City of Savage v. Varey

358 N.W.2d 102, 1984 Minn. App. LEXIS 3787
CourtCourt of Appeals of Minnesota
DecidedNovember 13, 1984
DocketC2-84-736
StatusPublished
Cited by11 cases

This text of 358 N.W.2d 102 (City of Savage v. Varey) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Savage v. Varey, 358 N.W.2d 102, 1984 Minn. App. LEXIS 3787 (Mich. Ct. App. 1984).

Opinion

OPINION

FORSBERG, Judge.

This is an appeal from the entry of summary judgment in favor of the City of Savage in its action for reformation of a “General Release” signed by all of the parties here as settlement of an earlier action.

Respondents Arnold and Mildred Varey had brought a trespass action for damage to their property resulting from a sewer construction project involving the City, Or-fei and Sons (the contractor), and appellant Owen Ayres & Associates. The three defendants each paid $2,000 to the Vareys in *104 the settlement. The General Release, drafted by Owen Ayres’ attorney, discharged not only the Vareys’ claims but all claims the defendants might have against each other. The City later brought a claim for arbitration pursuant to its contract with Owen Ayres against that company, which contended that the claim was barred by the release. The trial court granted summary judgment reforming the release. We affirm.

FACTS

The City in 1977 contracted with appellant’s predecessor, Ellison-Philstrom-Ayres [hereafter, Ayres], for architectural and engineering services in connection with the Credit River District Improvement Project, a project involving sewer, street restoration, and utility work. Planning was completed in 1978 and 1979, and the project constructed in 1979 and 1980. Respondent Orfei and Sons was the contractor. Total cost of the mile-long project was around $7 million.

The Vareys, residents of the City and owners of land along the project from whom the City had acquired an easement, brought an action alleging that the City and its contractors had exceeded the bounds of the easement granted, removed 40 trees and failed to replace soil and sod. They asked for actual damages of $10,195, as well as treble damages.

The City denied the claims, and asserted a cross-claim against Ayres and Orfei, alleging that its negligence, if any, was secondary to that of the other defendants. Defendants Ayres and Orfei also cross-claimed, against the City as well as each other. All sought indemnity or contribution for any sums found owing to the Var-eys.

The Varey action came on for trial on April 26, 1983, but following negotiations a settlement agreement was reached. The parties’ understanding of the agreement was set forth on the record. The only mention of the effect of the settlement on cross-claims among the defendants was the following statement by Ayres’ attorney:

[MR. HALLS:] “And, secondly, it’s understood that all crossclaims and counterclaims are also released by this settlement.”

The parties agreed that Halls, co-counsel for Ayres, would prepare a release. In addition to discharging the Vareys’ claims, this “General Release” discharged all claims among the defendants, “whether related or unrelated to the present dispute as to law or facts or both * * The release purported to cover all claims arising out of the contract, as follows:

“... all claims, cross-claims, and counterclaims which were asserted or which could have been asserted in connection with each of the other defendants’ (and Owen Ayres’) services, labor, material or material furnished, or agreements made, or acts of carelessness or neglect, in connection with that certain construction project known as the Credit River District Improvements Project performed on the property of the Plaintiffs in Savage, Minnesota.”

The release was signed by all parties, including officials of the City.

The City later made a petition for arbitration of claims against Owen Ayres arising out of the Credit River Project. This petition, which is dated June 24, 1983, lists fourteen separate grievances, only one of which concerns the Varey claim. Total damages alleged are $655,872.09.

The petition for arbitration was required by the City’s contract with Owen Ayres, which provided that “any controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by arbitration * *

Both parties have submitted affidavits from the attorneys involved in the Varey settlement negotiations. The City’s attorney states that the negotiations at no time included any claims other than those made by the Vareys. This position is supported by the attorneys for the Vareys, and for Orfei, the other Varey defendant. Neither of these parties contests the reformation of the release.

*105 The attorneys for Owen Ayres state that it was agreed that a “broad form” release would be drafted releasing “all claims.” Each states that the General Release conforms to his understanding of the intent of the attorneys in arriving at the settlement.

ISSUES

1. Did the trial court err in ordering summary judgment reforming the release?

2. Are the City’s arbitration claims barred by its failure to assert them in the trespass action?

ANALYSIS

1. Summary judgment reforming the release

The trial court found that the settlement discussions on April 26, 1983, were limited to the liability of the Varey defendants in that action. It found that the General Release did not conform to the settlement agreement.

Reformation of a written instrument is granted if the following is shown:

1) there was a valid agreement between the parties expressing their real intentions;
2) the written instrument failed to express those intentions; and
3) the failure was due to mutual mistake, or a unilateral mistake accompanied by fraud or inequitable conduct of the other party.

Nichols v. Shelard Nat. Bank, 294 N.W.2d 730, 734 (Minn.1980).

The trial court found the first two elements required for reformation. Although it did not find the third element — here, unilateral mistake accompanied by inequitable conduct — it summarized the case as follows:

“It is unconscionable to this court how defendant Ayres on April 26, 1983, could conclude that any and all claims that may arise out of the Credit River Sewer Project costing approximately $7 million were summarily released upon the payment of $2,000 by said defendant toward the total of $6,000 settlement of the Var-ey claims.”

Appellant contends that its attorneys understood the settlement negotiations in Varey to include all potential Credit River claims. It claims that they understood Owen Ayres’ $2000 contribution towards the settlement released it from all claims on the $7 million project. As the trial court noted, this is inherently incredible, especially as appellant does not assert that any other claims were discussed.

On a motion for summary judgment, all inferences from circumstantial evidence and all doubts must be resolved against the moving party. Forsblad v. Jepson, 292 Minn. 458, 195 N.W.2d 429

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Construction Services, Inc. v. Belton
749 N.W.2d 388 (Court of Appeals of Minnesota, 2008)
Quality Improvement Consultants, Inc. v. Williams
129 F. App'x 719 (Third Circuit, 2005)
Hughes v. Lund
603 N.W.2d 674 (Court of Appeals of Minnesota, 1999)
Drilling v. Berman
589 N.W.2d 503 (Court of Appeals of Minnesota, 1999)
Shamblin v. Beasley
1998 OK 88 (Supreme Court of Oklahoma, 1999)
Bast v. Capitol Indemnity Corp.
562 N.W.2d 24 (Court of Appeals of Minnesota, 1997)
Dairyland Insurance Co. v. Starkey
524 N.W.2d 491 (Court of Appeals of Minnesota, 1995)
Personalized Marketing Service, Inc. v. Stotler & Co.
447 N.W.2d 447 (Court of Appeals of Minnesota, 1989)
Ackerman v. American Family Mutual Insurance Co.
435 N.W.2d 835 (Court of Appeals of Minnesota, 1989)
County of Hennepin v. Ada-Bec Systems
394 N.W.2d 611 (Court of Appeals of Minnesota, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
358 N.W.2d 102, 1984 Minn. App. LEXIS 3787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-savage-v-varey-minnctapp-1984.