City of New Richmond v. State Dept. of Natural Resources

428 N.W.2d 279, 145 Wis. 2d 535, 1988 Wisc. App. LEXIS 519
CourtCourt of Appeals of Wisconsin
DecidedJune 21, 1988
Docket88-0407, 88-0408
StatusPublished
Cited by6 cases

This text of 428 N.W.2d 279 (City of New Richmond v. State Dept. of Natural Resources) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of New Richmond v. State Dept. of Natural Resources, 428 N.W.2d 279, 145 Wis. 2d 535, 1988 Wisc. App. LEXIS 519 (Wis. Ct. App. 1988).

Opinion

MYSE, J.

The American Resource Recovery (ARR) appeals the circuit court’s decisions and orders concerning two petitions 1 filed under ch. 227, Stats., challenging various decisions of the Department of Natural Resources (DNR). Essentially, those decisions and orders rescinded an air pollution control permit issued by the DNR. 2 The circuit court ruled that because the DNR’s environmental assessment (assessment) was inadequate, 3 the DNR had failed to comply with the Wisconsin Environmental Policy Act *539 (WEPA), sec. 1.11, Stats., and that therefore the air pollution control permit must be rescinded as a matter of law. This court now concludes that the assessment was adequate and that the DNR’s decision not to prepare an EIS was reasonable.

To better understand this case, a preliminary background discussion is necessary. The ARR, under contract with St. Croix County, applied to the DNR for an air pollution control permit and a solid waste facility license. The license and permit would allow the ARR to construct, and St. Croix County to operate, a municipal solid waste incinerator. The combustion process involved in incinerating municipal waste converts the solid waste into two other forms: (1) particulates which are emitted into the air, and (2) ash which must be disposed of in a landfill. In its application, the ARR submitted a feasibility report and identified the landfill that would be used to dispose of the ash generated by the incinerator. Additional cost-related information was later submitted.

Wisconsin does not have a single, comprehensive regulatory program for municipal incinerators. Because incineration is by definition "solid waste treatment,” sec. 144.43(7r), Stats., an incinerator is subject to the regulatory controls and licensing requirements applicable to a "solid waste facility.” Section 144.43(5), Stats. The air emissions from the incinerator’s combustion process constitute "emissions from a stationary source” within the meaning of sec. 144.30(10) and (23), Stats., and are therefore subject to air pollution control permit requirements under sec. 144.391, Stats. Finally, the ash from the combustion process is solid waste under sec. 144.01(15), Stats., and can only be disposed at a facility licensed under sec. 144.44(4), Stats. Therefore, under the DNR’s program, the *540 construction and operation of an incinerator require both a solid waste facility license and an air pollution control permit, and any ash generated at the facility must be disposed at a licensed solid waste disposal site.

After receiving the ARR’s license and permit applications, the DNR issued its "Preconstruction Review,” which evaluated the projected emissions from the facility, identified applicable emission limitations, and stated its preliminary determination that the air permit application was approvable. Later, public notice and a request for comments were published in the New Richmond newspaper and sent to the mayor of New Richmond, the United States Environmental Protection Agency, and others.

In addition to this public notice, the DNR issued a draft assessment, which discussed both the solid waste license and air pollution permit applications and concluded that an EIS was not required. It solicited comments on the proposed assessment during a fifteen-day comment period. The DNR received more than a dozen comments both in support of and in opposition to the proposed incinerator. The DNR also held a public hearing in New Richmond.

The final assessment, including the decision not to prepare an EIS, was prepared before the hearing and later amended. Thereafter, the DNR approved the feasibility report and operating plan for the solid waste facility and issued the license as well as the air pollution control permit. A request for a contested case hearing on the solid waste facility approval was denied on July 22,1987. A request for a contested case hearing on the air permit was granted on July 22, 1987.

The petitions for judicial review of the cases on appeal were filed on June 12, 1987. In Case No. *541 87-CV-320, the petitioners sought review of the DNR’s assessment and its decision that an EIS was not required before the permits were issued.

The trial court ruled that the DNR had not adequately investigated the incinerator’s impact in its assessment. The court therefore ordered the department to prepare an EIS. The DNR moved for partial reconsideration, specifically focusing on the order to prepare an EIS. The DNR asserted that the appropriate remedy was remand for a determination of the need for an EIS based on an adequate assessment. The court agreed and so modified its decision and order.

In Case No. 87-CV-323, the petitioners sought judicial review of the DNR’s issuance of the air pollution control permit for the incinerator. The court granted the petitioners’ motion to vacate the ARR’s air control permit because the issuance of the permit required compliance with WEPA. The court held that its finding that the assessment was inadequate constituted noncompliance with WEPA; therefore, the air control permit was void as a matter of law.

On appeal, the ARR contends that the circuit court erred by determining that the DNR’s assessment was inadequate and by ordering the air pollution control permit vacated. The petitioners cross-appeal, challenging the trial court’s amended order requiring the preparation of a new assessment instead of an EIS. The issue now is whether the DNR complied with WEPA, sec. 1.11, by preparing an adequate record and, if so, whether its decision not to order an EIS was reasonable. We conclude that under the test articulated in WED v. PSC, 79 Wis. 2d 409, 256 N.W.2d 149 (1977) (WED III), the record prepared by the DNR is adequate and that its decision not to prepare an EIS *542 was reasonable. Accordingly, we reverse the circuit court’s decisions and orders and remand with directions to dismiss the two petitions. Because we reach this conclusion, we need not address the ARR’s other contentions.

The Wisconsin legislature has attempted to protect our environment by creating the Wisconsin Environmental Policy Act, sec. 1.11, Stats. (1971). The purpose of WEPA is to insure that agencies consider environmental impact during decision-making. See WED III, 79 Wis. 2d at 416, 256 N.W.2d at 153. WEPA, which is procedural in nature, does not control agency decision making. It simply "require[s] that agencies consider and evaluate the environmental consequences of alternatives available to them in the exercise of that discretion, and to require that they undertake that consideration in the framework sec. 1.11 provides.” Id.

WEPA requires that all state agencies prepare an EIS for "every recommendation or report on proposals for legislation and other major actions significantly affecting the quality of the human environment.” Section l.ll(2)(c), Stats.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Applegate-Bader Farm, LLC v. DOR
2021 WI 26 (Wisconsin Supreme Court, 2021)
State Ex Rel. Boehm v. Wisconsin Department of Natural Resources
497 N.W.2d 445 (Wisconsin Supreme Court, 1993)
Larsen v. Munz Corp.
482 N.W.2d 332 (Wisconsin Supreme Court, 1992)
Larsen v. MUNZ CORP.
480 N.W.2d 800 (Court of Appeals of Wisconsin, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
428 N.W.2d 279, 145 Wis. 2d 535, 1988 Wisc. App. LEXIS 519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-richmond-v-state-dept-of-natural-resources-wisctapp-1988.