City of San Antonio v. Casey Industrial, Inc.

Court of Appeals of Texas·Decided August 31, 2015·No. 04-14-00429-CV·Published

Opinion

ACCEPTED

04-14-00429-CV

FOURTH COURT OF APPEALS

SAN ANTONIO, TEXAS

8/31/2015 1:47:50 PM

KEITH HOTTLE

CLERK

NO. 04-00429-CV

IN THE COURT OF APPEALS FOR THE FILED IN 4th COURT OF APPEALS

FOURTH COURT OF APPEALS DISTRICTSAN ANTONIO, TEXAS SAN ANTONIO, TEXAS 08/31/2015 1:47:50 PM KEITH E. HOTTLE

Clerk

CITY OF SAN ANTONIO, ACTING THROUGH CITY PUBLIC SERVICE BOARD OF SAN ANTONIO Appellant,

v.

CASEY INDUSTRIAL, INC.,

Appellee.

On Appeal from the 408th Judicial District Court Bexar County, Texas

The Hon. Michael E. Mery, Presiding

CPS ENERGY’S RESPONSE TO

MOTION FOR RECONSIDERATION EN BANC

JUDITH R. BLAKEWAY ANNALYN G. SMITH State Bar No. 02434400 State Bar No. 18532500 STRASBURGER & PRICE, LLP SCHMOYER REINHARD, LLP 2301 Broadway 17806 IH-10 West, Suite 400 San Antonio, Texas 78215 San Antonio, Texas 78257 Telephone: (210) 250-6000 Telephone: (210) 447-8033 Facsimile: (210) 250-6100 Facsimile: (210) 447-8036 judith.blakeway@strasburger.com asmith@sr-llp.com

ATTORNEYS FOR APPELLANT

CPS ENERGY

TABLE OF CONTENTS

TABLE OF CONTENTS ................................................................................... i TABLE OF AUTHORITIES ............................................................................ ii ARGUMENT .................................................................................................... 1 A. The panel majority properly considered relevant evidence necessary to resolve the plea to the jurisdiction without reaching the merits. .............................................................................. 4 B. Because Casey does not claim damages recoverable under section 271.153, the panel majority correctly found that CPS Energy’s immunity from Casey’s claims was not waived. .................... 6 1. There is no balance due and owed by CPS Energy under section 271.153(a)(1). ....................................................................7 2. The “additional work” for which Casey seeks another $12 million was already included within contract price for the fixed-price contract, so Casey is not entitled to recover under section 271.153(a)(2). ........................................................ 8 C. There is no factual issue whether there is a writing signed by CPS Energy committing the ratepayers to pay an extra $12 million dollars—it is undisputed that there is no such writing. .......... 11 D. Casey had a full and fair opportunity in the trial court to develop the record as to immunity; it failed to request a continuance; and in the absence of written change orders—

which Casey admits do not exist—supplementation would be futile. .................................................................................................... 12 CONCLUSION ............................................................................................... 13 CERTIFICATE OF COMPLIANCE ................................................................ 14 CERTIFICATE OF SERVICE......................................................................... 14

i

TABLE OF AUTHORITIES

Page(s)

CASES City of San Antonio v. Casey Indus., Inc., 381 S.W.3d 589 (Tex. App.—San Antonio 2012, pet. denied) .................10

Lubbock Cnty. Water Control and Imp. Dist. v. Church & Akin, LLC, 44 S.W.3d 297 (Tex. 2014) ......................................................................... 1 Sharyland Water Sys. v. City of Alton, 354 S.W.3d 407 (Tex. 2011) ....................................................................... 6 Texas Dept. of Parks & Wildlife v. Miranda, 133 S.W.3d 217 (Tex. 2004) ....................................................................... 5 Tooke v. City of Mexia, 197 S.W.3d 325 (Tex. 2006) ..................................................................... 12 Ulico Gas Co. v. Allied Pilots Ass’n, 262 S.W.3d 773 (Tex. 2008) ..................................................................... 11 Zachry Constr. Corp. v. Port of Houston Auth., 449 S.W.3d 98 (Tex. 2014) .......................................................... 1, 9, 11, 12 STATUTES TEX. LOC. GOV’T. CODE § 271.152 .................................................................... 13 TEX. LOC. GOV’T. CODE § 271.153(a)(1). ................................................... 7, 8, 9 TEX. LOC. GOV’T. CODE § 271.153(a)(2)............................................................ 8

