This text of 481 A.2d 180 (City of Portland v. Gemini Concerts, Inc.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Portland v. Gemini Concerts, Inc., 481 A.2d 180, 1984 Me. LEXIS 787 (Me. 1984).

Opinion

SCOLNIK, Justice.

The defendant, Gemini Concerts, Inc. (Gemini), appeals from a judgment of the Superior Court (Cumberland County) affirming a summary judgment of the District Court (Portland) entered in favor of the plaintiff, the City of Portland, on the City’s complaint for breach of contract. Gemini argues on appeal that the District Court erred in the following respects: (1) by refusing to grant an enlargement of time to remove the case to the Superior Court; (2) by entering summary judgment when there existed a genuine issue as to a material fact; and (3) by failing to make findings of fact and conclusions of law pursuant to a request under M.D.C.Civ.R. 52. The plaintiff cross-appeals from that portion of the Superior Court judgment affirming the District Court’s vacating of an earlier default judgment entered against the defendant. We deny both the appeal and the cross-appeal.

I.

On August 4, 1981, the City of Portland commenced this action alleging that the defendant breached an agreement to rent the Portland City Hall Auditorium for the production of the show “Beatlemania” during the week of February 17, 1981. The plaintiff alleged that $5,446.70 was still owing under the contract.

When the defendant failed to file an answer within the time prescribed by M.D.C. Civ.R. 12(a), a default judgment was entered. On November 4, 1981, Gemini obtained relief from that judgment and its answer and counterclaim alleging breach of contract were accepted by the District Court. Because the defendant’s counterclaim exceeded the $20,000 jurisdictional limit of the District Court, see 4 M.R.S.A. § 152(2) (Supp.1982-1983), amended by P.L.1983, ch. 275, Gemini filed a motion on January 27, 1982 for enlargement of time in which to file notice of removal to the Superior Court. When that motion was denied, the defendant dismissed its counterclaim and instead instituted a separate action in the Superior Court.

On October 25, 1982, the plaintiff filed a motion for summary judgment. After hearing, the District Court granted the motion and entered judgment in the amount of $5,446.70 plus interest and costs. The defendant moved for findings of fact and conclusions of law. The motion was denied and Gemini filed a timely notice of appeal to the Superior Court. The plaintiff cross-appealed.

The Superior Court denied both appeals and affirmed the judgment of the District Court. Both parties appeal from the Superior Court judgment.

II.

On this appeal, we review directly the action of the District Court. When the Superior Court acts as an intermediate appellate court, we review the initial adjudication and not the decision of the Superior Court. Emery v. Emery, 476 A.2d 193 at 195 n. 1 (Me.1984); Rubin v. Josephson, 478 A.2d 665 at 667 n. 2 (Me.1984); Williams v. Williams, 444 A.2d 977, 978-979 (Me.1982).

The defendant first argues that the District Court erred in denying its motion for enlargement of time within which to file *182 notice of removal to the Superior Court. We find no error.

Pursuant to M.D.C.Civ.R. 73(b), a party must file a notice of removal within the time for serving his answer to the claim asserted against him. In the present case, the complaint was served on July 20, 1981. Neither the answer, the counterclaim, nor the notice of removal were filed within the twenty days allowed by M.D.C.Civ.R. 12(a). The motion for enlargement of time within which to file notice of removal was not filed until January 27, 1982 — more than five months after the time permitted by the rules for the filing of notice of removal and nearly twelve weeks after the District Court vacated the default judgment and accepted the defendant’s answer and counterclaim.

Gemini nevertheless argues that it should have been permitted to remove the action against it. It relies on M.D.C.Civ.R. 6(b) which provides in pertinent part:

Enlargement. When by these rules or by a notice given thereunder or by order of the court an act is required or allowed to be done at or within a specified time, the court for cause shown may at any time in its discretion ... (2) upon motion made after the expiration of the specified period permit the act to be done where the failure to act was the result of excusable neglect ....

We have previously stated that the standard of “excusable neglect” is a strict one. Haskell v. Phinney, 460 A.2d 1354, 1360 (Me.1983); Estate of Everett, 460 A.2d 1026, 1029 (Me.1983); Givertz v. Maine Medical Center, 459 A.2d 548, 555 (Me.1983). The determination whether neglect in a particular case is excusable is left to the sound discretion of the motion justice. Sevigny v. City of Biddeford, 344 A.2d 34, 38 (Me.1975). His ruling will be reviewed only for abuse of discretion or error of law. Id.

The defendant alleges no special facts in support of its contention that its failure to file a motion to remove within the time prescribed by Rule 73(b) should be excused. The motion merely states (1) that the defendant has a counterclaim exceeding the jurisdictional limit of the District Court; (2) that in the interest of judicial economy, the plaintiffs complaint and the defendant’s counterclaim should be heard at the same time by the same court; and (3) that there will be no delay in removing the case to the Superior Court. The District Court did not abuse its discretion by concluding that these facts are insufficient to establish “excusable neglect” and committed no error by denying the motion.

III.

The defendant next argues that summary judgment was improper because there existed genuine issues of material fact. Gemini contends that there was a factual issue as to duress and thus whether a valid contract existed. Alternatively, it asserts that the plaintiff breached the contract by not permitting Gemini to sell tickets through the box office at City Hall in accordance with industry practice, thereby raising a factual question as to the amount owed by the defendant. 1 Both arguments are without merit.

At early common law, two classes of duress were recognized: (1) duress by unlawful imprisonment, see Bates v. Butler, 46 Me. 387 (1859); Soule v. Bonney, 37 Me. 128 (1854); and (2) duress per minas or by threats, see Flynt v. J. Waterman Co., 123 Me. 320, 122 A. 862 (1923); Knowlton v. Ross, 114 Me. 18, 95 A. 281 (1915). See generally 25 Am.Jur.2d Duress and Undue Influence §§ 3, 4, 10 (1966). Duress per minas

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Republicash, LLC v. Sanborn
Maine Superior, 2023
Pat Doe v. Rudy A. Lozano
2022 ME 33 (Supreme Judicial Court of Maine, 2022)
In re Child of Rebecca J.
2019 ME 76 (Supreme Judicial Court of Maine, 2019)
Remmes v. Mark Travel Corp.
Maine Superior, 2014
Begin v. Mark travel Corp.
Maine Superior, 2014
Bridgam v. Nadeau
Maine Superior, 2013
Cherryfield Foods v. Brown
Maine Superior, 2005
Everett J. Prescott, Inc. v. Ross
383 F. Supp. 2d 180 (D. Maine, 2005)
Piampiano v. Central Maine Power Co.
221 F. Supp. 2d 6 (D. Maine, 2002)
Weinstein v. Bonney
Maine Superior, 2001
Gregory v. City of Calais
2001 ME 82 (Supreme Judicial Court of Maine, 2001)
Wheaton Van Lines, Inc. v. Gahagan
669 A.2d 745 (Supreme Judicial Court of Maine, 1996)
State v. Tempesta
617 A.2d 566 (Supreme Judicial Court of Maine, 1992)
State v. Lemay
611 A.2d 67 (Supreme Judicial Court of Maine, 1992)
Ray v. Blue Alliance Mutual Insurance
594 A.2d 1110 (Supreme Judicial Court of Maine, 1991)
Denbow v. Harris
583 A.2d 205 (Supreme Judicial Court of Maine, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
481 A.2d 180, 1984 Me. LEXIS 787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-portland-v-gemini-concerts-inc-me-1984.