, Amici Curiae.

Appeal from the United States District Court for the Southern District of Texas.

Before GARWOOD, SMITH and CLEMENT, Circuit Judges.

GARWOOD, Circuit Judge:

Plaintiffs-appellants brought this suit under the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq., and the Clean Water Act (CWA), 33 U.S.C. § 1251 et seq., against the United States Army Corps of Engineers (Corps) seeking recision of a 33 U.S.C. § 1344 dredge and fill permit issued by the Corps to the Port of Houston (Port) for the construction of a ten-berth cargo and cruise ship terminal adjacent to the Bayport Shipping Channel off Galveston Bay. The district court granted summary judgment to the Corps and the intervenor Port. We affirm.

Facts and Proceedings Below

On October 8, 1998, the Port filed an application with the Corps for a 33 U.S.C. § 1344 permit to dredge and fill navigable waters of the United States. The Port proposed building a cargo and cruise ship terminal on undeveloped land adjacent to the Bayport Shipping Channel along the northwestern coast of Galveston Bay. The plan called for seven cargo ship berths, three cruise ship berths, and extensive ancillary facilities along a region of the coast that is heavily industrialized. The Port intends to finance the Bayport project with proceeds from a $387 million 1999 bond issue for that purpose approved by the voters of Harris County, Texas in which both the Port and Bayport are located.

The Corps undertook the comprehensive technical and public interest review required by the Code of Federal Regulations. See, e.g., 33 C.F.R. § 230 (procedures for implementing NEPA); 33 C.F.R. § 320 (outlining the Corps' general regulatory policy); 40 C.F.R. § 1502 (preparation of an environmental impact statement). Following public input and preliminary technical work, the Corps issued its Draft Environmental Impact Statement (DEIS) on November 12, 2001. The Corps continued its technical work and accepted public comment on the DEIS until August 2002. Nine months later, on May 16, 2003, the Corps issued its Final Environmental Impact Statement (FEIS) and entertained further public comment until August 2003. The Corps then issued its eight-volume Record of Decision (ROD) on December 19, 2003, in which the Corps approved a plan for the construction of the Bayport terminal and the mandatory preservation of undeveloped areas elsewhere to compensate for the environmental loss at Bayport. The Corps granted the 33 U.S.C. § 1344 dredge and fill permit on January 5, 2004, over five years after the permit application was filed.

Meanwhile, as the Corps was considering the Bayport permit application, it was also considering a similar dredge and fill permit application filed in April 2000 by Texas City, Texas to build a six-berth cargo terminal at Shoal Point in Galveston County along the southwestern coast of Galveston Bay. The Corps issued a permit to Texas City on April 23, 2003, approximately one month before it handed down its FEIS on the Port's Bayport permit application.

On January 29, 2004, appellants filed their second (and final) amended complaint asking the district court to vacate the permit and enjoin the Port from proceeding with the Bayport project because the Corps had issued the permit in violation of the CWA and NEPA.1 Appellants also sought a preliminary injunction against construction while judicial review was pending. Rather than rule on this motion, the district court agreed to an expedited pretrial schedule and a summary judgment ruling by May 4, 2004. The Port then agreed to "stand still" while the case went forward through summary judgment. The parties filed cross-motions for summary judgment in April 2004, and the district court granted summary judgment to appellees and against appellants on May 4, 2004. Final judgment was entered the same day.

Discussion

1. Standard of Review

We review a grant of summary judgment de novo under the same standard applied by the district court. Terrebonne Parish Sch. Bd. v. Mobil Oil Corp., 310 F.3d 870, 877 (5th Cir. 2002).

The decision of the Corps to grant a permit under 33 U.S.C. § 1344 is reviewed under the standard set forth in the Administrative Procedures Act, 5 U.S.C. § 701 et seq. We will "hold unlawful and set aside" the Corps' permit to the Port only if we determine that the Corps' "action, findings, and conclusions" are, inter alia, "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A); Shell Offshore v. Babbitt, 238 F.3d 622, 627 (5th Cir. 2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mississippi River Basin Alliance v. Westphal
230 F.3d 170 (Fifth Circuit, 2000)
Shell Offshore Inc. v. Babbitt
238 F.3d 622 (Fifth Circuit, 2001)
Terrebonne Parish School Board v. Mobil Oil Corp.
310 F.3d 870 (Fifth Circuit, 2002)
United States v. Needham
354 F.3d 340 (Fifth Circuit, 2003)
City of Shoreacres v. Waterworth
420 F.3d 440 (Fifth Circuit, 2005)
United States v. Riverside Bayview Homes, Inc.
474 U.S. 121 (Supreme Court, 1985)
Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
Department of Transportation v. Public Citizen
541 U.S. 752 (Supreme Court, 2004)
Custer County Action Ass'n v. Garvey
256 F.3d 1024 (Tenth Circuit, 2001)
Danforth Manning v. The Upjohn Company
862 F.2d 545 (Fifth Circuit, 1989)
North Buckhead Civic Association v. Skinner
903 F.2d 1533 (Eleventh Circuit, 1990)
Citizens Against Burlington, Inc. v. Busey
938 F.2d 190 (D.C. Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
420 F.3d 440, 2005 WL 1864251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-shoreacres-v-waterworth-ca5-2005.