TEX. LOC. GOV’T. CODE § 271.153(b)(1) ............................................................ 9

ii

ARGUMENT

The Texas Local Government Contract Claims Act does not waive

immunity from suit for damages not recoverable under section 271.153. The waiver does not depend on the outcome, but it “does require a showing of a substantial claim that meets the Act’s conditions.” Zachry Constr. Corp. v. Port of Houston Auth., 449 S.W.3d 98, 109 (Tex. 2014). Casey contends the panel majority impermissibly considered facts relating solely to the merits of Casey’s claim and CPS’s affirmative defenses rather than limiting its review to facts relevant to the trial court’s jurisdiction. Not so.

“[U]nder Chapter 271, the terms of the written contract are themselves the substance that determines whether immunity is waived. Lubbock Cnty. Water Control and Imp. Dist. v. Church & Akin, LLC, 44 S.W.3d 297, 304 (Tex. 2014). Here, the contract was a fixed-price contract under which CPS agreed to pay $85,760.12, and not a penny more. There is no writing in which CPS Energy agreed to pay an extra $12 million. That in itself demonstrates that the additional $12 million was not contemplated by the parties to the contract.

That conclusion is buttressed by other terms of the contract. The contract charges Casey (the “D/B Contractor”) with the responsibility to act as the overall construction manager of the contract and oversee

Wheelabrator’s performance using the “design-build” project delivery method consistent with a traditional turnkey approach. C.R. 156. Casey is responsible for delivering the complete and fully operational facility to CPS Energy on a lump-sum fixed-price basis. C.R. 79. Casey—not CPS Energy— assumes all risks of delay in the project’s schedule and is responsible for all costs related to bringing the project back on schedule. C.R. 108. To obtain a schedule relief change order, the contract requires Casey to show CPS Energy-caused delay. C.R. 114-15. Casey agreed that it was not entitled to more time or money for delays caused by Wheelabrator. C.R. 141, 142. Casey expressly agreed that no adjustment to price or schedule would be authorized as a result of mistakes relating to Casey or Wheelabrator’s respective portions of the work. C.R. 118. And although the contract authorized Casey to request a change order for more time or money if Casey was not in default itself and a default by Wheelabrator resulted in impairment of Casey’s work through no fault of Casey, C.R. 135, Casey never requested or obtained any change orders for the claims for which CPS Energy sought dismissal. Each of these provisions is just as relevant to determination of the trial court’s jurisdiction as the one sentence that Casey plucks out of context (Casey has no responsibility for Wheelabrator’s obligations).

As conceded by Casey’s counsel at oral argument:

 Casey agreed there was no indication of owner-caused delays;

 Casey agreed there were no construction change directives;

 Casey agreed there were no actual change orders.

In the absence of any of these facts, Casey’s claims do not fall within section 271.173 and, hence, there is no claim for damages allowed by section 271.153, and thus no waiver of governmental immunity.

Free access — add to your briefcase to read the full text and ask questions with AI

City of San Antonio v. Casey Industrial, Inc., (Tex. Ct. App. 2015).

City of San Antonio v. Casey Industrial, Inc. (City of San Antonio v. Casey Industrial, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Ulico Casualty Co. v. Allied Pilots Ass'n
262 S.W.3d 773 (Texas Supreme Court, 2008)
Tooke v. City of Mexia
197 S.W.3d 325 (Texas Supreme Court, 2006)
Lacy v. State
44 S.W.3d 296 (Supreme Court of Arkansas, 2001)
Hearts Bluff Game Ranch, Inc. v. State
381 S.W.3d 468 (Texas Supreme Court, 2012)
Sharyland Water Supply Corp. v. City of Alton
354 S.W.3d 407 (Texas Supreme Court, 2011)