City of Seattle v. Sparger

265 P. 173, 147 Wash. 126, 1928 Wash. LEXIS 528
CourtWashington Supreme Court
DecidedMarch 19, 1928
DocketNo. 20954. Department One.
StatusPublished

This text of 265 P. 173 (City of Seattle v. Sparger) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Seattle v. Sparger, 265 P. 173, 147 Wash. 126, 1928 Wash. LEXIS 528 (Wash. 1928).

Opinion

Tolman, J.

In April, 1923, the respondent E. L. Sparger entered into a contract with the city of Seattle for the construction of a tunnel under the Duwamish "Waterway. He gave a statutory bond in the sum of $40,000 for the faithful performance of the contract, with the respondent Aetna Casualty and Surety Company as surety thereon. The work was to be paid for, under the contract, on the unit price plan. The contract is in the form commonly used by the city of Seattle for such work, is too long to be here set out in full, but carries the usual provisions for the commencement of the work and its regular and uninterrupted prosecution under the direction of the city engineer; *127 that the contractor must satisfy himself as to the material to he penetrated and the difficulties likely to be encountered; and provides that estimates shall he issued monthly covering all work done in the preceding month, and that the city shall pay such estimates, less the retained percentages provided by the contract, on or about the 25th day of the month following the performance of the work for which the estimate has been issued. There is also a provision to the effect that the city engineer, if in his opinion the work is unnecessarily delayed and will not he finished within the prescribed time, shall notify the contractor to that effect in writing, and if within five days thereafter the contractor has not taken proper measures to insure the satisfactory completion of the work, the hoard of public works may, on notice, require the contractor to discontinue, and may itself employ a force and complete the work, and the expenditures thereby caused shall be paid out of moneys due or which might become due under the contract; and if greater than that, that the contractor shall he liable for the excess.

The work started about May 15,1923, and proceeded more or less satisfactorily until December of that year, when difficulties were encountered. Work was suspended, the contractor sealed up the tunnel to prevent its caving in and filling up, and the city claims that he abandoned the work on December 17,1923. There was admittedly due the contractor for work done in November, $4,241.50, for which an estimate had been given, and for which a warrant would be due on the 25th of that month. And there was also $1,893.65 earned by the contractor in December for which no estimate was ever issued and which has not been paid. On December 18, after there had been some discussion between the contractor and the representatives of the city, with reference to the difficulties which caused the *128 sealing of the tunnel, and with reference to further proceeding with the work, the city engineer wrote the contractor a letter, bearing that date, saying that the work was not proceeding in a satisfactory manner and that he was led to the conclusion that the contract would not be completed within the specified time, and

“You are therefore notified at this time that, unless you shall proceed with said work within five days from the date of this notice, you are cited to appear before the board of public works and show cause why steps should not be taken to declare you in default on your contract.”

At about the time this letter was received by the contractor, and before- he had any time within which to determine how to proceed to overcome the difficulties encountered in the work and complete the contract, he learned, by inquiry at the office of the city comptroller, that the superintendent of the water department had filed with the comptroller a written memorandum directing the comptroller to withhold the warrant for $4,241.50 until further advices. The contractor’s payroll was then due. It appears clearly that the withholding of the warrant prevented his further financing the work, and the warrant being refused, he elected to treat it as a breach of the contract on the part of the city, and did not thereafter undertake to resume work on the contract.

The city thereupon, about the 14th of January, 1924, purported to cancel the contract, and still later let a new contract to another, under which the work was finally completed. Thereupon the city brought this suit against the contractor and his bondsman, claiming that, by reason of the contractor’s default, it was obliged to relet the contract, and that by doing so the work cost the city $88,611.56 more than it would have cost under the Sparger contract. And by a second and *129 a third cause of action the city also claimed items for the furnishing of electric energy for power and for installation. As to these items there is practically no dispute.

A jury was impaneled to hear the cause, and after all the evidence had been received, each party moved for an instructed verdict, and the court thereupon, with the consent of all, or at least without objection, discharged the jury, and made findings of fact and conclusions of law, and entered judgment, whereby it denied to the city any relief on its first cause of action, but granted its demands upon its second and third causes of action, though refusing to render judgment thereon against the bond, and awarding to Sparger, upon his counterclaim, the amount which he has earned under the contract and which was unpaid on December 17, 1923. The city’s claims as allowed, being the smaller, were offset, and respondent Sparger was by the judgment allowed recovery of the overplus in his favor. The city has appealed from the judgment.

As we see it, the question here presented is one of fact only. The record is long and involved, •much of the evidence being of a technical character; but, after a painstaking study of it, notwithstanding that the burden of establishing his affirmative defense was upon respondent Sparger, we feel satisfied that the trial court reached a correct conclusion. It is not seriously contended that the city gained any rights by reason of its engineer’s letter of December 18, 1923, nor could it be, as the city made no attempt, even if the conditions were as stated in the letter, to proceed under the terms of the contract. The burden was on the city to show an abandonment of the work, and that burden it has failed to sustain. The failure of the city to pay the estimate due in December is an admitted *130 fact, and since such failure to pay was not justified by a previous abandonment of the work by the contractor, it was in itself a breach of the contract justifying the contractor in refusing to proceed with the work. Bishop v. Ryan Construction Co., 106 Wash. 254, 180 Pac. 126; Dyer v. Middle Kittitas Irr. Dist., 25 Wash. 80, 64 Pac. 1009.

The controlling facts found by the trial court are shown in the following quotation from his findings:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bishop v. T. Ryan Construction Co.
180 P. 126 (Washington Supreme Court, 1919)
Dyer v. Middle Kittitas Irrigation District
64 P. 1009 (Washington Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
265 P. 173, 147 Wash. 126, 1928 Wash. LEXIS 528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-seattle-v-sparger-wash-1928.