*240 WARREN, J.

Plaintiff City of Oregon City brought this action for declaratory, injunctive and other relief, seeking to prevent further urban development of and the provision of urban services to the Country Village property, which the private party defendants seek to develop as a phased mobile home park. The city also opposed the development in defendant Clackamas County’s proceedings relating to its design review approval and appealed the county’s approval decision to LUBA. LUBA and, in turn, we affirmed the county’s decision. City of Oregon City v. Clackamas County, 96 Or App 651, 773 P2d 1343, rev den 308 Or 315 (1989). While the appeal to LUBA was pending, defendants moved to dismiss this action, on the ground that LUBA had exclusive subject matter jurisdiction under ORS 197.825(1). The trial court allowed the motion. The city appeals from the resulting judgment, and we affirm in part and reverse in part.

The principal substantive issue that the parties dispute is whether the Country Village development may proceed or receive urban services before the area is annexed to the city. In 1982, the city and the county entered into a revised urban growth management agreement, under which the city was to furnish urban facilities and services to Country Village and certain other unincorporated areas. The agreement provides that “City may require annexation prior to the provision of such urban facilities and services” and that the “provision of such services shall be preceded by annexation to the City, unless the parties specifically agree otherwise.” In 1987, the parties executed a second addendum to the agreement, providing that the

“agreement provisions which require annexation to City will require annexation * * * when this property is contiguous to the City or when the City requires annexation.”

In City of Oregon City v. Clackamas County, supra, decided after the parties filed their briefs in this appeal, we rejected the city’s contention that the agreement and the addendum required the county to make annexation of the area a condition of its design review approval. We explained:

“Assuming that the annexation provisos of the 1982 agreement, standing alone, would have required county to impose the annexation condition, city’s argument can succeed only if
*241 it is correct in contending that the second addendum leaves the provisos standing and simply makes their enforcement optional with city. We do not agree that the addendum can be read that narrowly. If the original provisos mandated annexation before services could be provided or development allowed, the second addendum modifies them substantially. It permits pre-annexation services and development until the area becomes contiguous to city or city elects to require annexation. The addendum eliminates any requirement of pre-development annexation in the underlying agreements.
* ** * *
“We are unsure whether city also argues here that the second addendum itself, independently of the annexation provisos in the 1982 agreement, contains any requirement that county make pre-development annexation a condition of its approval. If that argument is made, it is unmeritorious for the reasons that LUBA stated. There is nothing in the addendum to suggest that county must take any action to implement city’s decision to annex, let alone the very specific action that city seeks to compel.” 96 App at 655-56. (Emphasis in original.)

Most of the jurisdictional questions here also turn on the 1982 city-county agreement and the 1987 addendum. The city argues that the agreement is a “land use regulation,” that this is an action to enforce the contractual annexation requirements and that the circuit court therefore has jurisdiction under ORS 197.825(4). 1

Although the city acknowledges that the Country Village development is proceeding in accordance with county *242 land use decisions, which were or could be reviewed exclusively by LUBA, it contends that it was not limited to the “land use decisionmaking context” in exercising its contractual right to require annexation. The city notes that it requested the county “not to engage in land use decisionmaking so that the city could annex the site” and argues:

“Circuit court action was appropriate when the County refused to comply with the City’s request.
“Following design review approval by the County, circuit court action was the only avenue available to the City to prevent urban services from being provided by another service provider, since no further ‘land use decisions’ were necessary to allow the developer to develop the site.” (Emphasis city’s.)

The city seems to perceive ORS 197.825(4)(a) as an election of remedies statute, under which circuit court “enforcement” may be sought by a party after the land use decisionmaking process has yielded adverse results. We understand the statutory scheme differently. If the opposed action takes the form of or is permitted by a land use decision, the exclusive avenue of review is to LUBA and then to this court, in accordance with ORS 197.805 to ORS 197.855. ORS 197.825(4) (a) does not establish circuit court jurisdiction to render a second decision on the same subject, in the guise of enforcement.

Doughton v. Douglas County, 90 Or App 49, 750 P2d 1174 (1988), on which the city relies, is inapposite. We said there that jurisdiction arises under ORS 197.825(4) (a) if there is a “claim that, independently of [a land use] decision, the county’s plan or regulations are not being enforced.” 90 Or App at 54. (Emphasis supplied.) We also said that the purpose of ORS 197.825(4)(a) is

“[t]o enable local governments and members of the public to compel compliance with local land use legislation under circumstances where the non-compliance is not embodied in a discrete land use decision.” 90 Or App at 55. (Emphasis sup; plied.)

Here, the county did make a discrete land use decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flight Shop, Inc. v. Leading Edge Aviation, Inc.
373 P.3d 177 (Court of Appeals of Oregon, 2016)
Rogue Advocates v. Board of Commissioners
372 P.3d 587 (Court of Appeals of Oregon, 2016)
State ex rel. Moore v. City of Fairview
13 P.3d 1031 (Court of Appeals of Oregon, 2000)
Doney v. Clatsop County
921 P.2d 1346 (Court of Appeals of Oregon, 1996)
State ex rel. J.C. Reeves Corp. v. City of Portland
886 P.2d 1095 (Court of Appeals of Oregon, 1994)
STATE EX REL. REEVES CORP. v. Portland
886 P.2d 1095 (Court of Appeals of Oregon, 1994)
Clackamas County v. Marson
874 P.2d 110 (Court of Appeals of Oregon, 1994)
Campbell v. Board of County Commissioners
813 P.2d 1074 (Court of Appeals of Oregon, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
779 P.2d 172, 98 Or. App. 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-oregon-v-mill-maple-properties-inc-orctapp-1989.