City of Michigan City v. Witter, Trustee

34 N.E.2d 132, 218 Ind. 562, 135 A.L.R. 1259, 1941 Ind. LEXIS 185
CourtIndiana Supreme Court
DecidedMay 26, 1941
DocketNo. 27,522.
StatusPublished
Cited by2 cases

This text of 34 N.E.2d 132 (City of Michigan City v. Witter, Trustee) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Michigan City v. Witter, Trustee, 34 N.E.2d 132, 218 Ind. 562, 135 A.L.R. 1259, 1941 Ind. LEXIS 185 (Ind. 1941).

Opinion

Roll, J.

In December, 1934, appellant city entered into a written contract with R. C. Witter and Sons, Inc., *564 for the construction of. an interceptor sewer system in the City of Michigan City.

After completion of the work, and after payment of the agreed contract price, plus an additional amount for approved changes, said firm instituted this action to recover the further sum of $29,475.86, for extra work and materials occasioned by changes made in plans at the direction of the engineer in charge of construction.

The record discloses that soon after the contractor began work, it developed that certain changes in the plans would be necessary in order to make the sewer system work properly.

The bill of particulars, filed as an exhibit and made a part of the complaint, shows that the extras claimed by appellee consisted of cost of materials and labor in constructing extra manholes not shown on the detailed plans, cost of constructing a different type of manhole than those specified, occasioned by conditions discovered as the work progressed, changes in the size and kind of pipe, relocation of the sewer, and other changes and delays occasioned by' conditions discovered after the work was commenced, and all done at the direction of the engineer in charge of the work.

The evidence produced at the trial shows that soon after the contractor started construction of the sewer, it was discovered that the exact place of the existing sewers was not correctly located on the plans, and also the contractor discovered existing sewers not shown in the plan. These .discovered conditions made it advisable to construct extra manholes, and in certain instances where the plans specified a standard manhole, to change it to either an interceptor manhole or a combination of a standard and interceptor manhole. After the contractor had made three changes at the direction of the engineer in. charge, he, the contractor, requested a *565 meeting with the Board of Works of the City of Michigan City. Such a meeting was held, and Mr. R. C. Witter appeared before the board and made explanation of the changes already made and stated that additional changes would, in all probability, be found necessary as the work progressed and that such changes would occasion extra labor and materials. He also stated that he should be paid for whatever extras would be occasioned by the changes. One of the members of the board stated that whenever the engineer in charge of construction should determine upon changes to be made in the original plans and specifications, and such change occasioned additional work and extra material, the contractor should write a letter to Walter E. Parent, an áttorney employed by the city to conduct .the legal phases of this project, notifying him of the proposed change, and if' the contractor received no objections from the board of works, he should proceed under the direction of the engineer in charge, and the city would pay for any extras occasioned by said changes.

The contractor did write to Mr. Parent concerning the three changes already made, antedating the letters to correspond with the date the extra work was performed. Afterwards some twenty-two additional changes were made by the engineer in charge which required extra labor and materials. Each time the contractor wrote a letter to Mr. Parent covering the changes to be made and an estimate of the extra cost. No objections were received to these changes from the board of works, and the changed specifications were carried out.

Mr. Parent testified that he submitted to the board of works all of the letters received from the contractor concerning the proposed changes. After the work was completed, the sewer was accepted by the city and the *566 contract pricé paid. Appellee demanded payment of the extras but the city refused payment therefor.

Appellant, in its brief, makes no contention that the changes made and for which extra cost is claimed by the contractor were not made at the direction of the engineer in charge of the construction, and it does not contend that the verdict of the jury for $15,734.92 was excessive. While the evidence concerning the arrangement made between the contractor and the board of public works as to the changes in the plans and the payment for the extra cost is conflicting, the appellant, in effect, concedes the evidence upon that point to be sufficient to support the verdict.

Appellant’s principal contention is based upon the provisions of Section 11 of the plans and specifications, which provision reads as follows:

“Section 11. The Board reserves the right to alter or change any detail in the materials or method of construction, which will not materially increase or decrease the cost of the work, withbut any additional compensation to the Contractor. More important changes or alterations may be made by the Board, should the exigency arise and become apparent during the progress of the work, through faulty design discovered in the drawings and specifications, or should the Board deem it advisable to do so for the betterment of the work, notwithstanding that such changes or alterations may materially increase or decrease the cost of the construction; but the Contractor shall not proceed with such alterations or changes without a written order from the Board. The price to be added to or deducted from the contract amount, if agreed upon between the Board and the Contractor, shall be appended to the order; but in case the Board and Contractor cannot agree as to the price, it shall be taken as the estimated actual cost of the work ordered to be added or deducted by the Board, plus twelve and one-half per cent (12V2%) for profit and overhead, as determined by the Engineer. *567 It is expressly agreed and understood that any alterations or changes made, as provided and set out in this section, shall not in any way violate or annul any of the obligations or conditions of the contract.”

Appellant leans heavily upon the provision, “but the Contractor shall not proceed with such alterations without a written order from the Board,” and insists that this provision of the contract cannot be waived by the city and even if it be conceded that extra work and materials were furnished by the contractor at the direction of the engineer in charge and in pursuance to the arrangement hereinbefore mentioned, still appellee is not entitled to recover.

We do not think that appellant’s position can be sustained. In the case of Alsmeier v. Adams (1916), 62 Ind. App. 219, 245, 105 N. E. 1033, 109 N. E. 58, the court had under consideration a very similar question. In that case certain landowners, whose lands were affected by the construction of an interceptor sewer, instituted an action asking that the acceptance of the sewer by the board of public works and the primary assessment roll adopted thereon, be set aside as fraudulent and void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Home Owners Construction Co. v. Borough of Glen Rock
169 A.2d 129 (Supreme Court of New Jersey, 1961)
Seim v. Independent District of Monroe
17 N.W.2d 342 (South Dakota Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
34 N.E.2d 132, 218 Ind. 562, 135 A.L.R. 1259, 1941 Ind. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-michigan-city-v-witter-trustee-ind-1941.