the City of San Antonio, Texas, Acting Through the City Public Service Board of San Antonio, Texas v. Casey Industrial, Inc.

381 S.W.3d 589, 2012 Tex. App. LEXIS 6293, 2012 WL 3104429
Court of Appeals of Texas·Decided August 1, 2012·No. 04-11-00791-CV, 04-11-00814-CV·Published·Cited by 4 cases

Opinion

OPINION

Opinion by: SANDEE BRYAN MARION, Justice.

These aré two consolidated accelerated appeals arising from orders in favor of Casey Industrial, Inc. (“Casey”). In the first order, the trial court granted Casey’s motion for summary judgment, holding that the parties’ contract was void. The trial court granted the parties permission to appeal pursuant to Texas Civil Practice and Remedies Code section 51.014(d). 1 In the second order, the trial court denied the plea to the jurisdiction filed by the City of San Antonio Acting through City Public Service Board of San Antonio a/k/a CPS Energy (hereinafter, “CPS”). CPS appealed pursuant to Texas Civil Practice and Remedies Code section 51.014(a)(8). 2 On the parties’ motion, this court consolidated the two appeals. On the issue of whether the contract is void, we reverse the summary judgment in favor of Casey, render summary judgment in favor of CPS, and remand for further proceedings. On CPS’s plea to the jurisdiction, we reverse the trial court’s order denying the plea and we render judgment that Casey’s quantum meruit claim against CPS is dismissed for want of jurisdiction.

BACKGROUND

In an effort to reduce air pollution at the J.T. Deely power plant, CPS proposed to install two baghouses, which are multistory, warehouse-size structures that collect fly ash, a by-product of the coal combustion process. CPS chose a design-build project delivery method for the design and construction of the baghouses, and offered the project for competitive bidding. Casey responded and submitted a proposal that identified Wheelabrator Air Pollution Control, Inc. (“Wheelabrator”) as the subcontractor to Casey and as both the baghouse supplier and as primary engineer for the balance of plant services. Casey also identified Wheelabrator as its technology partner and it included Wheelabrator as part of its engineering team.

CPS eventually selected Casey and requested a meeting with Casey for the purpose of negotiating a contract. As part of the contract, CPS was required to secure payment and performance bonds from Casey. During the negotiation process, Casey informed CPS that it could not bond Wheelabrator’s work. To address the bonding issue, CPS agreed to Casey’s proposal that the scope of the work for the project be divided between Casey, which would perform the design and construction *591 of the baghouses, and Wheelabrator, which would perform the equipment design and supply tasks. The contract the parties negotiated was signed by CPS, Casey, and Wheelabrator.

The underlying dispute arose when Wheelabrator was allegedly unable to meet its obligations and Casey incurred additional costs to satisfy those obligations. Casey then sued CPS to recover these additional costs, alleging three causes of actions: implied in law/quasi-contract, quantum meruit, and breach of contract. Casey moved for a partial summary judgment on two grounds: (1) the contract is void because CPS violated statutory procurement laws and (2) Casey is entitled to recover under the doctrine of quantum meruit. CPS moved for summary judgment on a variety of grounds: (1) Casey lacks standing to bring its claim; (2) Casey’s claim is moot; and (3) the contract is not void because CPS complied with the appropriate procurement laws and/or its own internal procurement procedures. The trial court denied CPS’s motion. The trial court granted Casey’s motion, specifically holding the contract was “void because [sic] not a design build contract' and in house procurement procedures did not save it.” The court also held Casey “is entitled to prove liability, if any, and damages, if any, under the doctrine of quantum meruit.”

CPS also filed a plea to the jurisdiction on the ground that it was immune from suit for additional work or for quantum meruit. The trial court denied the plea.

On appeal, CPS raises two issues: (1) the trial court erred in granting Casey’s motion for summary judgment and in denying its motion for summary judgment, and (2) the trial court erred in denying CPS’s plea to the jurisdiction because there is no waiver of governmental immunity from suit for quantum meruit claims. On appeal, CPS does not challenge the trial court’s denial of its motion for summary judgment on the grounds that Casey lacks standing; Casey’s claim is moot, CPS’s affirmative defense of laches, or CPS’s affirmative defense of unclean hands. Instead, on appeal, CPS asks only that its “motion for summary judgment declaring the contract valid be granted and the case remanded for trial on [the parties’] breach of contract claims.” As to this issue, in its motion for summary judgment, CPS asserted it is not required to follow the statutory competitive-bidding requirements because it is exempt from those requirements, and, even if not exempt, the undisputed evidence shows the contract complies not only with Texas Local Government Code Chapter 271 but also with CPS’s internal procurement policies.

STANDARD OF REVIEW

We review an order granting a traditional motion for 'summary judgment de novo. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005). A traditional motion for summary judgment should be granted only when the movant establishes there are no genuine issues of material fact and the movant is entitled to judgment as a matter of law on the grounds expressly set forth in the motion. Tex.R. Civ. P. 166a(c); Browning v. Prostok, 165 S.W.3d 336, 344 (Tex.2005). When parties file cross-motions for summary judgment on overlapping issues and the trial court grants one motion and denies the other, we review the summary judgment evidence supporting both motions and determine all questions presented and preserved. See FM Props. Operating Co. v. City of Austin, 22 S.W.3d 868, 872 (Tex.2000). We “should render the judgment that the trial court should have rendered.” Id.

*592 IS THE CONTRACT VOID?

The parties’ contract was executed in August 2004. At that time, subchapter H of Local Government Code Chapter 271 was in effect. 3 In its motion for summary judgment, Casey argued that CPS violated subchapter H by, after selecting the design-build method of delivery for the project, failing to execute a design-build contract because it did not contract with a “single entity” or “offeror” (i e., only Casey) that had exclusive responsibility for the project. Instead, according to Casey, CPS improperly contracted with more than one entity, one of which was not an “offeror” (ie., Wheelabrator). Casey asserts Wheelabrator is not an “offeror” as that word is used in section 271.119 because it did not submit any of the required responses to the request for qualifications or the request for preliminary proposals during the competitive bidding process.

Free access — add to your briefcase to read the full text and ask questions with AI

the City of San Antonio, Texas, Acting Through the City Public Service Board of San Antonio, Texas v. Casey Industrial, Inc., 381 S.W.3d 589, 2012 Tex. App. LEXIS 6293, 2012 WL 3104429 (Tex. Ct. App. 2012).

381 S.W.3d 589 (the City of San Antonio, Texas, Acting Through the City Public Service Board of San Antonio, Texas v. Casey Industrial, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of San Antonio v. Casey Industrial, Inc.
Court of Appeals of Texas, 2014