City of Seattle v. Federal Energy Regulatory Commission

923 F.2d 713
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 15, 1991
DocketNo. 89-70486
StatusPublished
Cited by1 cases

This text of 923 F.2d 713 (City of Seattle v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Seattle v. Federal Energy Regulatory Commission, 923 F.2d 713 (9th Cir. 1991).

Opinion

FERNANDEZ, Circuit Judge:

Public Utility District No. 1 of Pend Or-eille County, Washington (PUD) petitioned the Federal Energy Regulatory Commission (FERC) for an order interpreting a license which had been granted to the City of Seattle (Seattle). The license provision in question gave PUD certain rights to receive power from Seattle. FERC issued an order, which had the effect of requiring Seattle to abide by the terms of the license, and which also interpreted the scope of the license in a manner favorable to PUD. We uphold the determinations by the FERC.

BACKGROUND

In the 1950’s, PUD and Seattle competed for the right to install a hydroelectric facility on the Pend Oreille River (the Boundary Project). Ultimately, the Federal Power Commission (FPC) issued the license to Seattle, but because it was recognized that it was somewhat unjust to prefer Seattle to the energy district in the county where the project was to be located, an ameliorative provision was placed in the license. That provision is found at Article 49 and reads as follows:

The Licensee shall assign 48,000 kilowatts to the PUD from the Boundary Project at the PUD’s system load factor, any part or all of which shall be available to the PUD at cost upon two years’ notice by the PUD, to meet the load requirements of present or potential consumers (not including purchasers for resale) within the PUD’s service area; Provided, That the amount of power made available by this article shall be reduced by the amount of any power recaptured by the PUD under the Box Canyon contract with Seattle and sold for use outside Pend Oreille County.

While the provision was designed to balance the scales, it was not all that PUD desiréd. PUD, therefore, did not satisfy itself with that benefit. Rather, it continued to contest Seattle’s rights, but it was ultimately unsuccessful in that contest. See Public Util. Dist. No. 1 v. FPC, 308 F.2d 318 (D.C.Cir.1962), cert. denied, 372 U.S. 908, 83 S.Ct. 719, 9 L.Ed.2d 716 (1963); see also City of Seattle v. Beezer, 376 U.S. 224, 84 S.Ct. 709, 11 L.Ed.2d 656 (1964).

For many years thereafter, PUD did not seek to use the boon given to it by Article 49. However, in 1985 it did seek to draw upon two megawatts of power, and that was provided to it under certain interim agreements. It then occurred that an opportunity presented itself to PUD when a new large customer, the Ponderay Newsprint Company (Ponderay), sought to enter PUD’s service area in Pend Oreille County. [715]*715That company would need a substantial amount of power, and PUD contracted to supply that power to the company. Of course, PUD had to find the necessary supplies, so it turned to Article 49 and requested 24 megawatts from that source. It also contracted with the Bonneville Power Administration (BPA) for the supply of additional power, and BPA undertook to build the transmission lines necessary to move the electricity to Ponderay. -Seattle, which was now called upon to perform under Article 49, was displeased with that prospect and asserted that it need not do so at all. Given Seattle’s position, PUD petitioned FERC to interpret the license and to grant relief against Seattle.

Seattle responded. It claimed that Article 49 could not be enforced because PUD had continued to contest Seattle’s rights after the license was issued. It also contended that BPA’s involvement was illegal, and that should preclude PUD from demanding the power. Moreover, it asserted claims that the power should be sold at Seattle’s cost of replacing the number of megawatts taken, and that allocation of costs on a demand-related basis would be unfair to it.

BPA intervened to assert that FERC lacked jurisdiction to review its relationship with PUD, and to suggest that Seattle’s attack came too late in any event. Puget Sound Power and Light Co. also intervened. It asserted that Seattle’s attack came too early.

FERC did not agree with Seattle and, without holding an evidentiary hearing, FERC issued its order to that effect. It also reiterated that position when it turned aside a motion by Seattle for reconsideration.

Seattle then filed this Petition for Review with us, in which it raised the already mentioned issues and, in addition, asserted that FERC erred when it failed to hold an evidentiary hearing.

JURISDICTION AND STANDARD OF REVIEW

We have jurisdiction. to entertain this Petition for Review pursuant to ■ 16 U.S.C. § 825Z.

We examine decisions of FERC to determine whether they are “arbitrary, capricious, an abuse of discretion, unsupported by substantial evidence, or not in accordance with law.” The Steamboaters v. FERC, 759 F.2d 1382, 1388 (9th Cir.1985). In so doing, we generally “show great deference to [FERC’s] interpretation of the law which it is charged with administering.” Id.

DISCUSSION

A. FERC’s Failure to Hold an Eviden-tiary Hearing.

, At the- threshold we are met with Seattle’s claim that FERC’s decision was arbitrary because it failed to grant a hearing on Seattle’s claims. For that proposition Seattle cites National Wildlife Fed’n v. FERC, 801 F.2d 1505 (9th Cir.1986). Undoubtedly, as that case indicates, it would be arbitrary for FERC to ignore the evidence before it or to fail to consider all proper aspects of the issues with which it was faced. Id. at 1511-12. That, however, is of no help to Seattle in this case.

Here, as the ensuing discussion will underscore, the situation is like the one dealt with in Sierra Ass’n for Env’t v. FERC, 744 F.2d 661 (9th Cir.1984). Here, as there, the issues before FERC required no evidentiary hearing, for they raised no material issues of fact. Rather, they were legal questions based upon an historical factual record that was not in real dispute. The resolution of the issues before FERC simply did not require a hearing under the circumstances of this case.

Seattle also complains of FERC’s refusal to conduct an informal conference between it and PUD. It points, however, to no authority that would require an informal conference. At any rate, even though PUD was recalcitrant on the issue, FERC made it quite clear that it would render informal aid if both parties wanted it.

We must, of course, be satisfied that FERC “properly addressed all the relevant [716]*716factors in dispute and that a formal hearing was unnecessary.” Pacific Gas & Elec. Co. v. FERC, 746 F.2d 1383, 1386 (9th Cir.1984). We are. Beyond that, we allow FERC “wide discretion in selecting its own procedures.” Id.

In short, the procedures used here did not deprive Seattle of any rights.

B. Interpretation of the License.

The principal issue before FERC was the proper interpretation of Article 49 of the license. Its interpretation is entitled to deference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
923 F.2d 713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-seattle-v-federal-energy-regulatory-commission-ca9-1991.