City of Lubbock v. Corbin

942 S.W.2d 14, 1996 WL 862330
CourtCourt of Appeals of Texas
DecidedOctober 9, 1996
Docket07-94-0080-CV
StatusPublished
Cited by27 cases

This text of 942 S.W.2d 14 (City of Lubbock v. Corbin) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lubbock v. Corbin, 942 S.W.2d 14, 1996 WL 862330 (Tex. Ct. App. 1996).

Opinion

DODSON, Justice.

Plaintiff, the City of Lubbock (Lubbock) instituted an action for an injunction to enforce a Housing Standards Commission order requiring defendants Webb and Mary Helen Corbin to secure a house they were constructing and clean up the lot upon which the house was being built. The Corbins counterclaimed against Lubbock under Title 43, § 1983 of the Federal Civil Rights Act alleging due process and equal protection violations. Upon a jury verdict, the trial court rendered judgment in favor of the Corbins for $303,000.

By sixteen points of error, Lubbock asserts the trial court erred in refusing their motions for summary judgment, instructed verdict, and judgment non obstante veredicto with respect to the Corbins’ § 1983 claim; there is no evidence or factually insufficient evidence to support the jury’s finding of a § 1983 violation or the corresponding award of damages; various separate damages were improperly submitted in one issue; there is no basis for an award of attorney’s fees; the award of prejudgment interest was excessive; the trial court erred in refusing their motions for summary judgment, instructed verdict, and judgment non obstante veredicto with respect to Lubbock’s claim for injunc-tive relief because the Housing Standards Commission order for which they sought an injunction was final and not appealed by the Corbins; and finally there is no evidence to support the jury’s finding that the house was not a nuisance, or the finding is against the great weight and preponderance of the evidence.

Because we conclude the Corbins did not prove a § 1983 cause of action as a matter of law, we reverse and render that the Corbins take nothing on their § 1983 claim. We also conclude the order for which Lubbock sought an injunction was a final appealable order, was not appealed by the Corbins, and is thus binding upon them. However, as Lubbock has provided no support for its assertion that *17 it is entitled to an injunction, we affirm that portion of the trial court’s judgment denying the requests for injunctive relief.

Background

On April 17, 1986, Webb and Mary Corbin purchased a lot for their future home in Lubbock. Webb believed he could construct their house for $120,000, and the Corbins secured interim financing to build the home from David Harmon, a Lubbock banker. The bank Harmon then worked for later became a part of, and will be hereinafter referred to, as Lubbock National Bank.

The Corbins obtained their first building permit on April 18, 1986, but delayed initiation of construction until June or July of 1987, when they poured the foundation. Over the next two years, the Corbins did some work on the house themselves. They also hired several different framers to perform framing work, several bricklayers to partially brick the house, and also a subcontractor to partially complete the roof. However, the remaining work continued to progress unevenly.

On December 24, 1988, the Corbins received a letter signed by neighbors who resided near the house under construction. They expressed concern about the slow construction progress on the house, problems they had experienced with debris from the construction site, and the negative effect of the unfinished house on their property values. When Webb received the letter, he and Mary were attempting to renew their interim financing with Lubbock National Bank, but they received no response until March of 1989.

In the meantime, Max Garza, the supervisor of Lubbock’s Building Code Department, had continued to extend the Corbins’ original building permit 1 often without charging the required fee. On February 20, 1989, in eon-neetion with an additional extension, Garza imposed a construction schedule on the Cor-bin house. The construction schedule provided in relevant part:

After receiving your request for an extension of the building permit for your home located at 4109-86th, I have decided to grant an extension of 30 days. The extension will be until March 21,1989. At the end of these 30 days an inspection will be made to determine if construction work is proceeding at an acceptable pace. If work is proceeding satisfactorily the permit will be extended another 30 days. At the end of 60 days, April [21], 1989, with the next extension (at no charge) the house should be completed on the outside, i.e. all doors, windows, brick and roofing.
Should this work be completed as stated above, inspections will be made and an extension granted for the remaining 120 days of your request.

Webb presented Garza’s construction schedule letter to Harmon, and nineteen days later Harmon advised Webb that Lubbock National Bank’s loan committee would renew the credit line (which had expired) if the Corbins would pay a $1,000 pre-payment for interest points. Webb decided to obtain interim financing elsewhere, and on March 31, 1989, the Corbins transferred to City Bank, obtained a $75,000 line of credit, and used approximately $17,000 of these funds to pay off unsecured notes owed to Lubbock National Bank.

By the time the Corbins secured the loan at City Bank, the first thirty-day deadline on the building schedule had already expired. As a result, on March 31, the Building Code Department gave them an additional extension until April 21, 1989, so that they could complete the initially scheduled construction.

*18 On May 25,1989, Garza, Rob Allison (Lubbock’s Code Enforcement Administrator), and two others, met at the Corbin house. Garza, acting under the Building Code Department, placed a stop-work tag on the house because the building permit had expired due to non-compliance with the construction schedule. The tag stated that significant progress had not been made on the house, and the Building Code Department’s position was that the Corbins had not complied with the agreed construction scheduling letter.

The Corbins later received a notice from Lubbock’s Code Enforcement Department (of which Rob Allison was the supervisor) dated July 14, 1989, stating that the Corbin house was in violation of the Housing Code. 2 A condition allegedly existed on the property which would constitute a common law nuisance because the structure was open and accessible, and the letter gave the Corbins ten days to enclose the structure. They proceeded to close in the house with sheet-rock, plywood and particle board. However, because the garage doors had to be specially ordered, they were not installed until August 25,1989, and the house remained open.

The Corbins next received a notice dated August 23,1989, from the Code Enforcement Department, stating that an inspection had been made of the house on August 18, 1989. The letter provided that the property had deteriorated to the extent that it had become substandard and was of questionable habitability. A violation report, dated August 18, 1989, and allegedly attached to the notice, showed primarily that the house was structurally incomplete, open and accessible, and constituted a fire hazard.

The notice stated that a hearing would be held before the Housing Standards Commission on September 12, 1989, to ascertain whether the house was substandard and in violation of the Housing Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fred Hoffman v. Candace Moore
Court of Appeals of Texas, 2020
City of Houston v. Downstream Environmental, L.L.C.
444 S.W.3d 24 (Court of Appeals of Texas, 2014)
Gerald Allen Perry v. Gene Kroll
Court of Appeals of Texas, 2012
Bishop State Community College v. Williams
4 So. 3d 1152 (Court of Civil Appeals of Alabama, 2008)
Susan C. Lee v. City of Houston
Court of Appeals of Texas, 2006
Dallas County v. Gonzales
183 S.W.3d 94 (Court of Appeals of Texas, 2006)
Carrollton-Farmers Branch Independent School District v. JPD, Inc.
168 S.W.3d 184 (Court of Appeals of Texas, 2005)
Democracy Coalition v. City of Austin
141 S.W.3d 282 (Court of Appeals of Texas, 2004)
Colorado Department of Public Health & Environment v. Bethell
60 P.3d 779 (Colorado Court of Appeals, 2002)
San Miguel v. City of Windcrest
40 S.W.3d 104 (Court of Appeals of Texas, 2001)
Sanders v. Palunsky
36 S.W.3d 222 (Court of Appeals of Texas, 2001)
Curtis M. Pilgrim v. City of Mustang Ridge
Court of Appeals of Texas, 2000
Franklin National Bank v. Boser
972 S.W.2d 98 (Court of Appeals of Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
942 S.W.2d 14, 1996 WL 862330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lubbock-v-corbin-texapp-1996.