City of Santa Clara v. Watkins

984 F.2d 1008, 93 Cal. Daily Op. Serv. 643, 93 Daily Journal DAR 1305, 1993 U.S. App. LEXIS 1260, 1993 WL 15232
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 28, 1993
DocketNo. 91-15168
StatusPublished
Cited by4 cases

This text of 984 F.2d 1008 (City of Santa Clara v. Watkins) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Santa Clara v. Watkins, 984 F.2d 1008, 93 Cal. Daily Op. Serv. 643, 93 Daily Journal DAR 1305, 1993 U.S. App. LEXIS 1260, 1993 WL 15232 (9th Cir. 1993).

Opinion

FLETCHER, Circuit Judge:

Appellants-defendants and appellants-in-tervenors-defendants (this court previously held them to have a right to intervene as parties affected by the settlement) appeal the district court’s order interpreting a settlement agreement between appellees-plain-tiffs and appellants-defendants. At issue is a term in the settlement agreement that the parties neglected to define. The elusive term is “nonwithdrawable” as applied to hydroelectric power allocated to municipalities in northern California. Appellants 1 contend that “nonwithdrawable” is a [1010]*1010term of art that incorporates three exceptions. Appellees2 and the district court interpret the word to mean “not withdraw-able for any reason.” Our review of the contract, the extrinsic evidence presented to the district court and the statutory and contractual context of the negotiations lead us to REVERSE.

FACTS

This litigation concerns the allocation of hydroelectric power from a' federal reclamation project. Details of the dispute as it developed from the early 1960’s until 1978 are set forth in prior published opinions. See City of Santa Clara v. Kleppe, 418 F.Supp. 1243 (N.D.Cal.1976), rev’d and remanded, City of Santa Clara v. Andrus, 572 F.2d 660, 668 (9th Cir.), cert. denied, 439 U.S. 859, 99 S.Ct. 176, 58 L.Ed.2d 167 (1978). We summarize that history here.

The Central Valley Project (CVP) is a multipurpose federal reclamation project consisting of dams, hydroelectric power plants, transmission lines, and irrigation canals. CVP’s primary purpose is irrigation. However, the Reclamation Act of 1939 permits power generated beyond the needs of CVP to be sold or leased. Because CVP power is much less expensive than power purchased from private utilities, customers in Northern California compete vigorously for it. Western is the agency of the Department of Energy that oversees CVP and markets its power.

CVP expanded its generating capacity in the early 1960’s, and made contracts to sell the power to numerous customers, including Shasta and Cities. The city of Santa Clara was not among the customers. When it tried to contract for power in 1965, it was informed that all anticipated power was committed to other customers. However, CVP did agree to sell some power to Santa Clara on a “withdrawable” basis. The amount of withdrawable power allocated to Santa Clara grew throughout the late 1960’s, and the first withdrawals began in the 1970’s.

Santa Clara brought suit in federal court, alleging (among other things) that by allocating “nonwithdrawable power” to some customers but not to Santa Clara, the Secretary violated the statutory command that in sales of CVP power “preference shall be given to municipalities and other public corporations or agencies” and REA cooperatives, 43 U.S.C. § 485h(c). City of Santa Clara v. Kleppe, 418 F.Supp. 1243 (N.D.Cal.1976). On appeal, we held that the Secretary had unreviewable discretion to determine how allocations among preference customers were made. City of Santa Clara v. Andrus, 572 F.2d 660, 668 (9th Cir.), cert. denied, 439 U.S. 859, 99 S.Ct. 176, 58 L.Ed.2d 167 (1978). We also held, however, that the Secretary could not continue its practice of selling CVP power to PG & E, a non-preference customer, if a preference customer was willing and able to purchase it. The case was remanded for determination as to whether Santa Clara was willing and able to buy power allotted to PG & E. Id. at 672. Both opinions used the terms “withdrawable” and “nonwith-drawable” but did not discuss whether the latter entailed the exceptions at issue in this case. See Kleppe, 418 F.Supp. at 1248 n. 14, 1255, 1259 n. 40, 1262; Andrus, 572 F.2d at 663-65, 668.

Extended settlement negotiations followed this court’s remand of Andrus, and resulted in a Memorandum of Understanding (MOU) dated February 8, 1980. The MOU allocates 472.6 MW of CVP power among the customers that were parties to the Andrus suit. It is liberally sprinkled with the terms “withdrawable,” “nonwith-drawable,” “nonwithdrawable customers,” [1011]*1011“withdrawable power,” and the like. Santa Clara, for example, has the right under the MOU to purchase 65 MW of CVP power “on a nonwithdrawable basis” and an additional 60 MW “on a withdrawable basis.” MOU ¶ 6-7. Nowhere are these terms defined. The parties signed a Mutual Release of claims on August 29, 1980 that expressly incorporated the MOU. The district court approved the settlement and dismissed the lawsuit in an order dated October 3,1980, but retained jurisdiction for the purpose of entering orders necessary to enforce compliance.

The MOU was not itself a contract for the sale of power; it was a contract to enter into such contracts. See MOU ¶ 24 (“The parties hereto agree to execute those new contracts and amendments to the contracts between any of them which are necessary to implement the commitments contained herein”). The current problem arose when Western sent contracts to individual customers to implement the commitments made in the MOU. The tendered contracts contained provisions allowing Western to withdraw power from its customers on a pro rata basis if necessary to satisfy the power demands of what the parties refer to as “the three stated purposes.” Each of the three stated purposes has a statutory or contractual basis:

(1) “Project use” requirements of the CVP, i.e., the power CVP needs to operate its pumping, lighting, maintenance and other operations. Under CVP’s enabling statute, the Reclamation Project Act of 1939, no contract for sale of power “shall be made unless, in the judgment of the Secretary, it will not impair the efficiency of the project for irrigation purposes.” 43 U.S.C. § 485h(c). Only the surplus is available for sale.

(2) “First preference” customers in Trinity, Calaveras, and Tuolumne Counties, the sites of two of CVP’s dams. The statutes authorizing the construction of the Trinity River and New Melones projects require that Western devote up to 25% of the power from those projects to the “first preference” of certain customers in the counties where those projects are located. 69 Stat. 719 (Act of August 12, 1955); 76 Stat. 1173 (Act of October 23, 1962). Public utilities in Trinity, Calaveras and Tuolumne Counties (the “First Preference Customers”) are the beneficiaries of this stated purpose.

(3)“Load level protection” that caps deliveries of CVP power at a maximum of 1050 MW. Hydroelectric plants are subject to dips in production. In order to maintain regular output, they require “firming energy” from an outside source. In 1967, PG & E entered into a long-standing contract (“Contract 2948A”) to provide Western with up to 1050 MW of firming energy, an expansion from the previous 550 MW. Western’s existing contracts with Cities were amended in 1967 to take advantage of the increased capacity.

When the MOU was drafted, the parties considered the possibility of withdrawals for the three stated purposes to be “scant” (to the extent they thought about it at all). Findings at 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Crow Winthrop Operating Partnership
241 F.3d 1121 (Ninth Circuit, 2001)
City of Santa Clara v. Watkins
984 F.2d 1008 (Ninth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
984 F.2d 1008, 93 Cal. Daily Op. Serv. 643, 93 Daily Journal DAR 1305, 1993 U.S. App. LEXIS 1260, 1993 WL 15232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-santa-clara-v-watkins-ca9-1993.