Patton, Chief Justice.

Defendant-appellant, city of Cleveland, appeals the trial court’s ruling granting the motion of plaintiff-appellee, city of Richmond Heights, for summary judgment and denying Cleveland’s motion for summary judgment.

The following facts were stipulated to by the parties. On April 16, 1982, Cleveland and Richmond Heights entered into a contract regarding the supply of water and water-related services.

On August 2,1993, a Cleveland sixteen-inch water main broke at 507 Richmond Road located in Richmond Heights, causing water to flow from the break into the pavement and the right of way of Richmond Road. Cleveland was first notified of the water main break at 12:23 p.m. A worker was dispatched to investigate and reported back to Cleveland’s radio room at 12:57 p.m. A pipe repair crew arrived on the job site at 1:15 p.m. and shut down the sixteen-inch main. At 8:15 p.m. Cleveland’s dispatcher notified Richmond Heights via fax that the repairs to the water system were completed and that Richmond Heights should see that the right of way was secured and repaired.

In order to repair the water main break Cleveland excavated an area that measured seven feet by seventeen feet. Between August 3 and 10, 1993, repairs were performed to the affected area of Richmond Rd., which cost Richmond Heights $39,174. On September 13, 1993, Richmond Heights submitted an *380 invoice to the Cleveland Division of Water and demanded payment for $39,174. Cleveland refused to pay the invoice based on Section 13.01 of the contract.

Richmond Heights prayed for the following judgment against Cleveland: (a) $39,174 for restoring Richmond Rd. to its previous condition before the water main leak, (b) a declaration that Section 7.03 obligates Cleveland in the instant case and in the future to reimburse Richmond Heights when Richmond Heights restores to previous condition the easements and streets after repair of a water main break, and (c) a declaration that Section 13.01 does not prevent Richmond Heights in the instant case or in future cases from being reimbursed for restoring to previous condition the easements and streets after repair of a water main break.

The trial court granted judgment in favor of Richmond Heights in the amount of $39,174 plus interest. The trial court entered a declaratory judgment in favor of Richmond Heights stating that Section 7.03 of the agreement obligated Cleveland in the instant case and in the future to reimburse Richmond Heights when Richmond Heights restores to previous condition the easements and streets after repair of a water main break. The trial court also declared that Section 13.01 does not prevent Richmond Heights in the instant case or in future cases from being reimbursed for restoring to previous condition the easements and streets after repair of a Cleveland water main break.

Cleveland’s sole assignment of error states:

“The trial court erred in granting summary judgment to Richmond Heights and in denying summary judgment to Cleveland where the governing provisions of the parties’ water service agreement barred Richmond Heights’ claim for reimbursement of all expenses incurred following a water main break as a matter of law.”

Cleveland maintains that the trial court erred when it granted Richmond Heights’ motion for summary judgment and denied its motion for summary judgment because the governing provisions of the water service agreement barred Richmond Heights’ claim for reimbursement of all expenses incurred following a water main break as a matter of law. Specifically, Cleveland asserts that Section 13.01 prohibits claims for damages to the affected area caused by the flow of water that arose before Cleveland had notice of the leak and a reasonable period of time to cure the leak. Cleveland also claims that the trial court misapplied Section 7.03.

Generally, courts surmise that the intent of the parties to a contract resides in the language they select to place in the agreement. Shifrin v. Forest City Ent., Inc. (1992), 64 Ohio St.3d 635, 638, 597 N.E.2d 499, 501; Kelly v. Med. Life Ins. Co. (1987), 31 Ohio St.3d 130, 31 OBR 289, 509 N.E.2d 411. When *381 terms in a contract are unambiguous, courts mil not in effect create a new contract by finding an intent not expressed in the clear language employed by the parties. Shifrin, supra; Alexander v. Buckeye Pipe Line Co. (1978), 53 Ohio St.2d 241, 246, 7 O.O.3d 403, 406, 374 N.E.2d 146, 150. The Supreme Court of Ohio set forth a test for determining whether contract terms are ambiguous in Alexander, at paragraph two of the syllabus, which states: “Common words appearing in a written instrument will be given their ordinary meaning unless manifest absurdity results, or unless some other meaning is clearly evidenced from the fact or overall contents of the instruments.”

The sections in dispute state:

“Article 7, Right to Use Streets, Water Mains and Equipment
* * *
“7.03 The surface easements and streets shall be restored to previous condition (after laying, extending, repairing and maintaining water mains) by MUNICIPALITY [Richmond Heights] at PURVEYOR’S [Cleveland’s] expense unless otherwise agreed to in writing by MUNICIPALITY and PURVEYOR.”
“Article 13, Damage to System and Release of Liability
“13.01 MUNICIPALITY [Richmond Heights] agrees to make no claim against PURVEYOR [Cleveland] on account of any break or leak in any water main, or fire hydrant in any public street, highway or easement which claim arises before PURVEYOR [Cleveland] has notice of such leak and before PURVEYOR [Cleveland] has had a reasonable period of time to act after such notice is received to cure any such condition.”

Richmond Heights claims that Section 7.03 means that Cleveland is responsible to reimburse it the costs of placing the street in its previous condition after repairing the water main leak. Richmond Heights also asserts that Section 13.01, which covers claims for damages, does not preclude the reimbursement agreed upon in Section 7.03.

Cleveland argues that under Section 7.03, it is responsible only for the cost to fix the part of the road it had to excavate in order to repair the water main leak. Cleveland argues that pursuant to Section 13.01 it is not responsible to pay for the damages caused by the water main leak because it fixed the leak in a reasonable period of time after it received notice of the leak.

After a. thorough review of the entire contract we find that Section 13.01 must be read in pari materia with Section 7.03.' Section 7.03 does state that Cleveland will reimburse Richmond Heights for restoring streets to their previous condition after repairing a water main.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Liverpool v. Buckeye Water Dist.
2010 Ohio 3170 (Ohio Court of Appeals, 2010)
State v. Brown, C-080320 (4-24-2009)
2009 Ohio 1889 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
668 N.E.2d 991, 107 Ohio App. 3d 378, 1995 Ohio App. LEXIS 4817, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-richmond-heights-v-city-of-cleveland-ohioctapp-1995.