City of Phoenix v. Long

761 P.2d 133, 158 Ariz. 59, 1 Ariz. Adv. Rep. 73, 1988 Ariz. App. LEXIS 30
CourtCourt of Appeals of Arizona
DecidedFebruary 11, 1988
Docket2 CA-CV 87-0318
StatusPublished
Cited by12 cases

This text of 761 P.2d 133 (City of Phoenix v. Long) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Phoenix v. Long, 761 P.2d 133, 158 Ariz. 59, 1 Ariz. Adv. Rep. 73, 1988 Ariz. App. LEXIS 30 (Ark. Ct. App. 1988).

Opinion

OPINION

HOWARD, Presiding Judge.

This is an appeal from a summary judgment in an action for declaratory relief involving the validity of a contract commonly referred to as Effluent Option Agreement (EOA) entered into between six cities (Phoenix, Glendale, Scottsdale, Tempe, Mesa, and the town of Youngstown) and two public utilities, Arizona Public Service (APS) and Salt River Project (SRP).

This lawsuit is the culmination of a series of attacks launched by John F. Long, John F. Long Homes, Inc., and John F. Long Properties, Inc. (the Longs) against the EOA. 1 The Longs’ first challenge to the EOA took the form of a lawsuit alleging antitrust and certain other federal and state claims. That action was commenced in the federal district court in Phoenix in December 1983 against the cities, APS, SRP, and various other defendants. The federal court entered a judgment dismissing that action on November 22, 1985.

The second challenge to the EOA took place in Maricopa County Superior Court in the form of a lawsuit attacking the validity of the EOA under Arizona water law. Summary judgment was granted in favor of the utilities and cities on the water law challenge.

*61 The third attack upon the EOA occurred in September 1985, when the Longs initiated a letter-writing campaign directed at the mayors and city council members of the municipal signatories to the EOA. The Longs asserted that the EOA was void on a variety of grounds and demanded that the mayors and council members cease performing under the agreement.

In November 1985, after the mayors and council members had refused to agree to Longs’ demands, the Longs attempted to file certain counterclaims and amended counterclaims in the action in the Maricopa County Superior Court. Leave to file those pleadings was eventually denied on December 19, 1985.

In reaction to the Longs’ letter-writing campaign and the counterclaims that the Longs were then attempting to assert in the water law action, the cities filed this action for declaratory relief on November 22,1985, against the Longs. APS and SRP were joined as indispensable parties. The cities sought a declaration that the EOA was a valid contract and that the Longs were barred by the statute of limitations, laches, estoppel and/or waiver from asserting any claims challenging the validity of the EOA. The Longs filed a counterclaim asserting that the EOA was void because (1) it extended beyond the terms of the city councils which entered into the agreement; (2) it constituted an unauthorized option of municipal property; (3) in entering into the EOA the cities failed to comply with the requirements of A.R.S. § 9-402 because the EOA constitutes an unlawful delegation or surrender of municipal powers. The cities, joined by the utilities, moved for summary judgment. The Longs filed a cross-motion for summary judgment. The trial court granted summary judgment in favor of the cities, APS and SRP. The trial court failed to grant APS its request for attorney’s fees. This appeal by the Longs and cross-appeal by APS followed.

The relevant facts in this case are undisputed. In the 1950’s and 1960’s, in order to dispose of the residential sewage, the cities entered into various agreements which provided for the collection of the sewage at treatment plants located at 23rd Avenue and 91st Avenue in Phoenix. These agreements were amended in 1979 by cancelling any interest that the cities other than Phoenix had in the 23rd Avenue treatment plant.

In 1973, the cities entered into the EOA with APS and SRP. The EOA grants to the utilities four separate options, one for each of four planned reactor units at the Arizona Nuclear Power Project (Palo Verde), to purchase 35,000 acre feet of effluent per year or a total of 140,000 acre feet of effluent per year over the life of the agreement, which is 67 years. The most recent estimate of the total volume of effluent from the 91st Avenue and 23rd Avenue plants is 156,016 acre feet per year by 1985. There are no later figures contradicting this estimate and, as can be seen, there is now more effluent than the total amount optioned to the utilities.

Under the agreement, the options originally could be kept open by payment of one dollar per acre foot per year, increasing to two dollars in 1976 when construction permits were issued for Palo Verde. These sums are payable each year even though the utilities take no effluent and even though the effluent could be sold to others until needed at Palo Verde. When an option is exercised, the price of the effluent actually taken is set at 40 percent of the current price for Central Arizona Project water, but no more than $30 per acre foot nor less than $20 per acre foot. APS exercised the options for unit 1 and unit 2 in 1982, and as of 1985 the cities had received $1,880,318 under the EOA.

There are other provisions of the EOA which should be noted. Any unused options expire on December 30, 2000. The utilities are not required to use the effluent at Palo Verde but may use it at other facilities within or without the state. The cities are prohibited from constructing any new sewage treatment facilities, modifying existing contracts or entering into new contracts, if to do so would impair their ability to perform under the EOA. However, the cities may cease delivery of effluent under *62 the agreement if they have a critical need for it.

The effluent is used by Palo Verde to cool its reactors. Further treatment of the effluent for such use is necessary, but under the EOA the obligation to provide this treatment is upon the utilities and not the cities.

The effluent from the Phoenix plants not utilized by Palo Verde is discharged into the Salt River. 2 Past efforts to sell effluent have been unsuccessful, with one exception: 30,000 acre feet per year is delivered to the City of Buckeye by discharging the effluent into the Salt River.

Since entering into the EOA, the utilities have spent $290,000,000 to construct a pipeline for the delivery of effluent from the 91st Avenue treatment plant to the Palo Verde site, and to construct a waste water treatment plant to further treat the effluent so that it can be used as a coolant. Any further facts will be set forth in the body of this opinion as they relate to the various issues under review.

Appellants present the following issues: (1) Did the trial court err in concluding that the EOA lawfully binds future city councils? (2) Did the trial court err in concluding that the cities have the authority to enter into option contracts regarding municipal property? (3) Did the trial court err in concluding that the cities may sell effluent without regard to public bidding laws? (4) Did the trial court err in concluding that the EOA does not constitute an unlawful delegation or surrender of municipal powers?

CONTRACTUALLY BINDING A CITY COUNCIL FOR MORE THAN ONE YEAR

The general rule is that a contract extending beyond the term of office of the members of a public board such as the city council is, if made in good faith, ordinarily a valid contract. The rationale for the rule is that such a body is a continuously existing corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenawalt v. Sun City West Fire District
250 F. Supp. 2d 1200 (D. Arizona, 2003)
Arizona Consumers Council v. Arizona Corp. Commission
22 P.3d 905 (Court of Appeals of Arizona, 2001)
Serna v. Pima County
916 P.2d 1096 (Court of Appeals of Arizona, 1995)
Grant Simmons v. New Haven Bd. of Educ., No. Cv92 0300432s (Sep. 22, 1995)
1995 Conn. Super. Ct. 10934 (Connecticut Superior Court, 1995)
Piedmont Public Service District v. Cowart
459 S.E.2d 876 (Court of Appeals of South Carolina, 1995)
Arizona Water Co. v. City of Bisbee
836 P.2d 389 (Court of Appeals of Arizona, 1991)
City of Casa Grande v. Tucker
817 P.2d 947 (Court of Appeals of Arizona, 1991)
Arizona Public Service Co. v. Long
773 P.2d 988 (Arizona Supreme Court, 1989)
White v. Pima County
775 P.2d 1154 (Court of Appeals of Arizona, 1989)
Emergency Medical Transport, Inc. v. City of Tempe
756 P.2d 929 (Court of Appeals of Arizona, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
761 P.2d 133, 158 Ariz. 59, 1 Ariz. Adv. Rep. 73, 1988 Ariz. App. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-phoenix-v-long-arizctapp-1988.